Ringsview Apartments Limited v Vishnu Builders Company Ltd & another (Environment and Land Case Civil Suit 782 of 2014) [2023] KEELC 591 (KLR) (9 February 2023) (Judgment) Neutral citation: [2023] KEELC 591 (KLR) REPUBLIC OF KENYA IN THE ENVIRONMENT AND LAND COURT AT NAIROBI ENVIRONMENT AND LAND CASE CIVIL SUIT 782 OF 2014 SO OKONG'O, J FEBRUARY 9, 2023 BETWEEN RINGSVIEW APARTMENTS LIMITED ................................................. PLAINTIFF AND VISHNU BUILDERS COMPANY LTD .......................................... 1ST DEFENDANT VIJAY MORJARIA .......................................................................... 2ND DEFENDANT JUDGMENT 1. This suit was commenced by way of a plaint dated 17th June 2014. The plaint was amended on 17th March 2015 with leave of the court. In the amended plaint, the Plaintifi sought the following reliefs against the Defendants; a. A mandatory injunction compelling the Defendants to forthwith return the keys to the residential apartments on L.R No. 4858/11 commonly referred to as Ringsview Apartments (hereinafter referred to only as “the suit property”). b. A permanent injunction restraining the Defendants from selling, disposing of, transferring and/or accessing residential apartments on the suit property. c. A permanent injunction restraining the Defendants jointly and severally from barricading and/or dealing with or in any way interfering with the possession and quiet enjoyment of the residential apartments on the suit property. d. Kshs. 140,000,000/- from the 1st Defendant. e. Kshs. 112,150,000/- from the 2nd Defendant. f. A declaration that the leases for apartment numbers C1, A4 and B4 on the suit property were fraudulently registered through blackmail. https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 1
page 1 of 45
g. An order for cancellation of the leases registered in respect of apartment numbers C1, A4 and B4 on the suit property. h. Interest on 4 and 5 above. i. Costs and interest thereon. The Plaintifi ’s case: 2. The Plaintifi averred that by an agreement for building works dated 26th July 2011 between the Plaintifi and the 1st Defendant, the 1st Defendant agreed to construct for the Plaintifi apartments on the suit property at a contract sum of Kshs. 223,894,300.20/-. The Plaintifi averred that the construction which was to take 66 weeks was to commence on or about 27th July 2011 and be completed on 19th October 2012. 3. The Plaintifi averred that from the start, the 1st Defendant carried out the contractual works slowly and demanded the payment of the contractual sum in advance contrary to the terms of the agreement dated 26th July 2011(hereinafter referred to only as “the contract”). The Plaintifi averred that it indicated to the 1st Defendant that it was unable to advance such funds since it had not made arrangements for the same. The Plaintifi averred that the 1st Defendant thereafter introduced the 2nd Defendant to the Plaintifi as one of the potential buyers of the apartments and its business partner who could advance to the Plaintifi money that the 1st Defendant had demanded. 4. The Plaintifi averred that it accepted advances from the 2nd Defendant to enable the project to move forward and gave four (4) apartments on the suit property to the 2nd Defendant purely as a lien for the money that he had advanced to the Plaintifi. The Plaintifi averred that the money advanced to it was to be paid back to the 2nd Defendant. The Plaintifi averred that the 2nd Defendant refused to acknowledge receipt of the cash payments that were made to him as well as a sum of Kshs. 9,735,000/- that was paid to him as interest on the loan that he had advanced to the Plaintifi. 5. The Plaintifi averred that as at the time of filing this suit, the 2nd Defendant was still holding several documents relating to the construction project including titles for apartments that he obtained fraudulently and in respect of which he was claiming ownership. The Plaintifi averred that it never prepared sale agreements with respect to apartments C1, A4 and B4 on the suit property in favour of the 2nd Defendant. The Plaintifi averred that the 2nd Defendant misrepresented to the Land Registrar that he had valid sale agreements in respect of the apartments and the Land Registrar registered leases in respect thereof in his favour. The Plaintifi averred that the said leases were fraudulently registered and as such the same should be cancelled since the 2nd Defendant had not paid for the apartments. 6. The Plaintifi averred that despite the inordinate delay of over 1 year and 6 months on the part of the 1st Defendant in completing the construction of the apartments on the suit property, the Plaintifi paid to the 1st Defendant an aggregate sum of Kshs. 226,859,657/- which was over and above the agreed contractual sum of Kshs. 201,000,000/-. The Plaintifi averred that in a meeting held on 19th May 2014 between among others, the Plaintifi’s directors and the directors of the 1st Defendant, it was agreed that the main contractor would complete the construction works by 23rd May 2014 in default of which the construction contract was to stand terminated. 7. The Plaintifi averred that as at the time of filing the suit, the construction works remained incomplete and the Plaintifi consequently terminated the contract between it and the 1st Defendant on or about 31st May 2014. The Plaintifi averred that by an agreement dated 25th April 2012, the 1st Defendant undertook to pay to the Plaintifi Kshs. 10,000,000/- every month as damages for delayed completion https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 2
page 2 of 45
of the construction works from 30th March 2013 until completion of the said works. The Plaintifi averred that the 1st Defendant did not fulfil its part of this agreement. The Plaintifi averred that it was entitled to a sum of Kshs. 10,000,000/- per month from the 1st Defendant from 30th March 2013 until 31st May 2014 when the contract was terminated. 8. The Plaintifi averred that in response to the Plaintifi’s termination of the contract as aforesaid, the Defendants colluded to frustrate the project by; illegally barricading the entry into the apartments, confiscating the keys for all the apartments and continuously harassing the occupants and proprietors of the apartments by demanding payment from them. The Plaintifi averred that the 2nd Defendant had unlawfully obtained a sum of Kshs. 6,000,000/- from some of the purchasers of the apartments promising them additional features such as a swimming pool and gymnasium which payment was not remitted to the Plaintifi. The Plaintifi averred that the 2nd Defendant received a further sum of Kshs. 5,500,000/- from potential purchasers of the apartments which were also not remitted to the Plaintifi. The Plaintifi averred that the 2nd Defendant was liable to pay to the Plaintifi a total sum of Kshs. 11,500,000/- on account of the said unremitted payments received on behalf of the Plaintifi. 9. The Plaintifi averred that the 2nd Defendant unlawfully obtained the title deed for the suit property and refused to release the same to the Plaintifi unless the Plaintifi signed agreements for sale and sub-leases for apartments which the 2nd Defendant had not paid for and for which he owed the Plaintifi a sum of Kshs. 62,127,860/-. The Plaintifi averred that it signed the said sale agreements and sub-leases under compulsion. The Plaintifi averred that this action on the part of the 2nd Defendant occasioned a delay of over 7 months in charging the suit property to obtain finance a delay that caused the Plaintifi to incur a cost of Kshs. 14,000,000/- in bank interest charges for which the Plaintifi held the 2nd Defendant liable. 10. The Plaintifi averred that the 2nd Defendant owed it a sum of Kshs. 112,150,000/- made up as follows; Apartments .......Kshs.18,500,000/A9, Apartments ......Kshs. 29,000,000/A10, B4 and B6 and.....Kshs.10,500,000/Apartments B3 B5 and C1 Buyers ........Kshs. 11,500,000/C4 funds. Interest .....Kshs. 14,000,000/at Bankpaid to Vijay-Cash ......Kshs. 9,750,000/Funds Funds ..........Kshs. 8,000,000/owed Funds ............Kshs. 3,000,000/on C7 owed Swimming ......Kshs. 5,000,000/on C10 pool Legal .........Kshs. 2,900,000/built costs, and Total Kshs. 112,150,000/caveats demolished and Plaintifi averred that the 2nd Defendant had admitted being indebted to the Plaintifi. 11. The sales The Defendants’ agreementscase:12. The Defendants filed a joint statement of defence and counter-claim on 28th August 2014. The Defendants averred that after the commencement of the construction works on 27th July 2011, there were numerous delays occasioned by variation and extra works under clause 30.0 of the contract. The Defendants averred that the completion date of the contract was extended to 30th May 2014 instead of https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 3
page 3 of 45
19th October 2012 for various reasons such as; delay in the preparation of the valuation by the Quantity Surveyor, delay in the authorization of additional work in most of the areas that afiected the cash fiow, delay in payment, delay due to non-availability of lift and joinery sub-contractor on site, replacement of joinery sub-contractor, change and additional works on; parking area, shower cubicles, doorbells and hot water cylinder, major roof change, additional gypsum, shifting of base and change of specifications for the base of Block A, structural design change and additional steel. 13. The Defendants averred that the 2nd Defendant was introduced to the Plaintifi by one, Richard Maina and not by the 1st Defendant. The 2nd Defendant denied that he received a sum of Kshs. 9,735,000/from the Plaintifi as interest. The 2nd Defendant denied further that he unlawfully obtained the title deed for the suit property and demanded that the Plaintifi signs the sale agreements and transfers for apartments that he had not paid for before releasing the said title deed to the Plaintifi. The 2nd Defendant denied obtaining any documents from the Plaintifi fraudulently. 14. The Defendants averred that the delays in the commencement and completion of the construction works was as a result of the reasons given earlier and that the agreed contractual sum was varied because of the extra works and variations to the contract. The 1st Defendant denied receiving a sum of Kshs. 226,859,657/- from the Plaintifi. The 1st Defendant averred that the completion period was extended to 30th May 2014 in a meeting that was held on 16th May 2014 between the 1st Defendant and the Plaintifi’s agents. 15. The 1st Defendant averred that the Plaintifi unlawfully and without just cause terminated the contract on 31st May 2014 and took over the site without the same being handed over to it. The 1st Defendant averred that the Plaintifi failed to comply with clause 38.2 of the contract. The 1st Defendant averred that the agreement dated 25th April 2012 on the basis of which the Plaintifi had claimed a sum of Kshs. 10,000,000/- per month with efiect from 30th March 2013 for the delay in the completion of the construction works was illegal, null and void for having been obtained fraudulently through duress and coercion. The 1st Defendant averred that the said agreement was also overtaken by events through the various extensions of the completion period the last of which was up to 30th May 2014. The 1st Defendant averred further that the said agreement was punitive and that it could not override clause 43.1 of the contract. The 1st Defendant denied breaching the said agreement. 16. The 2nd Defendant denied that he obtained a sum of Kshs. 11,500,000/- by false pretence and that he was liable to the Plaintifi for the same. The 2nd Defendant denied further that he unlawfully obtained a title deed for the suit property and that he compelled the Plaintifi to sign sale agreements and sub-leases for apartments that he had not paid for. The 2nd Defendant denied owing the Plaintifi a sum of Kshs. 62,127,860/-. The 2nd Defendant also denied owing the Plaintifi a sum of Kshs.14,000,000/- allegedly incurred in bank interest occasioned by the delay that resulted from the 2nd Defendant’s refusal to release the title deed for the suit property. The 2nd Defendant denied that he owed the Plaintifi an aggregate sum of Kshs. 112,150,000/- claimed by the Plaintifi in the plaint. 17. In its counter-claim, the 1st Defendant averred that the Plaintifi breached clauses 30.0, 34.0 and 38.2 of the contract dated 26th July 2011. The 1st Defendant averred further that the Plaintifi breached the said contract by unlawfully taking over possession of the site without oficial handover. The 1st Defendant averred that as a result of the said breaches of the contract, the 1st Defendant sufiered loss and damage. The 1st Defendant averred that the Plaintifi failed to deposit the retention sum of Kshs. 21,895,218/in a joint account in the names of the Plaintifi and the 1st Defendant in accordance with clause 34.15 of the contract. The 1st Defendant averred that the Plaintifi also failed to pay a sum of Kshs. 5,300,000/due and owing to the 1st Defendant for the variation of the contract and extra works as provided for https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 4
page 4 of 45
