Kikimcon Building and Engineering Ltd v Registered Trustees Muthambi Catholic Parish & another (Commercial Case E125 of 2025) [2026] SCC 201 (KLR)
The bottom line
#What this practically means
#Executive summary
#Key legal issues
#Authority of the Claimant to represent the company in the contract
The objection that the Claimant lacked express authority was untenable; as a director named in the contract and executing it before an advocate, he had ostensible authority.
The Respondents entered into the contract describing the Claimant as a director, and he executed the contract before an advocate as representing the company. Although he did not attach a CR12 to prove his rank in the company, the Court held that a director has ostensible authority to bind the company, so the authority challenge failed.
Whether the contract period was extended by the Respondents
The Claimant failed to substantiate any agreement or conduct extending the contract beyond the agreed 16-week timeline.
It was common ground that the project overran the agreed timeline. The Claimant did not produce evidence that the Respondents received his letter, did not show payments were made after the contract term, and called none of the labourers to prove extension by conduct. The extension claim therefore failed on the burden of proof.
Proof of the level of completion of works for the claim of Kshs.630,000/-
The claim failed because the Claimant, as the engineer who did the works, could not certify his own works and produced no independent engineer's report.
Payment had been made per completed phase, and completion was disputed. As an engineer, the Claimant ought to have tendered an independent engineer's report certifying the works done and level of completion. He could not be an expert witness in his own case, so the Court could not infer the level of works and dismissed the claim.
Proof of the extra costs claimed in the counterclaim
The counterclaim failed for want of certified evidence: no report from the taking-over contractor on completion percentage or costs to conclude the project, and no witness (volunteer, foreman or labourer) was called.
The labour costs were uncertified and lifted from a handwritten book. The 2nd Respondent was not qualified to give evidence on those costs. Photographs alone could not establish completion percentage or costs without a certificate of completion or report from the engineer/contractor who took over the project.
Legal principles established
#- A director has ostensible authority to represent a company in contractual dealings.
- A party cannot provide expert evidence as to work he did himself and cannot be an expert witness in his own case.
- A court cannot determine the percentage of completion of construction works without a certificate of completion or report prepared by the engineer/contractor who took over the project.
Court orders
#- 1.The claim is dismissed
- 2.The Counterclaim is dismissed
- 3.Each party shall bear its own costs
- Jurisdiction invoked
- Small Claims Court Act (pecuniary jurisdiction raised as to the counterclaim amount)
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Kikimcon Building and Engineering Ltd v Registered Trustees Muthambi Catholic Parish & another (Commercial Case E125 of 2025) [2026] SCC 201 (KLR)", Case Analysis (2026). Not stated in the judgment. Source: https://new.kenyalaw.org/akn/ke/judgment/scc/2026/201/eng@2026-02-05
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.