The bottom line

#

Kenya's Employment Court confirmed that an employer can end a fixed-term contract using a notice clause, with no bonus or salary for the remaining term.

What this practically means

#

Executive summary

#
The claimant, employed as Chief Technical Officer by the respondent under a fixed term contract running from 2nd December 2013 to 31st May 2016 with a three months' termination notice clause, was served with three months' notice on 24th October 2014 ending his employment on 31st January 2015. He sued claiming a declaration of unfair termination, salary for the unexpired term (USD 283,140.00), a Facility Commissioning Bonus of USD 62,600.00 and a Discretionary Performance Bonus of USD 31,300.00, with interest and costs. The respondent defended the suit on the basis that the termination invoked an express contractual right, that all lawful benefits were paid, and that the bonuses were conditional and discretionary. The claimant testified but the respondent called no evidence; both parties filed submissions. The court framed two issues: whether the contract was unfairly terminated, and whether the reliefs were payable. Applying the contractual notice clause and the doctrine that courts cannot rewrite contracts absent fraud, coercion, mistake or undue influence, and relying on Kenya Revenue Authority v Menginya Salim Murgani, the court held that no reason for termination was required where the employer exercised a contractual right to terminate by notice; the burden of proving unfair termination under section 47(5) of the Employment Act was not discharged and did not shift. The bonus claims failed because the Facility Commissioning Bonus was conditional on commissioning and delivery of a Taking Over Certificate which never occurred, and the Discretionary Performance Bonus required completion of the term and Remuneration Committee approval. The suit was dismissed with no order as to costs.

Key legal issues

#
01

Whether the claimant's contract was unfairly terminated

Holding

The termination was lawful because it was effected pursuant to the express three months' notice clause in the contract, and the claimant did not plead or prove any vitiating factor

Reasoning

Clause 17.1 of the contract allowed either party to terminate on three months' notice without a reason. The employer served the stipulated notice and paid the notice-period salary. Although the Employment Act requires valid reasons under section 45, that applies only where termination is for cause. The claimant did not plead mistake, fraud, coercion or undue influence to vitiate the notice clause, so the burden of proving unfair termination under section 47(5) was not discharged.

p. 4
02

Whether the claimant was entitled to salary for the unexpired term of the fixed contract

Holding

The claim was dismissed because the contract permitted premature termination by notice, which was complied with

Reasoning

The fixed term contract ending 31.5.2016 expressly allowed premature termination by three months' notice or payment in lieu. The respondent served the notice on 24.10.2014 with employment ending 31.1.2015 and paid salary for the notice period. Enforcement of the contractual termination clause, absent vitiating factors, precludes damages for the unexpired term.

p. 4
03

Whether the claimant was entitled to the Facility Commissioning Bonus and Discretionary Performance Bonus

Holding

Both bonus claims were dismissed because they were conditional on events that never occurred and were subject to the employer's discretion

Reasoning

Clause 14 made the Facility Commissioning Bonus payable only on delivery of a Taking Over Certificate after commissioning; the project never took off after local objections. The Discretionary Performance Bonus required completion of the scheduled term and approval by the Remuneration Committee, which the claimant admitted never approved it. Following Nicholas Mbuya, bonus liability is confined to the contract's terms.

p. 5

Legal principles established

#
  • A court of law cannot rewrite a contract between parties; the parties are bound by its terms unless coercion, fraud or undue influence are pleaded and proved
  • A party to a contract of service may terminate it by serving the stipulated notice without giving any reason; a reason is only required where termination is for cause
  • Bonus liability, where labour law is silent, must be construed strictly within the meaning and intent accorded by the parties under their contract

Court orders

#
  1. 1.Declaration that the contract of service was unfairly and wrongfully terminated refused
  2. 2.Claim for salary for the unexpired period between February 2015 to May 2016 dismissed
  3. 3.Claim for Facility Commissioning Bonus of USD 62,600.00 dismissed
  4. 4.Claim for Discretionary Performance Bonus of USD 31,300.00 dismissed
  5. 5.Suit dismissed with no order as to costs

Authorities

#

Legislation

  • Employment Actsection 45
  • Employment Actsection 47(5)
  • Employment Actsection 41
  • Employment Act 2007section 35(1)
  • Employment Act 2007section 36

Cases cited (7)

  • Okello v Rift Valley Railways (U) Ltd
    HCCS No. 195/2009
  • Abigael Jepkosgei Yaot v China Hanan International Co. Ltd
    [2018]eKLR
  • Elizabeth Kioko v Beyene Haire Warde & Another
    [2018]eKLR
  • National Bank of Kenya Ltd v Pipeplastic Samkolit (K) Ltd and another
    (2002) EA 503
  • Hassan Zubeidi v Patrick Mwangangi Kibaiya & another
    [2014]eKLR
  • Kenya Revenue Authority v Menginya Salim Murgani
    [2010]eKLR
  • Nicholas Mbuya & 4 others v Alice Gesare Moninda
    [2015]eKLR
Jurisdiction invoked
Employment and Labour Relations Court jurisdiction under the Employment Act, 2007 (the judgment does not cite a specific constitutional article)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Later judgments citing this (15)

#

Judgments in the corpus that rely on this one. Where the Court said how it treated the authority, that is shown.

Cite this brief

#

Cite this brief

Caselaw, "Manuel Anidos v Kinangop Wind Park Limited (In Receivership) [2019] KEELRC 891 (KLR)", Case Analysis (2019). Cause No 272 of 2015. Source: https://new.kenyalaw.org/akn/ke/judgment/keelrc/2019/891/eng@2019-09-20

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.