under clause 30 of the contract. The 1st Defendant averred further that the Plaintifi failed to submit the last certificate of payment within 14 days of completion as provided for under clause 34.6 of the contract. The 1st Defendant averred that the Plaintifi had also failed to pay a sum of Kshs. 20,595,102/that was due and owing to the 1st Defendant. 18. On his part, the 2nd Defendant averred that the Plaintifi had denied him quiet and peaceful possession of apartments B3, B4, B5, B6, A4, A11, A12, C1, C9 and C11 on the suit property in breach of the sale agreements and sub-leases that he entered into with the Plaintifi. The 2nd Defendant averred that he had sufiered loss and damage as a result of the said breach. The 2nd Defendant averred in the alternative that the Plaintifi had failed to deliver possession of the said apartments as a result of which he had sufiered loss of rent that he would have earned amounting to a total of Kshs. 17,700,000/ between 30th March 2012 to 31st July 2014. The 2nd Defendant averred that he had also sufiered loss of profit from each of the apartments for which he was holding the Plaintifi liable. The 2nd Defendant averred that the Plaintifi was also liable in damages in the sum of Kshs. 4,400,000/- for failure to install solar system and intercom on the apartments. The 2nd Defendant averred further that the Plaintifi was also liable for the additional extra works done by the owners of the apartments in the sum of Kshs. 33,848,236/-. 19. In their counter-claim, the 1st and 2nd Defendants sought judgment against the Plaintifi for; 1. A mandatory injunction compelling the Plaintifi to forthwith return possession of the site to the 1st Defendant. 2. A mandatory injunction compelling the Plaintifi to give access and quiet and peaceful vacant possession of apartment numbers B3, B4, B5, B6, A4, A11, A12, C1, C9 and C11 to the 2nd Defendant. 3. A permanent injunction restraining the Plaintifi from interfering or stopping or barricading the 2nd Defendant and/or dealing in any way with apartment numbers B3, B4, B5, B6, A4, A11, A12, C1, C9 and C11 on the suit property or transferring or disposing of the said apartments. 4. An order that the sum of Kshs. 21,895,218/- held as retention money by the Plaintifi be deposited in a joint account of the advocates on record or as the court may direct within a specified time. 5. Kshs. 25,895,102/- to the 1st Defendant as claimed in paragraph 20(b) and (d) of the counterclaim. 6. Kshs. 17,700,000/-, 4,400,000/- and Kshs. 33,848,236/- to the 2nd Defendant as claimed in paragraphs 23(b), (d) and (e) of the counter-claim. 7. Damages for loss of opportunity, profit or market value for each apartment. 8. Interest at commercial rates. 9. Costs. Reply to defence and defence to counter-claim: 20. The Plaintifi filed a reply to the defence and defence to the Defendants’ counter-claim, dated 24th September 2014. In its reply to defence, the Plaintifi joined issue with the Defendants in their defence save where the Defendants had made admissions. The Plaintifi denied that it breached the contract with the 1st Defendant. In response to the 1st Defendant’s counter-claim, the Plaintifi denied the same in its entirety. The Plaintifi averred that it lawfully took over possession of the suit property upon termination of the 1st Defendant’s services. On the issue of the retention money, the Plaintifi averred https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 5
page 5 of 45
that it was its obligation to keep the retention money. On the issue extra work and variations, the Plaintifi denied that any extra work was done by the 1st Defendant. The Plaintifi averred further that there was no agreement to pay the 1st Defendant for extra work done. The Plaintifi averred that in any event there was no completion of the works in accordance with the contract. 21. With regard to the 2nd Defendant’s counter-claim, the Plaintifi averred that there were no valid agreements of sale between the Plaintifi and the 2nd Defendant in respect of apartments A4, B3, B4 and C1 and that no payments were made in respect of apartments B4, B3, B2, C1 and Block D. The Plaintifi averred further that there was no privity of contract between the Plaintifi and the 2nd Defendant or the alleged purchasers of apartments A4, A11, A12, B3, B4 and C1. The Plaintifi averred that the 2nd Defendant could not purport to represent persons who were not parties to this suit on the strength of a power of attorney held by him. 22. The Plaintifi urged the court to dismiss the Defendants’ counter-claims with costs and for judgment to be entered for the Plaintifi as prayed in the plaint. The Plaintifi ’s evidence: 23. The Plaintifi called its director, Dr. Benjamin Mbira Gikonyo (PW1) as its sole witness. PW1 stated that the 1st Defendant was a contractor engaged by the Plaintifi to put up apartments for it on the suit property while the 2nd Defendant was a businessman and a partner of the 1st Defendant. PW1 stated that the 2nd Defendant was also a buyer of apartments from the Plaintifi. PW1 adopted his witness statement filed in court together with the plaint on 17th June 2014 as part of his evidence in chief and produced documents attached to the Plaintifi’s list of documents filed in court on 14th October 2016 as PEXH.1. 24. PW1 stated that pursuant to the contract dated 26th July 2011(the contract), the 1st Defendant was to put up 30 apartments at agreed cost of Kshs. 223,894,300/-. PW1 stated that the apartments were revised to 34. He stated that the contract was to commence on 27th July 2011 and be completed by 19th October 2012. He stated that the contract was not completed as agreed resulting in extra costs. He stated that there was inordinate delay and that at a meeting held at an advocates ofice with the representatives of the 1st Defendant, it was agreed that the contract would be completed by March 2013 failure to which the 1st Defendant was to pay to the Plaintifi a sum of Kshs. 10,000,000/- per month as damages. PW1 referred the court to the letter dated 25th April 2012 at page 56 of PEXH.1. 25. PW1 stated that the 1st defendant did not complete the contract as a greed leaving the Plaintifi with no alternative but to terminate the contract through a letter dated 31st May 2014 under clause 38.1 of the contract. PW1 stated that the 1st Defendant owed the Plaintifi a sum of Kshs. 140,000,000/- for the delay in the completion of the contact at the rate of Kshs. 10,000,000/- per month from 1st April 2013 up to 31st May 2014 when the contract was terminated. 26. PW1 stated that as at the date of termination of the 1st Defendant’s contract, the Plaintifi did not owe the 1st Defendant any money for work done. PW1 stated that the Plaintifi had paid all the monies that were certified as due to the 1st Defendant. PW1 denied that the Plaintifi owed the 1st Defendant the sum of Kshs. 21,895,218 claimed by the 1st Defendant in the counter-claim. PW1 stated that the retention money was to be used to correct the defects. PW1 stated that since the 1st Defendant’s services were terminated; the retention money was used to correct the defects in the apartments. PW1 stated that the project was completed by a difierent contractor 3 months later after the termination of the 1st Defendant’s contract. https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 6
page 6 of 45
27. PW1 stated that after the Plaintifi had obtained several bids from potential contractors for the project, one of the Plaintifi’s directors Lucy Maina told him that she knew of someone who was interested in purchasing the apartments that the Plaintifi had planned to put up with whom the Plaintifi could partner in the project. PW1 stated that Lucy Maina thereafter introduced the 2nd Defendant to the Plaintifi. He stated that at a meeting held with the 2nd Defendant, the 2nd Defendant told them that he knew the 1st Defendant and that he had dealt with it and that it was capable of delivering quality work. PW1 stated that the 1st Defendant was one of the bidders but it was not the lowest bidder. PW1 stated that the 2nd Defendant assured them that he could negotiate with the 1st Defendant to lower its bid to match the lowest bid. PW1 stated that in the course of working with them, they learnt that the 1st Defendant and the 2nd Defendant were partners and that they were working together on other projects. 28. PW1 stated that the 2nd Defendant insisted on the 1st Defendant getting the contract because the 1st Defendant owed him some money which he intended to recover from the payments made to the 1st Defendant under the contract. PW1 stated that the Plaintifi’s claim against the 2nd Defendant was in respect of 8 apartments that he was to purchase from the Plaintifi. PW1 stated that the 2nd Defendant was not the purchaser of all the 8 apartments. He stated that some of those apartments were purchased by the 2nd Defendant’s relatives and friends. He stated that the 2nd Defendant purchased 2 apartments namely, apartment B5 and apartment B6. He stated that apartment A12 was purchased by the 2nd Defendant’s relative, Hitesh Morjaria and apartment B3 by his other relatives Hitesh and Payal Tharkar. He stated that apartment A11 was purchased by Mr. and Mrs. Ashok Shangani. He stated that it was only these apartments A11, B3, B5, B6 and A12 that were in dispute. He stated that the other three apartments were paid for and the Plaintifi executed the necessary agreements for sale and other documents of title. PW1 stated that during the construction, the 2nd Defendant introduced several changes to these apartments in dispute that increased the costs and prices of the apartments. The changes were in areas such as bathrooms and kitchen. PW1 stated that the Plaintifi and the 2nd Defendant signed separate documents in relation to these apartments that refiected these changes. The Plaintifi stated that the 2nd Defendant executed these documents before an advocate after which he took with him all the copies in the pretext that he was going to have them stamped. PW1 stated that the 2nd Defendant never returned the documents. He stated that all the changes in these apartments were costed. He stated that the extra cost for apartment A12 was Kshs. 6,000,000/-, for apartment B6 was Kshs. 6,000,000/-, for apartment B5 was Kshs. 6,000,000/-, for apartment A11 was Kshs. 5,500,000/and for apartment B3 was Kshs. 14,500,000/- which was its full price. He stated that the Plaintifi did not receive any payment for apartment B3. He stated that the 2nd Defendant told the Plaintifi that he would pay the purchase price to the 1st Defendant for the construction materials. PW1 stated that the payments made by the 2nd Defendant could not be accounted for during the costings done by the architect and the quantity surveyor. 29. PW1 stated that the 1st Defendant did not have money to start the construction and that the 2nd Defendant ofiered to deposit Kshs. 6,000,000/- in the Plaintifi’s account to be released to the contractor. He stated that the 2nd Defendant claimed this amount back with interest. He stated that the Plaintifi paid back to the 2nd Defendant a total sum of Kshs. 9,750,000/- towards this loan. PW1 stated that the Plaintifi’s incurred other costs attributable to the 2nd Defendant. He stated that the 2nd Defendant registered a caveat against the title of the suit property that caused a delay in the bank releasing to the plaintifi the money that the Plaintifi had borrowed from the said bank. PW1 stated that in the processes, the Plaintifi incurred losses in the form of monthly interest of Kshs. 2,000,000/-. PW1 stated that the Plaintifi was claiming Kshs. 14,000,000/- from the 2nd Defendant for this loss. PW1 stated that the 2nd Defendant insisted that the Plaintifi constructs a swimming pool on the suit https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 7
page 7 of 45
property and later on changed his mind that the swimming pool be demolished. He stated that on each occasion, the 2nd Defendant threatened to sue the Plaintifi. PW1 stated that the Plaintifi spent Kshs. 5,000,000/- to construct and demolish the said swimming pool which amount the Plaintifi was claiming from the 2nd Defendant. 30. PW1 stated further that through a conspiracy between the 2nd Defendant and his advocate, the 2nd Defendant managed to obtain a title deed for the suit property on which the apartments were constructed. PW1 stated that the 2nd Defendant used the said title deed to blackmail the Plaintifi. PW2 stated that the 2nd Defendant threatened that unless the Plaintifi agreed to transfer the 8 apartments referred to earlier to him, the Plaintifi would not get the title deed back. PW1 stated that under duress following the said blackmail, the Plaintifi wrote to the 2nd Defendant’s advocate agreeing to have the 8 apartments discharged in the hope that the 2nd Defendant would pay for the same later which the 2nd Defendant never did. PW1 stated that on account of this act of blackmail, the Plaintifi incurred costs of Kshs. 4,000,000/- in legal fees and other related expenses related to the lifting of the caveats that had been registered against the title by the 2nd Defendant. PW1 stated that Block D was not part of the original plan by the Plaintifi. He stated that when the Plaintifi decided to put up Block D, the Plaintifi borrowed Kshs. 18,000,000/- for construction. PW1 stated that the 2nd Defendant promised to pay to the Plaintifi the said sum of Kshs. 18,000,000/- after which he would use his own monies to complete the construction of the said Block D and to purchase the whole block. PW1 stated that the 2nd Defendant wrote to the Plaintifi’s bankers through two law firms undertaking to pay Kshs. 43.5 Million which undertaking was rejected by the bank for the reasons that the terms were unacceptable and secondly that the two law firms were unknown to the bank. PW1 stated that no monies were paid to the bank by the 2nd Defendant or his said lawyers whose undertakings were rejected. 31. PW1 stated that while they were negotiating over this Block D in the ofice of J.G.Wathigo & Co. Advocates, Mr. Wathigo asked PW1 to sign on the last page of an agreement so that when funds became available, he would just finalize the agreement without the necessity of PW1 being asked to go back to his ofice. PW1 stated that he later learnt that the 2nd Defendant went back to Mr. Wathigo’s ofice and took the last page of the agreement that PW1 had signed, put the agreement together and brought the same to court in support of his claim to the 6 apartments in Block D which he never paid for. PW1 stated that in addition to the apartments mentioned earlier, the 2nd Defendant had also lodged a claim against the Plaintifi in respect of other apartments some of which were sold to non-existent people who did not make any payment to the Plaintifi. PW1 stated that he reported these claims to the Police. PW1 urged the court to enter judgment for the Plaintifi as prayed in the amended plaint. 32. With regard to the Defendants’ counter-claims, PW1 stated that the same were based on fraudulent documentation and urged the court to reject the same. PW1 stated that apart from the apartments he had mentioned earlier, the Plaintifi did not deal with the 2nd Defendant in respect of any other apartment. 33. On cross examination, PW1 stated that the Plaintifi had been partially paid for the 8 apartments in dispute between it and the 2nd Defendant. He stated that the Plaintifi was paid in full for 3 of the apartments, paid partially for 4 of the apartments and not paid at all for 1 apartment. PW1 stated that the Plaintifi signed the leases for the 8 apartments under duress. PW1 stated that the 2nd Defendant was one of the purchasers of the Plaintifi’s apartments. He stated that the 2nd Defendant also brought other purchasers. He stated that some of the apartments were in the name of the 2nd Defendant while others were in the names of third parties. PW1 stated that the Plaintifi had sued the 2nd Defendant in respect of all the apartments because the 2nd Defendant claimed to have the power to act for the other purchasers. He stated that he signed documents such as leases in respect of the apartments on behalf of https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 8
page 8 of 45
