Nkonge v Lee Construction Ltd (Commercial Case E008 of 2025) [2025] SCC 34 (KLR)
The bottom line
#Both sides lost: the Small Claims Court dismissed a breach of contract claim and counterclaim because neither party produced enough evidence to prove their case.
What this practically means
#Executive summary
#Key legal issues
#Whether the Claimant proved entitlement to payment for machinery and NEMA fee
Not proved; the Claimant bore the burden to show a request by the Respondent's agent, an agreement to pay for leasing machinery, or corroboration of the lease arrangement, none of which was shown
The burden in the first instance lay on the Claimant to demonstrate that payment for machinery was agreed or that part of the payment would go to a third-party lessor. There was no communication with the lessor evidencing a payment plan or lease arrangement, and the Claimant's tabulation of payments was not accepted.
Whether the Respondent proved overpayment
Not proved; continued collection of gravel after expiry showed extension by conduct, and overpayment should be pursued against the contractor who requisitioned the funds
Payments were made only upon requisition by the contractor; the Claimant did not requisition funds himself. Since the contractor was no longer employed by the Respondent, any overpayment claim lay against that person. Extension by conduct negated the overpayment claim.
Whether the alleged forgery of signatures and irregular invoicing was proved
Not proved; fraud must be strictly pleaded and proved to a standard higher than balance of probabilities
The Respondent alleged forgery of the Claimant's signatures and irregular invoicing, but the contractor accepted the invoices and made requisition without audit queries, and no claim was brought against the Claimant on that discrepancy before this suit. The higher standard of proof for fraud was not met.
Whether the Respondent proved the cost of hired replacement excavators
Not proved; an undelivered invoice and absence of a contract with the equipment supplier did not connect the hired excavators to this project
The invoice of 22/08/2023 was a demand for payment that could be made after completion of service, and it was not received or stamped by the Respondent. There was no contract between Libs and the Respondent and no communication showing the excavators were procured for this project after the Claimant held the original excavators in lien.
Legal principles established
#- Fraud must be specifically pleaded, its particulars stated on the face of the pleading, and it must be distinctly alleged and distinctly proved, not inferred from facts
- The standard of proof for allegations of fraud in civil cases is higher than a balance of probabilities
- A contract may be extended by the conduct of the parties after its stated expiry
Court orders
#- 1.The Claim is dismissed with no orders as to costs
- 2.The counterclaim is hereby dismissed with no orders as to costs
- Jurisdiction invoked
- Small Claims Court Act (claims capped at Kshs. 1,000,000; claimant forfeited claim in excess of that cap)
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Nkonge v Lee Construction Ltd (Commercial Case E008 of 2025) [2025] SCC 34 (KLR)", Case Analysis (2025). Not stated in the judgment text provided. Source: https://new.kenyalaw.org/akn/ke/judgment/scc/2025/34/eng@2025-08-07
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.