National Environment Management Authority & 3 others v Maraba Lwatingu Residents Association & 505 others [2020] KEELC 1602 (KLR)
The bottom line
#What this practically means
#Executive summary
#Key legal issues
#Jurisdiction of the Tribunal and the ELC
The Tribunal was competent to hear the appeal from NEMA and the ELC has appellate jurisdiction over Tribunal decisions, so the matter is properly before the court.
Section 129(1) of EMCA empowers the Tribunal to hear appeals by persons aggrieved by NEMA decisions such as the issuance of a licence. Section 130 of EMCA channels further appeals to the High Court, which must now be read as the Environment and Land Court by virtue of Article 162(2)(b) of the Constitution. Section 13(1) and 13(3) of the Environment and Land Court Act confer original and appellate jurisdiction over environmental disputes and redress for threatened environmental rights.
Whether public participation preceding the EIA licence was adequate
Public participation was not carried out effectively; the appellants established newspaper publication but not radio announcements in both official and local languages as required by Regulation 17.
Regulation 17 of the Environmental (Impact Assessment and Audit) Regulations 2003 requires publicity by posters, newspaper notices for two successive weeks and radio announcements at least once a week for two consecutive weeks in official and local languages, plus at least three public meetings. The court found the newspaper notices were proved but the radio announcements were not. Citing Ken Kasinga, failure to follow environmental protection procedures permits the inference that the right to a clean and healthy environment is under threat, and the failure also breached Article 69(1)(d).
Adequacy of mitigation measures and the Tribunal's evaluation
The court could not fault the Tribunal's finding that mitigation measures were inadequate to avert the risk of contaminating Lwatingu stream.
The Tribunal had considered the Water Quality Regulations 2006, Wetlands Regulations 2009 and Air Quality Regulations 2014 and found the mitigation measures inadequate. Dr. Oonge Zablon, who prepared the EIA report, never testified to clarify technical matters. Following West Kenya Sugar Co. Ltd v Kenya Sugar Board, technical questions of this kind are best evaluated by specialist bodies, so the court declined to disturb the Tribunal's technical findings. The project site is a wetland near the stream used for domestic, cultural and religious purposes.
Whether the restoration order and costs against the 2nd appellant were excessive
The Tribunal used its discretion judiciously; the polluter pays principle justified the restoration order and costs against the 2nd appellant who undertook the project.
Section 129(3) of EMCA empowers the Tribunal to make such orders, including costs, as it deems just. The appellants argued the orders were harsh and punitive for a donor-funded public project, but the court held the 2nd appellant undertook the project and the Tribunal's discretion was properly exercised. The polluter pays principle, as set out in Michael Kibui and Principle 16 of the Rio Declaration, places pollution prevention and restoration costs on the polluter rather than the public.
Legal principles established
#- Where the procedures for the protection of the environment, including public participation, are not followed, an assumption may be drawn that the right to a clean and healthy environment is under threat
- Principles of the Rio Declaration on Environment and Development bind Kenyan decision-makers by virtue of Article 2(5) of the Constitution
- The ELC has jurisdiction over appeals from the National Environment Tribunal and applications for redress of threatened environmental rights
Court orders
#- 1.The appeal is dismissed
- 2.No orders as to costs
- On appeal from
- National Environment Tribunal
- N.E.T Appeal Number 113 of 2013
- Jurisdiction invoked
- Article 162(2)(b) of the Constitution; Sections 130 and 13(1) and 13(3) of the Environment and Land Court Act; Section 129 of EMCA
Key timeline
#Practical implications
#Frequently asked questions
#Later judgments citing this (4)
#Judgments in the corpus that rely on this one. Where the Court said how it treated the authority, that is shown.
- Kimeu v Kenya Pipeline Company Ltd & another (Environment and Land Petition 9 of 2019 & Petition 8 & 12 of 2019 (Consolidated)) [2025] KEELC 5239 (KLR)[2025] KEELC 5239 (KLR)11 Jul 2025
- Kiagi v Kanmark Limited (Land Case E092 of 2024) [2025] KEELC 605 (KLR)[2025] KEELC 605 (KLR)14 Feb 2025
- Mutula Kilonzo Junior & Kethi D Kilonzo t/a Kilonzo & Company Advocates v Kenya Urban Roads Authority & 2 others[2023] KEELC 19108 (KLR)27 Jul 2023
- Kirimi & another v Kenafric Industries Ltd & 4 others (Petition 5 of 2017) [2022] KEELC 2568 (KLR)[2022] KEELC 2568 (KLR)27 Jun 2022applied
Cite this brief
#Cite this brief
Caselaw, "National Environment Management Authority & 3 others v Maraba Lwatingu Residents Association & 505 others [2020] KEELC 1602 (KLR)", Case Analysis (2020). ELC Appeal No. 5 of 2019 (consolidated with ELC Appeal No. 10 of 2019). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2020/1602/eng@2020-07-28