the Plaintifi. He stated that he was not aware that some of the leases had been registered. He stated that some of the leases were fraudulent. He stated that although he wrote letters acknowledging receipt of payment for the apartments, some of the letters were written at the request of the 2nd Defendant and were issued on the understanding that the 2nd Defendant would make payment which he never did. He stated that the Plaintifi wrote the letters before receiving the payment. 34. PW1 stated that after the commencement of construction, there were variations that were documented. PW1 admitted that the Plaintifi had not mentioned the variations in its amended plaint. He stated that he mentioned the variations in his witness statement. He stated that the Plaintifi did not have written instructions from the 2nd Defendant to carry out the variations. He stated that the instructions from the 2nd Defendant were verbal. He stated that the changes were efiected, costs incurred and paid for. He stated that he did not have any document containing the variations. He stated that the documents were with the 2nd Defendant who refused to release the same. PW1 stated that there were extra costs paid to the 1st Defendant and that the certificates were issued in respect thereof and paid. He stated that the Plaintifi paid the contractor in accordance with the terms of the contract. He stated that there were payments made over and above the contract sum. PW1 stated that the caveat that had been placed by the 2nd Defendant against the title of the suit property costed the Plaintifi Kshs. 2,000,000/- per month. He stated that the costs consisted of the interest on the money that had not been released to the Plaintifi by the bank. He stated that he did not have a bank statement to support this claim. 35. PW1 reiterated that the 2nd Defendant threatened to file a suit if the Plaintifi failed to build a swimming pool. He stated that a similar threat from the 2nd Defendant led to the demolition of the said pool. He stated that both threats were verbal. He stated that he spent Kshs. 5,000,000/- on the swimming pool which figure was given to the Plaintifi by the contractor. He stated that the Plaintifi spent Kshs. 4,000,000/- to lift the caveat but had no supporting documentation. 36. PW1 stated that with regard to Block D, the Plaintifi signed only the last pages of the contracts. He stated that the 2nd Defendant took the contracts and added the other pages. He stated that the 2nd Defendant added even non-existent apartments. He stated that he saw the documents for the first time when the same were filed in court by the 2nd Defendant. He stated that the documents were forgeries and that he reported the same to the Police. He stated that he signed the documents in the ofice of J.G. Wathigo advocate an old friend of the 2nd Defendant. He stated that it was the said advocate who told him to sign the last pages of the contracts. PW1 stated that the Plaintifi had an agreement with the 2nd Defendant in respect of Block D but the 2nd Defendant never made the necessary payment. He stated that the 2nd Defendant had come to court to claim what he never paid for. PW1 stated that the Plaintifi did not release the retention money. He stated that the Plaintifi was authorised to utilise the same to cure the defects in the apartments. He stated that the Plaintifi did not pay the sum of Kshs. 4,300,000/- for the variations. He stated that the same was not certified by the architect. He stated that the Plaintifi paid for all the certificates that were received from the architect. In re-examination, PW1 stated that the Defendants had not given the details of any certificate issued by the architect and not paid by the Plaintifi. 37. PW1 was recalled and gave further evidence in chief and was further cross-examined and re-examined. In his further evidence, PW1 adopted his further witness statement as his further evidence in chief. On further cross-examination, PW1 stated that he first met James Wathigo advocate in 2011 when he was acting for the Plaintifi’s partners in the project Mr. & Mrs. Wangethi Mwangi who owned the suit property. He stated that at the material time, the said project partners wanted to transfer the suit property to the development company. He denied that James Wathigo was engaged as the https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 9
page 9 of 45
project advocate. He stated that James Wathigo transferred the responsibility that was given to him to another advocate. PW1 stated that James Wathigo gave an undertaking but the same was rejected by the bank. He stated that he was not aware that James Wathigo was to be paid his fees in kind in the form of an apartment. He stated that James Wathigo was not a party to the suit and that he had not particularised acts of fraud or wrong doing alleged against him. PW1 stated that the Plaintifi had not lodged any complaint against James Wathigo and that no proceedings had been brought against him by the Plaintifi. PW1 stated further that the Plaintifi had lodged a complaint against the 2nd Defendant with the Police but the 2nd Defendant had not been charged. 38. In further re-examination, PW1 stated that James Wathigo was never engaged as an advocate for the Plaintifi. He stated that James Wathigo was an advocate for Mr. and Mrs. Wangethi who were the original owners of the suit property. He stated that it was pursuant to the agreement dated 16th December 2013 that James Wathigo gave an undertaking to the bank which was rejected because he was not in their panel of advocates. PW1 stated that the bank did not receive any payment under the said undertaking. He stated that Mr. and Mrs. Wangethi were still shareholders of the Plaintifi. He stated that the advocates for the project were Mulondo, Oundo, Muriuki & Co. Advocates. PW1 stated that the Plaintifi did not sell apartment B2 to James Wathigo neither did it ofier the apartment to him for sale. The Defendant’s evidence: 39. The Defendants called 3 witnesses. The first witness was James Watune Wathigo (DW1). DW1 told the court that he was an advocate of the High Court of Kenya practising in the name and style of J.G.Wathigo & Co. Advocates. DW1 adopted his witness statement dated 30th January 2020 as his evidence in chief and produced the documents attached to the statement as DEXH. 1 and DEXH.2. On cross-examination, DW1 stated that he was acting for Mr. and Mrs. Wangethi who were directors and shareholders of the Plaintifi and that his role was to advise them on legal issues relating to the apartments project. He stated that his role continued after the suit property was transferred to the Plaintifi. He stated that apartment B2 was given to him by the Plaintifi in settlement of his fees. He stated that he never raised a fee note. He stated that he had a letter from the directors and shareholders of the Plaintifi in which they acknowledged that he had rendered legal services and that he would be paid in kind with the said apartment B2. He stated that his payment was agreed upon in the course of the project. 40. DW1 stated that the suit property was for a single unit dwelling and that it was necessary to change the user to multi-dwelling units. He stated that Mr. Kakad advocate was an expert in change of user and with the concurrence of his clients, he gave the task of change of user of the suit property to Mr. Kakad. DW1 stated that in the course of the project, apartment B2 was referred to as B4 and that the two were one and the same. He stated that apartment B2 that was given to him in settlement of his fees was during numbering given number B4. DW1 stated that he sold the said apartment B2 to the 2nd Defendant at Kshs. 13,500,000/- and that the 2nd Defendant paid him the said amount. DW1 stated that the agreement dated 16th December 2013 was signed before him. He stated that the 2nd Defendant put money on Block D. He stated that the agreement was not fully performed. 41. On re-examination, DW1 stated that in acting for the Wangethis, he was also an advocate for the Plaintifi since the Wangethis were shareholders and directors of the Plaintifi. He reiterated that apartment B2 was given to him for his fees. He stated that the Plaintifi had not sued him over the apartment and that the Plaintifi had confirmed through a letter dated 2nd November 2011 witnessed by him (DW1) that apartment B2 had been sold to the 2nd Defendant and paid for in full. DW1 stated that the Plaintifis had not raised any claim in respect of apartment B2 in their plaint. https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 10
page 10 of 45
42. The Defendants’ next witness was Bhimji Mawji Rabadia(DW2). DW2 told the court that he was a contractor and that he was carrying out business as Vishnu Builders Company Limited (the 1st Defendant). DW2 adopted his witness statement dated 27th August 2014 as his evidence in chief and produced the documents attached to his afidavit sworn on 10th July 2014 as exhibits(DEXH.3). 43. On cross-examination, DW2 confirmed that the Plaintifi and the 1st Defendant entered into the agreement dated 26th July 2011(the contract). He also confirmed the terms of the agreement. He stated that after the commencement of the work, the whole design of the building was changed. He stated that the Plaintifi was being given architectural drawings in bits and pieces. He stated that the Plaintifi and the 1st Defendant did not enter into a new agreement with regard to these changes. He stated that the 1st Defendant was not paid the whole agreed contract sum of Kshs. 223,894,300.20. He stated that the certificates No. 21 and No. 22 that were issued to the 1st Defendant by the architect were not paid by the Plaintifi. DW2 stated that the architect was yet to issue the 1st Defendant with the final certificate. He stated that one of the certificates was dated 5th July 2013 and it was for a sum of Kshs. 9,217,266.02(See page 281 of DEXH.3). He stated that the certificate was sent to the Plaintifi on the same date and it was not settled. He stated that the other certificate was dated 12th September 2013 and it was for Kshs. 11,056,746.87(See page 267 of DEXH.3). He stated that the certificate was also delivered to the Plaintifi and was not settled. He stated that in addition to the 1st Defendant delivering these certificates to the Plaintifi, the architect was also sending the same directly to the Plaintifi by e-mail. He stated that the 1st Defendant had counter-claimed against the Plaintifi for these unpaid certificates, the retention money and the costs of the extra works. DW2 stated that the Plaintifi’s contract was not terminated as neither the architect nor the project manager wrote to the Plaintifi on the issue. He stated that the handover of the project was supposed to be on 31st May 2014 and that before that the Plaintifi was locked out of the suit property. He stated that the original plan was for 4 fioors and that the Plaintifi added a 5th fioor on all the blocks. He stated that it took time to obtain approval for this additional fioor and this caused delay in the works and the architect gave the 1st Defendant extension of time. He stated that the Plaintifi was not involved and that the 1st Defendant was taking directions from the project consultants. He stated that the 1st Defendant did not have a contract with the Plaintifi for these additional works. He stated that it was the consultant/project manager who was giving the 1st Defendant directions on these extra works which led to extra costs. He stated that the Plaintifi was involved in the changes and paid part of the extra costs. He stated that the parties used to discuss the delays at the site meetings and that the 1st Defendant had agreed to pay to the Plaintifi damages at the rate of Kshs. 10,000,000/- per month for the delay. He stated that after that agreement, more work was added as a result of which the architect gave the 1st Defendant extra time. He stated that the 1st Defendant had undertaken to finish the works by March 2013 which deadline the 1st Defendant did not meet. DW2 stated that the architect certified a total sum of Kshs. 227,067,659.19. He stated that the 1st Defendant was paid the said amount less 10% retention sum. He stated that he received the whole amount from the Plaintifi save that the 1st Defendant was not issued with the final certificate. He stated that the 1st Defendant was locked out of the suit property before completing the work. He stated that in the circumstances, the 1st Defendant was unable to quantify the final work done. He stated that the 1st Defendant constructed a 5 fioor building together with Attic fioor. He stated that it was only Block D that he had not completed. He stated that the other blocks had been completed. He stated that he followed the agreed channel for lodging complaints over non-payment. He stated that the 1st Defendant was supposed to be paid the retention fees after 6 months upon repair of defects if any. He stated that they had not gone for site inspection since the 1st Defendant was locked out of the suit property. He stated that the 1st Defendant would not have known if there were any defects to be https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 11
page 11 of 45
