Zoa Limited v Arvind Mani & 2 other [2020] KEELC 1040 (KLR)
The bottom line
#The Environment and Land Court refused to stop construction because the developer had all approvals and the neighbour never challenged them before the proper tribunals.
What this practically means
#Executive summary
#Key legal issues
#Whether the Applicant demonstrated a prima facie case warranting an injunction against continued construction
No prima facie case was made out because the 1st Respondent had obtained all requisite approvals before resuming construction; the application was dismissed with costs.
The court noted the 1st Respondent had County approval from December 2019 and, pursuant to the consent with the Applicant, obtained NEMA and National Construction Authority approvals before continuing. Any grievance about the manner in which the approvals were granted lay before statutory tribunals, not the civil court at this stage. Commencement without permission attracted only a statutory penalty under section 57 of the Physical and Land Use Planning Act, which the court could not itself enforce. Following Deepak Harakch v Anmol Limited, an injunction was refused where statutory mechanisms were not exhausted.
Legal principles established
#- The only sanction for commencing construction without development permission is a statutory fine or imprisonment, enforceable by the authorities, not by way of civil injunction once approvals are regularised
- A party dissatisfied with grant of planning approvals and licences must first exhaust the statutory mechanisms (National Environment Tribunal and County Physical and Land Use Planning Liaison Committee) before seeking a civil injunction
Court orders
#- 1.The Applicant's Notice of Motion dated 20th April 2020 is dismissed
- 2.Costs of the application awarded to the Respondent
- Jurisdiction invoked
- Civil jurisdiction of the Environment and Land Court over disputes relating to development on land (Physical and Land Use Planning Act)
Key timeline
#Practical implications
#Frequently asked questions
#Later judgments citing this (5)
#Judgments in the corpus that rely on this one. Where the Court said how it treated the authority, that is shown.
- East Africa Tour Guides Drivers Association v Lazizi Mara Ltd & 12 others (Environment and Planning Petition E001 of 2026) [2026] KEELC 4071 (KLR)[2026] KEELC 4071 (KLR)2 Jul 2026
- Oak Valley Management Limited v County Executive Committee Member (CECM) Built Environment and Urban Planning, Nairobi City County & 5 others (Environment and Land Petition E004 of 2026) [2026] KEELC 2266 (KLR)[2026] KEELC 2266 (KLR)17 Apr 2026
- Dapash v Marriot International Inc & 4 others (Environment and Land Petition E003 of 2025) [2026] KEELC 1089 (KLR)[2026] KEELC 1089 (KLR)26 Feb 2026applied
- Jason Edward Matus & another v Summit Gehlot & another; National Environment Authority & 2 others (Interested Parties) [2021] KEELC 266 (KLR)[2021] KEELC 266 (KLR)20 Dec 2021
- Jason Edward Matus & another v Summit Gehlot & another; National Environment Authority & 2 others (Interested Parties) [2021] KEELC 266 (KLR)[2021] KEELC 266 (KLR)20 Dec 2021
Cite this brief
#Cite this brief
Caselaw, "Zoa Limited v Arvind Mani & 2 other [2020] KEELC 1040 (KLR)", Case Analysis (2020). Notice of Motion dated 20th April 2020 (suit on LR No.7158/81 v LR No.7158/447). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2020/1040/eng@2020-10-15
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.