Small ClaimsDismissedNot stated in the judgment· [2026] SCC 201 (KLR)

Kikimcon Building and Engineering Ltd v Registered Trustees Muthambi Catholic Parish & another (Commercial Case E125 of 2025) [2026] SCC 201 (KLR)

Small Claims Court
5 February 2026
820 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~3 min to read original · ~4 min brief

The bottom line

#

What this practically means

#

Executive summary

#
The Claimant, an engineer/company director, sued the Respondent claiming Kshs.630,000/- for unpaid services, alleging the Respondent failed to provide materials to conclude the plastering phase and terminated the contract without notice. The Respondent denied the claim, asserting instead a counterclaim of Kshs.1,033,700/-, contending the Claimant failed to complete the labour contract within the agreed 16 weeks and that plaster works had not commenced by 2/05/2024, justifying termination. The Claimant resisted the counterclaim as an afterthought and objected that its amount exceeded the court's pecuniary jurisdiction. The court framed three issues: whether the Claimant proved his case, whether the Respondent proved its counterclaim, and costs. On the claim, the court held the Claimant, as a director who executed the contract before an advocate, had ostensible authority despite not attaching a CR12. However, he failed to prove any extension of the contract timeline by the Respondents, producing no evidence that his letter was received and calling no labourers. On the Kshs.630,000/-, the court held that as the engineer who did the works, he could not be an expert witness in his own case and should have tendered an independent engineer's report certifying the level of completion; the court declined to infer completion. The claim was dismissed. The counterclaim also failed: the labour costs were uncertified and lifted from a handwritten book, the 2nd Respondent was unqualified to give evidence on costs, and no certificate of completion or report from the taking-over contractor was produced. Both claim and counterclaim were dismissed with each party bearing its own costs.

Key legal issues

#
01

Authority of the Claimant to represent the company in the contract

Holding

The objection that the Claimant lacked express authority was untenable; as a director named in the contract and executing it before an advocate, he had ostensible authority.

Reasoning

The Respondents entered into the contract describing the Claimant as a director, and he executed the contract before an advocate as representing the company. Although he did not attach a CR12 to prove his rank in the company, the Court held that a director has ostensible authority to bind the company, so the authority challenge failed.

p. 2
02

Whether the contract period was extended by the Respondents

Holding

The Claimant failed to substantiate any agreement or conduct extending the contract beyond the agreed 16-week timeline.

Reasoning

It was common ground that the project overran the agreed timeline. The Claimant did not produce evidence that the Respondents received his letter, did not show payments were made after the contract term, and called none of the labourers to prove extension by conduct. The extension claim therefore failed on the burden of proof.

p. 2
03

Proof of the level of completion of works for the claim of Kshs.630,000/-

Holding

The claim failed because the Claimant, as the engineer who did the works, could not certify his own works and produced no independent engineer's report.

Reasoning

Payment had been made per completed phase, and completion was disputed. As an engineer, the Claimant ought to have tendered an independent engineer's report certifying the works done and level of completion. He could not be an expert witness in his own case, so the Court could not infer the level of works and dismissed the claim.

p. 2
04

Proof of the extra costs claimed in the counterclaim

Holding

The counterclaim failed for want of certified evidence: no report from the taking-over contractor on completion percentage or costs to conclude the project, and no witness (volunteer, foreman or labourer) was called.

Reasoning

The labour costs were uncertified and lifted from a handwritten book. The 2nd Respondent was not qualified to give evidence on those costs. Photographs alone could not establish completion percentage or costs without a certificate of completion or report from the engineer/contractor who took over the project.

p. 3

Legal principles established

#
  • A director has ostensible authority to represent a company in contractual dealings.
  • A party cannot provide expert evidence as to work he did himself and cannot be an expert witness in his own case.
  • A court cannot determine the percentage of completion of construction works without a certificate of completion or report prepared by the engineer/contractor who took over the project.

Court orders

#
  1. 1.The claim is dismissed
  2. 2.The Counterclaim is dismissed
  3. 3.Each party shall bear its own costs
Jurisdiction invoked
Small Claims Court Act (pecuniary jurisdiction raised as to the counterclaim amount)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Kikimcon Building and Engineering Ltd v Registered Trustees Muthambi Catholic Parish & another (Commercial Case E125 of 2025) [2026] SCC 201 (KLR)", Case Analysis (2026). Not stated in the judgment. Source: https://new.kenyalaw.org/akn/ke/judgment/scc/2026/201/eng@2026-02-05

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.