repaired. He stated that there was not much work left by the time the 1st Defendant was locked out of the suit property. 44. In re-examination, DW2 stated that the contract was only for Blocks A, B and C up to the 4th Floor and attic. He stated that another Block D was added and additional fioor. He stated that the cost of the contract had to vary and that clause 30 of the contract provided for variations. He stated that the project consultants were; the architect, the engineer and the quantity surveyor who were all engaged by the Plaintifi and as such were giving instructions on behalf of the Plaintifi. He stated that the delay of the work was due to additional works, a delay on the part of plumbers and those who were dealing with electrical and joinery works who were also engaged by the Plaintifi. He stated that the 1st Defendant wrote on 12th April 2012 asking for extension in which letter he gave reasons for the delay. He stated that the extension was granted by the architect. He stated that the 1st Defendant asked for extension of time from time to time whenever there was a delay and the same was granted by the architect. He stated that the 1st Defendant could not have been granted extension if it was at fault. He stated that the letter dated 25th April 2012(See page 56, PEXH.1) by the Plaintifi regarding payment of Kshs. 10,000,000/per month for delay was written before the 1st Defendant was granted extension of time. DW2 stated that there were also delays in payment by the Plaintifi. He stated that for each certificate issued by the architect 10% was withheld as retention sum. He stated that the building constructed by the 1st Defendant was fully occupied and that the 1st Defendant did not receive a notice from the architect regarding any defect in the building neither had he seen evidence of any repairs that were carried out by the Plaintifi. DW2 stated that Plaintifi did not receive a termination notice and was not paid for all the work done. 45. The Defendants last witness was the 2nd Defendant, Vijay Morjaria(DW3). The 2nd Defendant told the court that he was a businessman. He adopted his witness statement filed on 19th June 2017 as his evidence in chief and produced the documents attached to the Defendants’ bundle of documents filed in court on 22nd March 2017 as DEXH.4. DW3 also produced the documents attached to his afidavit sworn on 9th July 2014 and filed on 10th July 2014 as DEXH.5. 46. On cross-examination, DW3 told the court that he was an investor in the property sector and had also ventured into construction as at the time of giving evidence. He denied that he was a partner in the 1st Defendant. He stated that he came to know the 1st Defendant through Mr. Maina who was a father to Ms. Lucie Maina who was one of the directors of the Plaintifi. He stated that it was Ms. Lucie Maina who introduced him to Dr. Gikonyo(PW1). He stated that Dr.Gikonyo and Ms. Lucie Maina were directors of the Plaintifi. DW3 stated that he had an interest in the project the two were involved in as he wanted to purchase an apartment. He stated that when Ms.Lucie Maina (Ms.Maina) and PW1 approached him they wanted him to be a partner in the project. He stated that he did not have funds at the time. He stated that he told them that the only way he could help was to purchase some apartments ofi-plan. He stated that the two also asked him if he knew of a good contractor. He stated that he had worked with the 1st Defendant before and introduced it to them. He stated that he was not a party to the contract between the Plaintifi and the 1st Defendant. He stated that he also assisted PW1 and Ms. Maina with money. He stated that the apartments were purchased by him and other people and that he paid a deposit. He stated that they purchased apartments B5, A10 and A9 whose numbers later changed to B6, A11 and A12 respectively. He stated that the purchase price was Kshs.10,000,000/-, 10,500,000/- and Kshs. 11,000,000/- respectively. DW3 stated that they paid a total deposit of Kshs. 3,500,000/- through RTGS. 47. He stated that apartment B5 belonged to him, apartment A10 to Hitesh Morjaria and apartment A9 to Ashok Shangani. He stated that they paid the balance of the purchase price in full in instalments. https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 12
page 12 of 45
DW3 referred the court to the bundle of cheques at pages 57 to 84 of DEXH.4. He stated that the said cheques were for the payments that they made for the 3 apartments and the other apartments. He stated that apart from the 3 apartments, they also purchased apartment B4 which became B5 on 27th December 2011 at Kshs. 9,000,000/-. The apartment was purchased by him. He stated that they also purchased apartment B3 in the names of Mitesh Tharkar and Payal Tharkar on 3rd May 2013 at Kshs. 14,500,000/-. DW3 referred the court to the agreement at page 106 of DEXH.5. He stated that apartment B3 did not change its number. DW3 stated that apartments B3 and B5 are similar. DW3 stated that he purchased another apartment namely; apartment No. B2 that later changed to B4 from James Wathigo. He stated that the apartment was given to James Wathigo as his legal fees by the Plaintifi. He stated that the apartment was not registered in the name of James Wathigo. He stated that James Wathigo sold the apartment to him and the Plaintifi prepared a lease in his favour. DW3 referred the court to the agreement dated 2nd November 2011 between him and Mr. James Wathigo. DW3 stated that he was not aware if James Wathigo had entered into an agreement with the Plaintifi in respect of this apartment. He stated that at that moment he was very familiar with the project and knew what he was purchasing. He stated that the reason why apartment B2 changed to B4 was because Mr. and Mrs.Maina who were the original owners of the suit property wanted apartment B2 and at the request of PW1, he did not mind taking apartment B4. He stated that the numbers of the other apartments changed because of the additional fioor that was added. He stated that due to the changes in numbering, the apartments that were earlier purchased as B5, A10 and A9 changed to B6, A11 and A12 respectively. He stated that apartment B4 which he had purchased earlier became B5. He stated that this apartment B4 that changed to B5 had nothing to do with apartment B2 which he surrendered and got another apartment known as B4. DW3 stated that overall, the apartments they purchased were B5, A10, A9, B4, B2 and B3 which later changed to B6, A11, A12, B5 and B4 respectively. He stated that apartment B3 was not given a new number. He stated that the current numbers for the apartments purchased by them were B6, A11, A12, B5, B4 and B3. DW3 stated that they paid for these apartments in full. He stated that Mr. Shah purchased apartments C1 and A4 at a total purchase price of Kshs. 28,000,000/-. He stated that there was an outstanding payment of Kshs. 2,500,000/- to be made by him and that the two apartments were not yet registered in the name of Mr. Shah. He stated that the total payment that they were supposed to make for all the apartments that they purchased save for the one purchased from James Wathigo was Kshs. 83,000,000/- of which they paid Kshs. 80,500,000/leaving a balance of Kshs. 2,500,000/- payable by Mr.Shah mentioned above. He stated that all the payments were made by RTGS, cheques and interest on loan that he gave to the Plaintifi. DW3 stated that he advanced several loans to the Plaintifi and that the Plaintifi acknowledged receipt of the same. DW3 referred the court to the documents at pages 1, 2, 3, and 5 of DEXH. 4. DW3 stated that it was a term of the said loans that the Plaintifi was to pay to him a sum of Kshs. 600,000/- per month as damages if the loan was not paid in 3 months. He stated that he was given post-dated cheques by the Plaintifi and a letter addressed to the bank to pay him Kshs. 6,000,000/-. DW3 further referred the court to the documents at pages 6 and 11 of DEXH. 4. DW3 stated that the Plaintifi resolved to borrow from him Kshs. 26,000,000/- and ofiered personal guarantees and a number of apartments as security. He stated that on the strength of these securities, he extended to the Plaintifi a further loan of Kshs. 21,000,000/-. He stated that when he introduced to the Plaintifi a buyer for apartments C7 and C9 he was ofiered a commission of Kshs. 1,500,000/- and when he introduced a buyer for apartment C10 he was to be given a commission of Kshs. 500,000/-. He stated that when he introduced buyers for apartments C1 and A4, he was promised additional sum of Kshs. 1,500,000/-. He stated that all these build up to the sum of Kshs. 80,500,000/- that he had mentioned earlier as having been paid. DW3 referred the court to a letter at page 24 of DEXH.4 addressed to the bank to pay him Kshs. 1,000,000/which was monthly interest that was due to him of the loan of Kshs. 21,000,000/- that he advanced to the Plaintifi. He stated that he was given many such letters together with post-dated cheques. In this https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 13
page 13 of 45
regard, DW3 referred the court to the documents at pages 85 to 89 of DEXH.4. He stated that at page 33 of DEXH. 4 is a letter by the Plaintifi to the efiect that he had paid for apartments B6, A11 and A12 in full. DW3 stated that at page 36 of DEXH.4 is a letter that was instructing him to collect some money to reimburse himself. He stated that a certificate of payment had been issued in favour of the 1st Defendant but the Plaintifi had no money. He stated that he paid the 1st Defendant Kshs. 2,000,000/and was asked to recover the amount from the 1st Defendant when it would ultimately be paid by the Plaintifi. He stated that there was also a commission of Kshs. 1,500,000/- that he was asked to collect himself. DW3 stated that the third parties to whom he made payments were not complaining. DW3 stated that he had not made any claim in respect of Block D. 48. In re-examination, DW3 stated that all the apartments in his counter-claim were paid for save for apartments C1 and A4 in respect of which there was an outstanding sum of Kshs. 2,500,000/-. He stated that he was ready and willing to pay the said amount to the Plaintifi. He stated that of the 8 apartments in dispute, 5 were already registered in their names. He stated that apartments C1, A4 and B4 were not registered in their names because they were not discharged. He stated that he was not asking for what he had not paid for from the Plaintifi. 49. After the close of evidence, the parties made closing submissions in writing. The Plaintifis’ submissions: 50. The Plaintifi filed its submissions dated 1st April 2022. The Plaintifi submitted that the 1st Defendant wanted payment in advance contrary to the terms of the contract and introduced the 2nd Defendant to the Plaintifi who advanced to the 1st Defendant a sum of Kshs. 9,735,000/- together with interest to enable the 1st Defendant commence work. The Plaintifi submitted that it paid back to the 2nd Defendant the said sum of Kshs. 9,735,000/- together with interest. The Plaintifi submitted that in order to secure the repayment of the money advanced to the 1st Defendant by the 2nd Defendant, the Plaintifi gave the 2nd Defendant apartments to hold as lien pending the repayment of the said money. The Plaintifi submitted that the 2nd Defendant held on to the said apartments and claimed that the same were owned by him. 51. The Plaintifi submitted that it did not execute any agreement for sale or lease in favour of the 2nd Defendant and its associates in respect of apartments C1, A4 and B4. The Plaintifi submitted that the leases registered in favour of the 2nd Defendant in respect of the said apartments were fraudulent in that the apartments were either not paid for at all or were paid for in part. The Plaintifi reiterated the particulars of the 2nd Defendant’s alleged fraud pleaded in the plaint. The Plaintifi submitted that the alleged fraud was committed while the title for the suit property was moved from the firm of James Wathigo advocate to the firm of P.J.Kakad & Co. Advocates. The Plaintifi submitted that it was at this time that caveats were registered against the said title and the leases for apartments A11, A12, B5, B6, B3, C9 and C11 registered in favour of the 2nd Defendant. The Plaintifi submitted that James Wathigo acted against the interest of his clients, Mr. & Mrs. Wangethi and took no action against the unauthorized use of the title for the suit property. The Plaintifi submitted that he instead collaborated with the 2nd Defendant to defraud the Plaintifi. 52. The Plaintifi submitted that James Wathigo was not given apartment B2 as his fees and that apartments did not change numbers. The Plaintifi submitted that apartment B2 did not change to B4. The Plaintifi submitted that although the 2nd Defendant claimed to have purchased apartments worth Kshs. 172,500,000/-, the evidence of payment placed before the court shows that the 2nd Defendant paid only a sum of Kshs. 37,500,000/- leaving a balance of Kshs. 125,000,000/- due and payable to the Plaintifi. The Plaintifi submitted that with regard to Block D, a meeting was held at the ofice of James Wathigo https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 14
page 14 of 45
on 9th December 2013 at which the 2nd Defendant ofiered to purchase a number of apartments. The Plaintifi submitted that James Wathigo who claimed to be an old friend of the 2nd Defendant agreed to issue a legal undertaking from his law firm to the bankers of the Plaintifi for the payment of a sum of Kshs. 43,500,000/- to cover the costs involved in the transaction. The Plaintifi submitted that the 2nd Defendant was to pay to the Plaintifi among others a sum of Kshs. 18,000,000/- that the Plaintifi had borrowed and spent on the construction of Block D up to that point. 53. The Plaintifi submitted that subject to the issuance and acceptance of the said undertaking by James Wathigo, the Plaintifi was to undertake partial discharges of a number of apartments. The Plaintifi averred that the said sum of Kshs. 43,500,000/- was not paid since the bank rejected the undertaking by James Wathigo and refused to discharge the apartments. The Plaintifi submitted that during the said meeting of 9th December 2013, James Wathigo printed the execution pages of the sale agreements and leases for the apartments that were to be discharged and convinced the Plaintifi’s directors to sign the same. The Plaintifi submitted that no payment was made by the 2nd Defendant since the undertaking was rejected as aforesaid and the said sale agreements and leases executed in the ofice of James Wathigo were used to defraud the Plaintifi of the apartments. The Plaintifi submitted that the documents were used by the 2nd Defendant to claim apartments that he did not pay for. The Plaintifi submitted that the 2nd Defendant admitted in evidence that he did not pay for any apartment in Block D. 54. The Plaintifi submitted that as part of his blackmail, the 2nd Defendant put a caveat on the title of the suit property which stopped the development thereof until the Plaintifi and the bank discharged all the apartments that he was interested in. The Plaintifi submitted that the said caveat that caused delays in the project was in place between June 2012 to January 2013; a period of 7 months. The Plaintifi submitted that this caused it a total loss of Kshs. 14,000,000/- being the interest that it was charged at the rate of Kshs. 2,000,000/- per month. The Plaintifi referred the court to a copy of the title deed at pages 28 to 32 of the Plaintifi’s further list of documents. The Plaintifi submitted that it was entitled to judgment for this sum of Kshs. 14,000,000/-. The Plaintifi also referred the court to the letter from P.K Kakad Advocates dated 5th November 2012 at pages 26 and 27 of the Plaintifi’s further list of documents in which the said advocates made it clear that the 2nd Defendant would not release the title for the suit property until the bank gave an irrevocable undertaking to release the apartments. 55. The Plaintifi submitted that the apartments in dispute were apartments A12 purchased by Hitesh Morjaria, B6 purchased by Vijay Morjaria, B5 purchased by Vijay Morjaria, B3 purchased by Mitesh and Payal Thakkar and A12 purchased by Ashok Shangani in respect of which a total sum of Kshs. 36,000,000/- was paid leaving a total balance of Kshs. 38,000,000/-. The Plaintifi submitted that the purchasers of these apartments refused to pay the balance of the purchase price because they wanted the 1st Defendant to carry out various modifications in the apartments that were carried out by the 1st Defendant and paid for by the Plaintifi. The Plaintifi submitted that the transfer and registration of leases in respect of these apartments were obtained through theft of title and blackmail and must be reversed by the court. 56. The Plaintifi submitted that the owners of apartments A12, A11, B5 and B6 represented by the 2nd Defendant owed the Plaintifi a total sum of Kshs. 23,500,000/- while the purchaser of apartment B3 owed it Kshs. 14,500,000/-. The Plaintifi submitted further that the 2nd Defendant owed him a further sum of Kshs. 14,000,000/- on account of the caveat and interest and a sum of Kshs. 19,000,000/- being interest on the outstanding amount. The Plaintifi submitted further that the 2nd Defendant also owed the Plaintifi a sum of Kshs. 9,735,000/- being a refund of the money paid to the 2nd Defendant for a loan allegedly advanced by the 2nd Defendant to the 1st Defendant to commence work. The Plaintifi submitted that it was also entitled to a sum of Kshs. 5,000,000/- for the swimming pool that was https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 15
