Skip to content
AI-generated case briefs sourced from Kenya Law · Not legal advice
AI-generated case brief
Case Brief · caselaw.co.ke
Small ClaimsDismissedNot stated in the judgment text provided· [2025] SCC 34 (KLR)

Nkonge v Lee Construction Ltd (Commercial Case E008 of 2025) [2025] SCC 34 (KLR)

Small Claims Court
7 August 2025
1,720 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~7 min to read original · ~4 min brief

The bottom line

#

Both sides lost: the Small Claims Court dismissed a breach of contract claim and counterclaim because neither party produced enough evidence to prove their case.

What this practically means

#

Executive summary

#
The Claimant sued in the Small Claims Court at Chuka seeking Kshs.1,000,000 (having forfeited the excess above the Small Claims Court cap) for breach of contract. He alleged the Respondent contracted him to excavate and supply gravel from parcel Kathwana/238 for the Kathwana-Makutano road at Kshs.1,280 per 16-tonne load, and claimed additional payment for machinery leasing and a NEMA fee. The Respondent filed an amended response and counterclaim seeking Kshs.421,730 as overpayment and Kshs.936,000 for loss of use of excavators allegedly held in lien by the Claimant. The parties did not dispute the contract's terms or execution. The Court found the Claimant failed to prove any agreement to pay for machinery or the NEMA fee, there being no evidence of a request by the Respondent's agent or of a lease arrangement with the lessor. On the counterclaim, the Court held that continued collection of gravel after the contract's expiry showed an extension by conduct, negating overpayment, and that any overpayment should be pursued against the contractor who requisitioned the funds. Allegations of forgery and irregular invoicing failed, fraud requiring strict proof to a standard higher than balance of probabilities, guided by Vijay Morjaria, Kinyanjui Kamau, Ndolo vs Ndolo, Christopher Ndaru Kagina and Central Bank of Kenya v Trust Bank. The claim for hired excavator costs also failed for want of evidence connecting them to this project. Both the claim and counterclaim were dismissed with no orders as to costs.

Key legal issues

#
01

Whether the Claimant proved entitlement to payment for machinery and NEMA fee

Holding

Not proved; the Claimant bore the burden to show a request by the Respondent's agent, an agreement to pay for leasing machinery, or corroboration of the lease arrangement, none of which was shown

Reasoning

The burden in the first instance lay on the Claimant to demonstrate that payment for machinery was agreed or that part of the payment would go to a third-party lessor. There was no communication with the lessor evidencing a payment plan or lease arrangement, and the Claimant's tabulation of payments was not accepted.

p. 2
02

Whether the Respondent proved overpayment

Holding

Not proved; continued collection of gravel after expiry showed extension by conduct, and overpayment should be pursued against the contractor who requisitioned the funds

Reasoning

Payments were made only upon requisition by the contractor; the Claimant did not requisition funds himself. Since the contractor was no longer employed by the Respondent, any overpayment claim lay against that person. Extension by conduct negated the overpayment claim.

p. 3
03

Whether the alleged forgery of signatures and irregular invoicing was proved

Holding

Not proved; fraud must be strictly pleaded and proved to a standard higher than balance of probabilities

Reasoning

The Respondent alleged forgery of the Claimant's signatures and irregular invoicing, but the contractor accepted the invoices and made requisition without audit queries, and no claim was brought against the Claimant on that discrepancy before this suit. The higher standard of proof for fraud was not met.

p. 3
04

Whether the Respondent proved the cost of hired replacement excavators

Holding

Not proved; an undelivered invoice and absence of a contract with the equipment supplier did not connect the hired excavators to this project

Reasoning

The invoice of 22/08/2023 was a demand for payment that could be made after completion of service, and it was not received or stamped by the Respondent. There was no contract between Libs and the Respondent and no communication showing the excavators were procured for this project after the Claimant held the original excavators in lien.

p. 5

Legal principles established

#
  • Fraud must be specifically pleaded, its particulars stated on the face of the pleading, and it must be distinctly alleged and distinctly proved, not inferred from facts
  • The standard of proof for allegations of fraud in civil cases is higher than a balance of probabilities
  • A contract may be extended by the conduct of the parties after its stated expiry

Court orders

#
  1. 1.The Claim is dismissed with no orders as to costs
  2. 2.The counterclaim is hereby dismissed with no orders as to costs

Authorities

#

Legislation

  • Small Claims Court Actjurisdictional cap (claim in excess of what the Small Claims court can award forfeited)

Cases cited (5)

  • Vijay Morjaria vs Nansingh Madhusingh Darbar & Another
    [2000] eKLR
  • Kinyanjui Kamau vs George Kamau
    [2015] eKLR
  • Ndolo vs Ndolo
    (2008) 1 KLR (G & F) 742
  • Christopher Ndaru Kagina -V- Esther Mbandi Kagina & Another
    [2016] eKLR
  • Central Bank of Kenya LTD -V- Trust Bank Ltd & 4 Others
Jurisdiction invoked
Small Claims Court Act (claims capped at Kshs. 1,000,000; claimant forfeited claim in excess of that cap)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Nkonge v Lee Construction Ltd (Commercial Case E008 of 2025) [2025] SCC 34 (KLR)", Case Analysis (2025). Not stated in the judgment text provided. Source: https://new.kenyalaw.org/akn/ke/judgment/scc/2025/34/eng@2025-08-07

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.