page 15 of 45
constructed and demolished at the instigation of the 2nd Defendant. The Plaintifi submitted that it was also entitled to legal costs in the sum of Kshs. 4,000,000/-. The Plaintifi submitted that it was also entitled to interest on the total amount claimed in the sum of Kshs. 64,000,000/- making the total amount due to it from the 2nd Defendant Kshs. 144,000,000/-. 57. The Plaintifi submitted that apartments C9 and C11 were purchased by Ramesh Thakkar who paid for the same in full. The Plaintifi submitted that it did not enter into any transaction with the persons claimed by the 2nd Defendant to have purchased apartments C1 and A4. The Plaintifi submitted that it did not also receive any payment from them. The Plaintifi submitted further that the leases purportedly issued by the Plaintifi in respect of apartments D1 and D6 were fraudulent as the two apartments did not exist. 58. With regard to its claim against the 1st Defendant, the Plaintifi submitted that the agreed contract sum was Kshs. 201,000,000/- that was later adjusted to Kshs. 223,894,300/-. The Plaintifi submitted that the Plaintifi paid to the 1st Defendant a total sum of Kshs. 227,067,659.19. The Plaintifi submitted that the contract commenced on 27th July 2011 and was to last for 66 weeks with a practical completion date of 19th October 2012. The Plaintifi submitted that the payments to the 1st Defendant were to be made against an interim certificate issued by the architect. 59. The Plaintifi submitted that due to the delay in the construction work, the 1st Defendant agreed on 24th April 2012 to complete the work by 30th March 2013 failure to which it will pay to the Plaintifi a sum of Kshs. 10,000,000/- monthly as damages until completion. The Plaintifi referred the court to the said agreement at page 56 of PEXH.1. The Plaintifi submitted that the 1st Defendant did not complete the work by 30th March 2013 and had not done so 14 months later. The Plaintifi submitted that it was entitled to a total of Kshs. 140,000,000/- from the 1st Defendant as damages for the delay. The Plaintifi submitted that it was also entitled to additional sum of Kshs. 7,000,000/- for the delay in accordance with the original contract under which it was entitled to Kshs. 500,000/- per month as delay cost. 60. The Plaintifi submitted that the 1st Defendant admitted receiving the said sum of Kshs. 227,067,659.19 which was over and above the contract sum. The Plaintifi submitted that the 1st Defendant was overpaid to the tune of Kshs. 3,000,000/- and as such no further payment was due from the Plaintifi to the 1st Defendant. The Plaintifi submitted that in addition to the said sum of Kshs. 227,067,659.19, there was a further sum of Kshs. 21,012,300/- paid to and on behalf of the 1st Defendant which were not part of the certificates issued by the architect. The Plaintifi submitted that the only certificates issued by the architect were Nos. 1 to 20. The Plaintifi submitted that certificates No. 21 and No. 22 for the main contract and No. 3 for Block D were never issued. The Plaintifi submitted that it did not owe the 1st Defendant any money. 61. The Plaintifi submitted that it had proved its claims against the Defendants. The Plaintifi submitted that it had proved that the 2nd Defendant defrauded it and that the 2nd Defendant’s claim was fraudulent. The Plaintifi submitted that the 2nd Defendant having been refunded the payment he made to the 1st Defendant to commence the construction work, he had no right to lay a claim to the apartments that were given to him to hold as lien. The Plaintifi submitted that it had cited various incidences that demonstrated the 2nd Defendant’s illegal conduct. The Plaintifi cited Black’s Law Dictionary, 9th Edition, Arthi Highway Developers Ltd. v. West End Butchery Limited & 6 Others [2015]eKLR and Rahemtullah Omar & another v. Musa Hersi Gahiye & 5 others[2014]eKLR in support of the foregoing submissions. The Plaintifi submitted that its witness was categorical that the Plaintifi was arm-twisted to sign the acknowledgments relied on by the 2nd Defendant as evidence https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 16
page 16 of 45
of payment for the apartments claimed by the 2nd Defendant. The Plaintifi submitted that the 2nd Defendant did not place before the court evidence of the alleged payments. 62. With regard to the 1st Defendant’s counter-claim, the Plaintifi submitted that its relationship with the 1st Defendant was strictly guided by the Agreement and Conditions of Contract for Building Works dated 26th July 2011(the contract). The Plaintifi submitted that the rights and obligations of the parties were set out in the contract. The Plaintifi submitted that the 1st Defendant was not entitled to the retention money. The Plaintifi submitted that the issue of retention money was to be considered after a joint inspection of the project and the issuance by the architect of the final certificate and certificate of practical completion. The Plaintifi submitted that the joint inspection of the site was not carried out and as such a certificate of practical completion was not issued. The Plaintifi submitted that the stage at which the Plaintifi was obligated to pay the retention money to the 1st Defendant had not been reached. The Plaintifi submitted that it would be unfair to require the Plaintifi to deposit the retention money in a joint account at this stage since the project was taken over and completed by another contractor. 63. With regard to the sum of Kshs. 5,300,000/- claimed by the 1st Defendant for the variations and extras, the Plaintifi submitted that under clause 30.14 of the contract, approval of the Plaintifi was required before any variation or extra work was done. The Plaintifi submitted that its approval was not sought for the variations and extras the costs of which were claimed by the 1st Defendant. The Plaintifi submitted that since the value of the extra work claimed exceeded 0.01% of the contract price, the same was not payable. In this regard, the Plaintifi referred to the e-mail dated 24th June 2014 from the architect at page 53 of DEXH.3. 64. With regard to the claim for Kshs. 20,595,102.00 by the 1st Defendant as money due and owing under the contract, the Plaintifi submitted that certificate No. 21 was yet to be prepared and that the certification sought was for Kshs. 11,816,880.53. The Plaintifi submitted that there was also valuation No. 22 for Kshs. 7,521,672.62 that was not certified for payment. The Plaintifi referred the court to page 64 of DEXH.3, pages 136 to 173 of DEXH. 3 and pages 105 to 134 of DEXH3. The Plaintifi submitted that the 1st Defendant had not made any claim in respect of certificates issued by the architect or certified valuations. The Plaintifi submitted that it was only to make payment against a certificate of payment issued by the architect and that the court had no jurisdiction to certify valuations. The Plaintifi submitted that under clause 38.5, the Plaintifi had a right to employ and pay other persons to carry out and complete the works and rectify any defects. The Plaintifi submitted that the 1st Defendant was not entitled to payment for works done by another contractor. The Plaintifi submitted that the project consultants were independent contractors and were not agents of the Plaintifi. 65. On the alleged failure to submit the last certificate of payment within 14 days from the date of completion pursuant to clause 34.6 of the contract, the Plaintifi submitted that it was not its role to issue a final certificate or any certificate for that matter. The Plaintifi submitted that clause 34.6 of the contract provided for simple interest on the delayed/unpaid certificate. The Plaintifi submitted that the 1st Defendant had not produced any certificate that was not paid by the Plaintifi for the purposes of computing interest on the delayed payment. The Plaintifi submitted that no payment was due to the 1st Defendant for the certificates issued for alleged work done in Block D. The Plaintifi submitted that the evidence adduced in court showed that the 1st Defendant did not do any work related to Block D. 66. With regard to the 2nd Defendant’s counter-claim, the Plaintifi framed a number of issues for determination. The first was whether any consideration was paid for the apartments claimed by the 2nd Defendant. On this issue, the Plaintifi submitted that the 2nd Defendant’s claim was in respect of apartments B3, B4/B2, B5, B6, A4, A11, A12, C1, C9 and C11. With regard to apartment B2 also known as B4 which the 2nd Defendant claimed to have purchased from James Gatune Wathigo advocate https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 17
page 17 of 45
to whom it was given by the Plaintifi as his legal fees, the Plaintifi submitted that no evidence was tendered showing that James Wathigo rendered any services to the Plaintifi. The Plaintifi submitted that there were no instruction notes or fee-note raised by the said advocate. The Plaintifi submitted further that there was no agreement between the Plaintifi and James Wathigo through which the apartment was given to the said advocate as his fees. The Plaintifi submitted further that there was no agreement or lease to support the transfer of the apartment by the Plaintifi to James Wathigo. 67. The Plaintifi submitted that in the agreement for sale dated 2nd November 2011 between the 2nd Defendant and James Wathigo in respect of apartment B2 at pages 90 to 93 of DEXH.4, James Wathigo sold the apartment to the 2nd Defendant at Kshs. 13,500,000/- as the beneficial owner thereof. The Plaintifi submitted that there is another agreement at pages 94 to 106 of DEXH. 4 allegedly between the Plaintifi and the 2nd Defendant over the same apartment B2 in which the Plaintifi sold the apartment to the 2nd Defendant at Kshs. 13,500,000/-. The Plaintifi submitted that this agreement did not refer at all to James Wathigo. The Plaintifi submitted that at pages 192 to 228 of DEXH.5 is another sale agreement dated 19th December 2013 and a lease over apartment B2. In this agreement the consideration is given as Kshs. 15,000,000/-. The Plaintifi submitted that these documents contradict those referred to earlier. The Plaintifi submitted that the 2nd Defendant was misleading the court on the alleged acquisition of apartment B2. The Plaintifi averred that all these contradictory documents are alleged to have been signed by the Plaintifi. The Plaintifi submitted that no evidence was placed before the court showing that the 2nd Defendant paid the purchase price for apartment B2 to James Wathigo. The Plaintifi submitted that James Wathigo failed to prove that apartment B2 was given to him by the Plaintifi. The Plaintifi submitted that in the circumstances, James Wathigo had no title in the apartment to transfer to the 2nd Defendant. In support of this submission, the Plaintifi cited Rico Kinyariro Kariuki v. Renate Wolfi & another[2018]eKLR. 68. With regard to apartment B3, the Plaintifi submitted that the sale agreement for the same was not dated and the consideration was given as Kshs. 14,500,000/-. The Plaintifi submitted that the lease in respect of this apartment is dated 3rd May 2013 in favour of Mitesh and Payal Thakkar and the consideration for the lease is given as Kshs. 14,000,000/-. The court was referred to pages 121 to 137 of DEXH. 5, page 155 of DEXH.4 and pages 107 to 120 of DEXH. 5. The Plaintifi submitted that there was also acknowledgment of payment of Kshs. 14,500,000/- at page 31 of DEXH.4. The Plaintifi submitted that no payment was received for this apartment and that the 2nd Defendant produced no evidence of payment. The Plaintifi submitted that having rejected the acknowledgment of payment, the 2nd Defendant and the registered owners of the apartment were under a duty to adduce evidence in support of the payment which they failed to do. 69. With regard to apartment B4, the Plaintifi submitted that the sale agreement is dated 27th December 2011 between the Plaintifi and Hitesh Morjaria and the consideration is given as Kshs. 9,000,000/-(See pages 26 to 39 of DEXH.5). The Plaintifi submitted that this sale agreement contradicts the evidence given by the 2nd Defendant and DW1 in which they claimed that apartment B2 was swapped with apartment B4. The Plaintifi submitted that the lease for this apartment is stamped but not registered (See pages 88 to 104 of DEXH.5). The Plaintifi submitted that no payment was received for this apartment and that the 2nd Defendant produced no evidence of payment. The Plaintifi submitted that the 2nd Defendant did not also produce evidence of payment of stamp duty that would have led to the registration of the apartment in his favour. 70. For apartments B6, A11 and A12, the Plaintifi submitted that on page 33 of DEXH.4 is an acknowledgement of receipt of payment of Kshs. 3,000,000/- from the 2nd Defendant in full and final payment for all the 3 apartments. The Plaintifi submitted that it was paid a sum of Kshs. 9,000,000/- https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 18
page 18 of 45
for apartment B6 leaving a balance of Kshs. 6,000,000/- which came about due to a change of design that was paid for by the Plaintifi. 71. With regard to apartments A4 and C1, the Plaintifi submitted that in a letter dated 16th April 2013(See page 173 of DEXH.5), the Plaintifi and the 2nd Defendant agreed on the settlement of friendly loans. The Plaintifi submitted that part of this agreement was that the Plaintifi would refund to the 2nd Defendant a sum of Kshs. 22,000,000/- if apartments A4 and C1 were not completed and transferred to the 2nd Defendant and that the loan of Kshs. 22,000,000/- from the 2nd Defendant would be converted to deposits towards the purchase of these apartments. The Plaintifi submitted that in the circumstances, no payment was made for these apartments. The Plaintifi submitted that the 2nd Defendant did not prove the existence of the said loan of Kshs. 22,000,000/-. The Plaintifi submitted that since the 2nd Defendant and the purported purchasers Nakrai Ratilalchand Shah and Niketan Ratilal Shah did not produce evidence of purchase of apartment A4 as ordered by the court on 1st July 2014, the same was sold by the Plaintifi and registered in the name of a third party on 29th April 2016. For apartment C1, the Plaintifi submitted that in the lease at pages 140 to 156 of DEXH. 5 in favour of Kankrai Ratilalchand Shah and Niketan Ratilal Shah, the consideration for the apartment is given as Kshs. 12,000,000/-. The Plaintifi submitted that no evidence of payment of the said amount was produced by the 2nd Defendant and the purported purchasers. The Plaintifi submitted that the apartment is still registered in the name of the Plaintifi and that the 2nd Defendant had no basis for claiming the apartment. 72. With regard to apartments B5, A10 and A9, the Plaintifi referred the court to the sale agreements at pages 10 to 24 of DEXH.5 and the letter of ofier at page 25 of the same exhibit in favour of Hitesh Morjaria. The Plaintifi submitted that for apartment B5, it received a sum of Kshs. 9,000,000/- leaving a balance of Kshs. 6,000,000/- due to change in design. For apartments A10 and A9, the Plaintifi submitted that the 2nd Defendant had not raised any claim in respect thereof. 73. With regard to apartment A11, the Plaintifi submitted that the lease in respect thereof was registered in favour of Hitesh Morjaria (See pages 40 to 55 of DEXH.5). The Plaintifi submitted that it received a sum of Kshs. 9,000,000/- against the agreed purchase price of Kshs. 10,000,000/-. The Plaintifi submitted that due to changes that were made to the apartments at the instance of the 2nd Defendant, the balance payable for the apartment is Kshs. 5,000,000/- due to increased costs. 74. With regard to apartment A12, the Plaintifi submitted that there is a registered lease in favour of Ashok Dhirajlal Sanghani and Sujat Ashok Sanghani and that the agreed consideration was Kshs. 10,500,000/-. The Plaintifi submitted that it received a sum of Kshs. 9,000,000/- in respect of this apartment leaving a balance of Kshs. 1,500,000/-. The Plaintifi submitted that due to change in design made on the instructions of the 2nd Defendant, the balance payable for this apartment was Kshs. 4,500,000/-. With regard to apartments C9 and C7, the Plaintifi submitted that the same were sold to Ramesh Thakkar and/or nominee on 17th January 2012 at a total consideration of Kshs. 36,000,000/(See pages 223 to 231 of DEXH.5). The Plaintifi submitted that apartment C9 is registered in the name of Ramesh Thakkar and Anila Thakkar. The Plaintifi submitted that it was paid in full for the two apartments by the purchasers thereof and it had no claim regarding the same. The Plaintifi submitted that the 2nd Defendant had no basis for his claim over apartment C9 as he had no power of attorney from the purchasers. 75. With regard to apartment C11, the Plaintifi submitted that the purchasers of this apartment had filed a separate suit against the Plaintifi and the dispute over the same was settled. The Plaintifi submitted that the 2nd Defendant had no right to lodge another claim in respect of the apartment. The Plaintifi submitted that the 2nd Defendant only had a power of attorney to act for particular purchasers and in https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 19
page 19 of 45
respect of particular apartments the particulars of which are in the documents attached to the 1st and 2nd Defendants’ defence and counter-claim. 76. The Plaintifi submitted further that in the agreement dated 16th December 2013 between the Plaintifi, the 2nd Defendant and James Wathigo for Mr. & Mrs. Wangethi(See pages 271 to 272 of DEXH.5), the parties agreed on how all the outstanding payments were to be settled. The Plaintifi submitted that it was agreed that the payment due to the Plaintifi was Kshs. 50,000,000/- of which a sum of Kshs. 43,500,000/- was to be paid to the Plaintifi on the strength of an undertaking that was to be given by J.G. Wathigo & Co. Advocates to PW1 to enable the Plaintifi to fulfil its obligations and to complete the project and Kshs. 7,000,000/- was to be deducted/recovered from the retention money due to the 1st Defendant. The Plaintifi submitted that the said agreement confirmed several facts that it had submitted on more particularly the apartments that had not been paid for and the fact that apartment B2 was not given to James Wathigo in settlement of his fees. The Plaintifi submitted that according to the said agreement, as at the date of the agreement, a total sum of Kshs. 25,500,000/- was due and payable to the Plaintifi for the apartments claimed by the 2nd Defendant herein. The Plaintifi submitted that J.G.Wathigo’s undertaking was not accepted by the bank and no further payment was made to the Plaintifi in respect of the said apartments. The Plaintifi submitted that the said professional undertaking was not enforceable as it was not acted upon by either party. The Plaintifi submitted that the undertaking was of no efiect. 77. With regard to Block D, the Plaintifi submitted that the claim in respect thereof was introduced by the 2nd Defendant in his witness statement and that the claim was abandoned by the 2nd Defendant in his defence since it was not part of his claim in the defence and counter-claim. The Plaintifi submitted that it did not execute any lease in respect of Block D and that the 2nd Defendant did not make any payment for the same. The Plaintifi submitted that the 2nd Defendant’s claim in respect of Block D had no basis having admitted that he did not make any payment in respect of Block D. 78. In conclusion, the Plaintifi submitted that it had proved its case against the Defendants and that the Defendants’ claim against it was not proved. The 1st and 2nd Defendants’ submissions: 79. In their submissions dated 4th May 2022, the Defendants framed the following issues for determination by the court; 1. Whether there was a breach of the contract dated 26th July 2011 and if so, by whom? 2. Who is the legal owner of the Apartments numbers B6, A11, A12, B2, B4, B5, B3, C1, A4, C9 and C11? 3. Whether the Plaintifi has established fraud on the Part of the 2nd Defendant. 4. Whether the Defendants are entitled to the prayers sought. 5. Who should bear the costs of the suit? Whether there was a breach of the contract dated 26th July 2011 and if so, by whom? 80. The Defendants submitted that the Plaintifi and the 1st Defendant entered into a legally binding contract dated 26th July 2011 for the construction of residential apartments for the Plaintifi, Ringsview Apartment Limited at a contractual sum of Kshs. 223,894,300.20. The Defendants submitted that the contract was for a period of 64 weeks and the date of practical completion was 19th October 2012. The Defendants submitted that amongst the terms of the contract was an obligation https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 20
page 20 of 45
on the Plaintifi/Employer to make financial arrangements to ensure payments of certificates as and when they fell due. 81. The Defendants submitted that the 1st Defendant commenced and dutifully executed its part of the contract and raised various interim certificates over the course of the project. The Defendants submitted that clause 34.5 of the contract required that once the contractor presented an interim payment certificate to the employer, the contractor was entitled to payment within fourteen days. 82. The Defendants submitted that contrary to the above provision, the Plaintifi on several occasions failed and/neglected to make good the payment for the certificates and was therefore in blatant breach of the contract. The Defendants submitted that the 1st Defendant had given a breakdown of all payments received from the Plaintifi vis-a-vis the certificates raised in the bundle of documents attached to the Replying Afidavit of Bhimji Rabadia (DEXH.3) at pages 102 to 104. The Defendants submitted that a balance of Kshs. 42,490,320.48 remained unpaid to the 1st Defendant. 83. The Defendants submitted that this breach forced the 1st Defendant to write various letters to the Plaintifi/Employer pleading with it to release the money rightfully owed to it in full and on time to enable a smooth fiow of the works. The Defendants referred the court to the letters at pages 70 and 78 of DEXH. 3 to the Project Manager and the Architect complaining of delays in payments and dishonoured cheques issued by the Plaintifi thus leading to slow progress of the works. The Defendants submitted that the Project Manager acknowledged receipt of the letter addressed to him through an email dated 29th November 2013 in which he informed all the sub-contractors and main contractor that it was in talks with the employer over the issue of payment and would advise. The Defendants submitted that instead of looking into the said issue, the Plaintifi through a letter dated 31st May 2014 opted to terminate the contract citing delays as the sole reason for termination. The Defendants submitted that the said termination was made in bad faith and without following the due process. The Defendants submitted that the delay in completion of the works was as a result of no fault of the 1st Defendant and that the same was attributable to the actions of the Plaintifi and its agents. 84. The Defendants submitted that the Plaintifi made various variations to the scope of work outlined in the Bill of Quantities specifications which significantly changed the dynamics of the contract. The Defendants submitted that the particulars of the changes were outlined in paragraph 2 of the 1st Defendant’s witness statement of Bhimji Rabadia dated 24th August 2014. The Defendants submitted that the variations included change of the structural design in all the column bases which set back the contract by 6 months, change of elevation and, addition of a swimming pool and a gym area in Block D. 85. The Defendants submitted that as a result of these changes to the original plan, there were delays in the initial phases of implementation which went for as long as 6 months in some instances. The Defendants submitted that there was need to get approvals from the then Nairobi City Council for the additional construction works particularly of the 5th fioor which took a total of 8 weeks. 86. The Defendants submitted that the Project Engineer who was an agent of the Plaintifi kept making changes to the contract thereby causing delays from the original completion period. The Defendants referred the court to the letter dated 8th December 2011 annexed to the 1st Defendant’s Replying Afidavit of Bhimji Rabadia sworn on 29th July 2014(DEXH3) that was addressed to the Plaintifi. The Defendants submitted that, in the letter, it was stated clearly that the major reasons for delays were delayed structural drawings and amendments on them, as well as delays in payment of the sums certified. The Defendants submitted that due to these changes, the 1st Defendant was issued with various extensions of time. The Defendants submitted that in the letter dated 21st June 2012 at page 100 of DEXH.3 from Achitekton Services, it was acknowledged that the delays were occasioned by the https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 21
page 21 of 45
revision of both the Architectural and Structural designs and as such, the 1st Defendant was granted an extension of time for 15 weeks up to 31st January 2013. 87. The Defendants submitted that this was further revised and an additional 17 weeks extension granted until 31st May 2013 through a letter dated 15th January 2013 at page 101 of DEXH.3. The Defendants submitted that this extension was necessitated by the modification of the design to include additional typical fioor thereby increasing the scope of work, a fact that was recognized by the Architect. The Defendants submitted that the 1st Defendant applied for a further extension of time which was granted through a letter dated 18th June 2013 at page 98 of DEXH. 3. The Defendants submitted that the completion date for Blocks A, B and C was extended to 26th July 2013 and that of Block D was extended to 30th August 2013. 88. The Defendants submitted that in addition to the foregoing, the 1st Defendant’s witness, Bhimji Rabadia (DW2) testified that the delays were also caused by certain factors beyond the control of the 1st Defendant such as bad weather conditions. The Defendants referred the court to a Clerk of Works Report by the Plaintifi at pages 17 to 19 of DEXH.3 which showed a breakdown of the total hours lost due to rainfall between the year 2011 to 2013. 89. The Defendants submitted that in exercise of caution the 1st Defendant once again applied for extension of time through a letter dated 5th June 2013 in which it explained the causes of delay and issued supporting documents. The Defendants gave among the reasons for extension loss of time due to rains and election period and addition of tiles to the walls. The Defendants submitted that the 1st Defendant also raised the issue of termination of a sub-contract agreement for the kitchen and ofice which afiected the entire joinery fittings. The Defendants submitted that the Plaintifi having been fully satisfied with these reasons, granted a time extension. 90. The Defendants submitted that the delays were also caused by the Sub- contractors nominated by the Plaintifi which had a general efiect on the whole project. The Defendants submitted that the 1st Defendant complained of these delays severally during meetings and through email correspondence. In one of the meetings held on 1st August 2013, minutesof which is part of DEXH.3, the delays were attributed to the subcontractors. The reasons for the delays were given as; Hwansung have not resumed work, aluminium subcontractor not yet on site, Lift subcontractor yet to resume mechanical installations on Block B and lack of enough scafiolding holding progress on finishes in Block A and B. The Defendants submitted that the subcontractors were reminded to work within the main contractor’s programme. The Defendants submitted that there was no doubt that the sub-contractors contributed to the delays in the completion of works and not the 1st Defendant as alleged by the Plaintifi. 91. The Defendants submitted that the Plaintifi had made a claim that the 1st Defendant owed it a sum of Kshs. 140,000,000/= as damages which was calculated at the rate of Kshs. 10,000,000 per month for the delay in completion of the project. The Defendants submitted that this claim arose from a meeting that was held on the 25th April 2012 between the 1st Defendant and the Plaintifi where it was agreed that the 1st Defendant was to complete the works by 30th March 2013, failing which damages shall accrue at Kshs. 10,000,000 per month. 92. The Defendants submitted that the Plaintifi conveniently omitted the fact that an extension of time was granted on the 18th June 2013 through which the completion period was extended from 30th March 2013 to 26th July 2013. The Defendants submitted that due to this further extension of the completion period, the conditions set on 25th April 2012 for default were overtaken by events and could not be invoked. The Defendant submitted that by granting an extension of time, the Plaintifi was satisfied https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 22
page 22 of 45
that valid reasons existed that delayed the completion of the project. The Defendants submitted that the Plaintifi waived the right to enforce the agreement of 25th April 2012. The Defendants submitted that any reference to the said agreement was therefore null and void. The Defendants referred the court to the extension of 18th June 2013 at page 284 of DEXH.3. 93. On the issue of the valuation of the works done, the Defendants submitted that clause 34 of the contract mandated the Quantity Surveyor to value the works done by the contractor including variation works within 7 days of the request and the Architect to issue a payment certificate within seven days of the date of receipt of the Quantity Surveyor’s valuation. The Defendants submitted that the 1st Defendant submitted its application for valuation of certificate number 21 on 17th March 2014 for the work done as well as extra work. This application however went unanswered prompting the 1st Defendant to make several follow ups as evidenced by correspondence at pages 60 and 61 of DEXH.3. The Defendants submitted that the 1st Defendant kept asking the Plaintifi through its consultants to issue valuation for the said certificate and additional work as late as 17th June 2014, nearly 9 weeks later. 94. The Defendants submitted that the Plaintifi’s claim that it was not liable to make payment of the sum due to the 1st Defendant since the amount claimed under certificate No. 21 had not been certified or approved by the Plaintifi was an old trick meant to deprive the contractor of the fruits of its labour. The Defendants submitted that the 1st Defendant dutifully wrote to the Plaintifi’s architect inviting him to verify the works done so as to avoid any issues of overpayment. The Defendants referred the court to the email correspondence from the Plaintifi’s said agent at pages 52 and 53 of DEXH.3 requesting for the Plaintifi’s approval for the extra works done. The Defendants submitted that it was absurd for the Plaintifi to refuse making the payment due to the 1st Defendant on account of its own misdeeds. The Defendants submitted that the Plaintifi should be held accountable for failure to approve the works, value and issue payment certificates as well as failure to pay the sums owed to the 1st Defendant. 95. The Defendants submitted that clause 30.7 of the contract required that the Plaintifi/Employer adjusts the contract price in light of variations but the Plaintifi refused and/or neglected to make adjustments to the contract price and as such the Plaintifi was in breach of the said contract. The Defendants referred the court to the letters at pages 81 and 83 of DEXH. 3 which the 1st Defendant wrote to the Plaintifi requesting that the contract sum be updated due to the additional works that they were instructed to undertake after the signing of the contract. 96. The Defendants submitted that the Plaintifi refused and/or neglected to abide by the provisions of clause 34.15 of the contract that required it to deposit in a joint interest earning bank account with the 1st Defendant the retention money and was therefore in breach of the contract. The Defendants submitted that owing to conduct of the Plaintifi, the 1st Defendant through a letter to the Plaintifi dated 7th June 2013 requested that it gives a written assurance that the 1st Defendant would be paid on time and in full (See page 43 of DEXH.3) 97. The Defendants submitted further that through a letter dated 17th June 2013, the Plaintifi gave an undertaking that the retention money would be paid on time and in full in accordance with clause 34.0 of the contract. The Defendants submitted that the retention money due to the 1st Defendant was to be released on the issuance of the certificate of practical completion. The Defendants submitted that this was impractical as the Plaintifi had already ignored and/or refused to value the works done for the purposes of the final certificate as shown above thus crippling the project’s progress. The Defendants submitted that instead of rectifying the breach, the Plaintifi went on to assign the contract to another contractor and wrongfully withheld the retention money owed to the 1st Defendant. https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 23
page 23 of 45
98. The Defendants submitted that the Plaintifi went against its undertaking and wrongfully withheld the retention money owed to the 1st Defendant while it was in breach of contract and was indebted to the 1st Defendant. The Defendants submitted that such acts by the Plaintifi were oppressive and were made in a bid to cripple the financial muscle of the 1st Defendant so as to defeat its ability to pursue legal claim against it. Who is the legal owner of apartments B6, A11, A12, B2, B4, B5, B3, C1, A4, C9 and C11? 99. Apartments originally known as B5, A10 and A9 and currently known as B6, A11 and A12. 100. The Defendants submitted that the 2nd Defendant, Vijay Morjaria in his evidence told the court of his working relationship with the directors of the Plaintifi, Ringsview Apartments Limited and explained how he was convinced to purchase apartments ofi plan and also to get his friends to purchase the apartments. The Defendants submitted that the 2nd Defendant testified that on 18th April 2011, he together with his colleague, Hitesh Morjaria entered into a sale agreement with the Plaintifi for the purchase of duplex apartments B5, A10 and A9 at a consideration of Kshs. 31,500,000/= in respect of which a deposit was paid. The Defendants referred the court to pages 10 to 25 of DEXH.5 for copies of the sale agreement and a letter of ofier. 101, The Defendants submitted that during the course of the construction, the Plaintifi caused an additional fioor to be added to the project and that this additional fioor altered the numbering of the apartments as a result of which apartment B5 changed to B6, A10 to A11 and A9 to A12. In this regard, the Defendants referred the court to the e-mail dated 12th November 2012 from Lucie Maina at page 18 of the Plaintifi’s additional bundle of documents dated 27th November 2020 in which Lucie Maina, a director of the Plaintifi stated in part as follows: “ We are adding an additional fioor at the Ringsview Apartment Project in Kileleshwa. As a result, the apartment numbers for the eight units have changed. Through this email, I am confirming the correct apartment numbers to be B3, B5, B6, A10, A11, A12, C9 and C11 and not Unit/Apartment Numbers B5, A10, A9, B4, B2, C9, C7 and C2 as earlier advised.” 102. The Defendants submitted that by a letter dated 22nd November 2012 (See page 33 of DEXH.4), the Plaintifi acknowledged receipt of the sum of Kshs. 3,000,000/- from Vijay Morjaria in full and final payment for apartment number B6, A11 and A12. The Defendants submitted that in this letter, the Plaintifi took cognizance of the fact that the apartment numbers had changed and acknowledged payment of the purchase price for the same. 103. The Defendants submitted that following that acknowledgment, the parties executed lease agreements using the new apartment numbers as follows; 104. i. Lease over apartment B6 dated 3rd May 2013 from Ringsview Apartment to Vijay Morjaria. ii. Lease over apartment A11 dated 3rd May 2013 from Ringsview Apartment Limited to Hitesh Morjaria. iii. Lease over apartment A12 dated 3rd May 2013 from Ringsview Apartments Limited and Ringsview Apartment Management Limited to Ashok Dhirajlal Sanghani and Sujata Ashok Sanghani. The Defendants referred the court to copies of the said leases at pages 40 to 87 of DEXH.5. The Defendants submitted that a copy of the title for the suit property at page 31 of the Plaintifi’s additional bundle of documents dated 27th November 2020 shows that apartment A11 is registered in the name of https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 24
page 24 of 45
Hitesh Morjaria, apartment A12 in the names of Ashok Dhirajlal Sanghani and Sujata Ashok Sanghani and apartment B6 in the name of Vijay Morjaria. The Defendants submitted that the apartments were registered in the names of the said purchasers on 12th July 2013 who were subsequently issued with share certificates refiecting their shares in Ringsview Apartment Management Company Limited on 8th August 2013. The Defendants referred the court to the copies of the said share certificates at pages 242, 243 and 245 of DEXH. 4. 105. The Defendants submitted that clause 2.1.3 of the sale agreement between the parties provided that the purchaser shall pay Kshs. 3,000,000/- on the completion date. The Defendants submitted that this amount was paid gradually leaving a balance of Kshs. 500,000/- only outstanding, a fact that was acknowledged in the reconciliation of the accounts done by all the parties on 13th December 2013. The Defendants submitted that the 2nd Defendant remained able and willing to pay the said sum of Kshs, 500,000/- upon completion. 106. The Defendants submitted that the 2nd Defendant had established how the 2nd Defendant and his associates whom he legally represents pursuant to the power of attorney dated 3rd July 2014 (filed together with the Defendants’ defence and Counterclaim at pages 105 to 107 thereof) acquired the aforesaid apartments. Apartment B4 formerly known as Apartment B2. 107. The Defendants submitted that James Gatune Wathigo advocate was retained by Mr. and Mrs. Wangethi to provide legal advice during the sale and construction of Ringsview Apartments Limited. They submitted that Mr. and Mrs. Wangethi were the owners of the suit property on which the apartments’ project was being undertaken. The Defendants submitted that the duties of James Gatune Wathigo advocate continued even after the suit property was transferred to the Plaintifi and he was representing the directors of the Plaintifi. The Defendants submitted that the directors of the Plaintifi gave James Gatune Wathigo advocate apartment B2 as payment for his legal fees. The Defendants submitted that James Gatune Wathigo advocate who did not want to keep the apartment sold the same to the 2nd Defendant with the full knowledge of the directors of the Plaintifi and was paid the full purchase price of Kshs. 13,500,000/- by the 2nd Defendant. The Defendants referred the court to the sale agreement between the two at page 90 of DEXH.4. The Defendants submitted that the Plaintifi confirmed through a letter dated 2nd November 2011 (See page 7 of DEXH.4) that apartment B2 was sold to the 2nd Defendant and the same had been fully paid for. 108. The Defendants submitted that in his evidence, the 2nd Defendant stated that he requested the Plaintifi to give him Apartment B4 instead of B2 because he wanted all the apartments he had bought to be on the same fioor, a request the Plaintifi willingly accepted. The Defendants submitted further that through a letter dated 3rd June 2014 from J.G Wathigo Advocate to P.J Kakad & Co. Advocates, it was indicated that apartment B2 was swapped for Apartment B4 and P.J Kakad & Co. Advocates was instructed to proceed and pursue a partial discharge for apartment B4. The court was referred to page 56 of DEXH. 4 in this regard. 109. The Defendants submitted that the Plaintifi thereafter executed a lease dated 3rd May 2013 for the apartment number B4 in favour of the 2nd Defendant. The Defendants submitted that it was clear that the 2nd Defendant purchased apartment B2 which was later swapped for apartment B4 for value and was therefore the legal owner thereof. https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 25
page 25 of 45
Apartment C1 and A4. 110, The Defendants submitted that the Plaintifi had requested for a loan of Kshs.22,000,000/- from the 2nd Defendant to be paid back on 28th February,2013. The Defendant submitted that the Plaintifi was unable to repay the loan and interests on time, and as such, it wrote to the 2nd Defendant on the 16th of April, 2013 (See letter at page 39 of the DEXH.4) requesting that the loan be settled as follows; a) That the sum of Kshs. 22 million be converted into a deposit for apartments C1 and A4 of which it acknowledged receipt. b) That if the apartments C1 and A4 were not completed and transferred to the 2nd Defendant, the directors of the Plaintifi undertook and guaranteed to refund the said deposit to the 2nd Defendant. 111. The Defendants submitted that the Plaintifi was estopped from claiming any further payments for the abovementioned apartments having given them to the 2nd Defendant in settlement of the said friendly loan of Kshs. 22,000,000/- owed to the 2nd Defendant. 112. The Defendants submitted that the 2nd Defendant was approached by Kanakrai Ratilal Chand Shah who was interested in purchasing apartments C1 and A4 which were being sold at Kshs. 14,000,000/each. The Defendants submitted that the 2nd Defendant was paid the full purchase price by the said Kanakrai Ratilal Chand Shah. The Defendants submitted that the Plaintifi’s claim that the purchasers of the two apartments ought to have presented evidence to show payment to itself or to the 2nd Defendant was unfounded as the 2nd Defendant explained how he acquired the said apartments. 113. The Defendants submitted that the Plaintifi’s director, Dr. Mbira Gikonyo (PW1) sent an email on 18th December 2013 (See page 44 of DEXH. 4) to P.J Kakad Advocates to the efiect that an agreement had been reached and the Plaintifi had agreed to execute partial discharges, sale agreements and leases with regard to apartments C10, B4, C1 and A4. The Defendants submitted that the firm of P.J Kakad Advocates went ahead to prepare and register leases for the said apartments and particularly for apartments C1 and A4 in favour of Kanakrai Ratilal Chand Shah on the said instructions of the Plaintifi. 114. The Defendants submitted that the agreements and leases presented before the court showed without doubt that Kanakrai Ratilal Chand Shah was the true legal owner of apartments C1 and A4 and as such was entitled to the rights incidental thereto. The Defendants submitted that any purported sale of the apartments to a third party as suggested by the Plaintifi in its submissions at paragraph 4.2 (e) (ii) was null and void as one cannot sell what he does not own. Duplex Apartments; Formerly C9 and C7, currently known as C11 and C9. 115. The Defendants submitted that on 19th January 2012, the Plaintifi entered into a sale agreement for apartments numbers C9 and C7 with Ramesh Thakkar (See pages 223 to 235 of DEXH.5). The Defendants submitted that pursuant to the said agreement, the parties executed two leases in respect of the apartments both dated 3rd May 2013 in favour of Ramesh Thakkar and Anila Ramesh Thakkar. The Defendants referred the court to the leases at pages 236 to 252 of DEXH.5. The Defendants submitted that the Plaintifi had in its submissions admitted receipt of Kshs. 36,000,000/- for the two apartments. The Defendants submitted that the 2nd Defendant had no claim over the apartments save for its wish that Ramesh Thakkar and Anila Ramesh Thakkar be declared as the owners of the two apartments. https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 26
page 26 of 45
Apartment B3. 116. With regard to apartment B3, the Defendants submitted that a lease agreement was entered into between the Plaintifi and, Mitesh Nitinbhai Thakkar and Payal Mitesh Thakkar at a consideration of Kshs. 14,500,000/=. The Defendants submitted that the lease was registered in favour of the purchasers (See pages 121 to 137 of DEXH.5). The Defendants submitted further that the Plaintifi also acknowledged receipt of the purchase price for the apartment through its letter dated 30th October 2012 (See page 38 of DEXH.5). The Defendants submitted that the Plaintifi was in the circumstances estopped from claiming any more money for the apartments. Block D. 117. With regard to Block D, the Defendants admitted the meeting that was held by all the parties involved in the project on 9th December 2013 and the minutes of the said meeting dated 16th December 2016. The Defendants submitted that at the said meeting, the parties reconciled all the pending accounts relating to the Defendants and agreed on the said reconciliation. The Defendants submitted that following the said reconciliation that also included Block D, it was agreed that the payment due to the Plaintifi was Kshs. 50,500,000/- of which a sum of Kshs. 7,000,000/- was to be deducted from the retention money due to the 1st Defendant and the sum of Kshs. 43,500,000/- was to be secured by a professional undertaking from J.G.Wathigo & Co. Advocates to Dr. Gikonyo(PW1). The Defendants submitted that the said reconciliation of accounts captured the position of all the then pending payments due by the Defendants and his associates to the Plaintifi. The Defendants submitted that the reconciliation also captured apartment B2 in respect of which the 2nd Defendant was to pay a sum of Kshs. 15,000,000/- the agreement in respect of which was drawn and executed on 19th December 2013(See pages 192 to 206 of DEXH.5). The Defendants submitted that part of the reconciliation was the agreement for sale of the entire Block D executed by the parties on 19th December 2013(See pages 274 to 288 of DEXH.5). 118. The Defendants submitted that in fulfilment of the said agreement arrived at following the said reconciliation of accounts, the firm of J.G. Wathigo & Co. Advocates issued a professional undertaking to I & M Bank dated 19th December 2013 to pay a sum of Kshs. 43,500,000/-. The Defendant submitted that the Plaintifi on its part did not act on its part of the agreement claiming that the undertaking was defective. The Defendants submitted that out of the said sum of Kshs. 43,500,000/that the 2nd Defendant was to pay to the Plaintifi, only Kshs. 10,500,000/- was owed to the Plaintifi for other accounts. The Defendants submitted that the sum of Kshs. 33,000,000/- was for the purchase of the whole of Block D and apartment B2. The Defendants submitted that there was no mention of Kshs. 172,500,000/- claimed by the Plaintifi. The legality of the agreements in respect of the apartments. 119. The Defendants submitted that the Plaintifi’s claim that the agreements that it entered into with the 2nd Defendant and its associates in respect of the apartments in dispute were void was meant to evade its obligations. The Defendants submitted that the sale agreements and leases between the Plaintifi and the 2nd Defendant and his associates with respect to the apartments aforesaid were valid and binding upon the parties thereto and should be enforced by the court. The Defendants submitted that the said agreements were valid in all material respects. The Defendants submitted that the said agreements were executed by the Plaintifi’s directors willingly before an advocate. The Defendants submitted that a party cannot be allowed to run away from the terms of its agreement. The Defendants submitted that they should be shielded from the obvious breach by the Plaintifi of the said agreements. In support https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 27
page 27 of 45
of this submission, the Defendants referred the court to Jeremiah Mucheru Ndibui v. Davis Gishure Ngugi [2019] eKLR and Shah v. Guilders International Bank Ltd. [2003] KLR. Registration of the Caveat. 120. The Defendants submitted that any person who has a right to obtain interest in land, whether such right is contractual or otherwise; has a right to lodge a caution with the registrar which caution might restrict registration of dispositions in accordance with the provisions of section 71 of the Land Registration Act 2012. The Defendants submitted that under the said provisions of the Land Registration Act, the person lodging the caution is under no obligation whatsoever to inform the proprietor of the land of the intention to register the caution neither is such person under any obligation to obtain consent from the proprietor of the land upon which caution is to be registered. 121. The Defendants submitted that the 2nd Defendant exercised his rights when he registered the caveat complained of by the Plaintifi and did not need the permission of the Plaintifi before doing so. The Defendants submitted that the action by the 2nd Defendant to place a caveat on the suit property was in protection of its constitutional right to ownership of property. 122. The Defendants submitted that section 72 of the Land Registration Act 2012 places obligation upon the registrar to give notice in writing to the proprietor whose land is afiected by a caution. The Defendants submitted that the claim that the 2nd Defendant did not inform the Plaintifi that it had registered a caveat against the title of the suit property was baseless and as such the Plaintifi’s claim that it should be awarded the costs for lifting the caveat was similarly unfounded and should be dismissed. Whether the Plaintifi has established the fraud alleged against the 2nd Defendant. 123. The Defendants submitted that the Plaintifi had alleged that; the 2nd Defendant obtained the title deed for L.R No. 4858/11(the suit property) illegally, hid it from the Plaintifi and refused to release the same unless the Plaintifi signed the sale agreements and sub-leases for apartments which the 2nd Defendant had not paid for. The Defendants submitted that the Plaintifi sought a declaration that the leases to apartments C1 and A4 were fraudulently registered through blackmail and an order for the cancellation of the same. 124. The Defendants cited sections 107 and 109 of the Evidence Act Chapter 80 Laws of Kenya and submitted that the burden was upon the Plaintifi to prove that the 2nd Defendant acquired the said apartments fraudulently. The Defendants submitted that the burden in this case rested fully on the Plaintifi and at no time did it shift to the 2nd Defendant. The Defendants cited several authorities on the standard of proof of fraud among them; Rop Albert (Suing as the representative of the estate of Francis Kiprop Sanga Deceased) & Another v. Gladys Koskey & 3 Others [2018] eKLR, Paul Muira & another v. Jane Kendi Ikinyua & 2 others [2014] eKLR, Mutsonga v. Nyati 1984 (KLR) 425 and Koinange & 13 Others v. Koinange [1986] KLR 23. 125. The Defendants submitted that given the seriousness of an allegation of fraud, a person alleging it must present suficient evidence to prove the existence of same. The Defendants submitted that it is not enough to simply particularize allegations of fraud in pleadings. They submitted that the allegations must be proved to a standard higher than that on a balance of probabilities. In support of this submission, the Defendants relied onGabriel S. Chepkwony v. Gidion Nzioki Mbili & another [2018] eKLR where the court observed that: “ When a person alleges fraud, this is a serious issue which is criminal in nature and it does not only require the particulars to be listed but must be specifically proved. How do you prove https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 28
page 28 of 45
that a transaction was fraudulent? Do you just shout from the roof top that a transaction is fraudulent or you engage the relevant investigative agencies to help in unearthing the act?” 126. The Defendants submitted that the Plaintifi reported the alleged fraud to the Police who investigated the matter and cleared the 2nd Defendant of any wrongdoing. The Defendants referred the court to a letter dated 22nd November 2016 from the Directorate of Criminal Investigations(DCI) at page 250 of DEXH.5. The Defendants submitted that the efiect of the said letter from the DCI was that the 2nd Defendant was not involved in any act of fraud. The Defendants submitted that the allegations of fraud were made maliciously and in bad faith to enable the Plaintifi to evade its contractual obligations. The Defendants submitted that the title deed for the suit property was all along in the custody of James Watune Wathigo advocate(DW1) to whom the same was deposited by Mr. and Mrs. Wangethi who were the original owners of the suit property. The Defendants submitted that on the instructions of Mr. and Mrs. Wangethi, James Watune Wathigo advocate(DW1) forwarded the title deed to P.J Kakad advocate who was to transfer the property to the Plaintifi and to obtain a change of user. The Defendants submitted that the title deed was thereafter returned to James Watune Wathigo advocate’s ofice. The Defendants submitted that at no time did the 2nd Defendant get the said title deed into his possession and as such the issue of the 2nd Defendant using the same to black mail the Plaintifi into transferring apartments C1 and A4 to the 2nd Defendant had no basis. The Defendants submitted further that no complaints had been made with the relevant professional bodies against the conduct of James Gatune Wathigo and P.J Kakad Advocate. The Defendants submitted that the allegations made against the said advocates of collusion and acting without instructions had no basis in the circumstances. The Defendants submitted that the evidence of fraud placed before the court by the Plaintifi did not meet the threshold established by the authorities cited earlier. The Defendants urged the court to find that the Plaintifi had not discharged the burden of proof of fraud alleged against the Defendants. The Defendants submitted that apartments A4, A11, A12, B3, B4, B5, B6 and C1 had been registered in the names of the 2nd Defendant and the other purchasers he introduced to the Plaintifi. The Defendants submitted that the 2nd Defendant having established that the 2nd Defendant and his associates acquired the said apartments lawfully and the Plaintifi having failed to prove fraud alleged against the 2nd Defendant, the titles held by the 2nd Defendant and his associates were indefeasible. 127. In support of this submission, the Defendants relied on sections 24(b) and 26 of the Land Registration Act 2012 and Margaret Njeri Wachira v. Eliud Waweru Njenga[2018]eKLR. The Defendants urged the court to declare the 2nd Defendant as the rightful owner of apartments B3, B4, B5, B6, A4, A11, A12 and C1. Whether the Defendants are entitled to the other reliefs sought. 128. The Defendants submitted that since they had demonstrated that the contract dated 26th January 2011 was illegally terminated by the Plaintifi, the 1st Defendant was entitled to the return of possession of the site so that it could complete the works as per the contract. 129. The Defendants submitted that the 2nd Defendant had demonstrated that he acquired apartments B3, A11, A12, C1 and A4 lawfully and as such he was the indefeasible owner thereof and entitled to enjoy all rights and privileges appurtenant thereto. The Defendants submitted further that having established pursuant to the power of attorney on record the ownership of apartments B4, B5 and B6, the 2nd Defendant was entitled to the 2nd prayer in which he was seeking a mandatory injunction compelling the Plaintifi to give access and quiet peaceful possession to the 2nd Defendant and the https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 29
page 29 of 45
purchasers of apartments B3, B4, B5, B6, A4, A11, A12 and C1. The Defendants also submitted that they were entitled to the prohibitory permanent injunction sought against the Plaintifi. 130. The Defendants submitted further that the 2nd Defendant was a businessman and that he purchased the apartments with a view to selling the same after making some improvements. The Defendants submitted that the actions of the Plaintifi and its agents of interfering with the said apartments made it impossible for the 2nd Defendant to sell or lease any of the apartments. The Defendants submitted that the 2nd Defendant was entitled to general damages for lost opportunity and profit and in the alternative, the market value for each of the apartments belonging to the 2nd Defendant. 131. The Defendants submitted further that the 2nd Defendant was entitled to a sum of Kshs. 17,700,000/being the total estimated loss of income he had sufiered from being unlawfully restrained from accessing the subject properties. The Defendants submitted that this claim was based on clause 10.1.4 of the sale agreements of the apartments which provided for damages in the event the purchaser was not granted possession of apartments on the completion date. The Defendants submitted that the amount claimed is particularized in paragraph 23(b) of the Defence and Counterclaim. 132. On the issue of costs, the Defendants cited Halbury’s Laws of England, 4th Edition (Re-issue), [2010] Vol. 10, para 16 where the authors have stated as follows: “ The Court has discretion as to whether costs are payable by one party to another, the amount of those costs, and when they are to be paid. Where costs are in the discretion of the Court, a party has no right to costs unless and until the Court awards them to him and the Court has an absolute and unfettered discretion to award or not to award them. This discretion must be exercised judicially; it must not be exercised arbitrarily but in accordance with reason and justice”. 133. The Defendants also relied on Cecilia Karuru Ngayu v. Barclays Bank of Kenya & another [2016] eKLR where the court adopted the decision in Republic v. Rosemary Wairimu Munene, Ex-Parte Applicant and Ihururu Dairy Farmers Co-operative Society Ltd where it was held that: “ The issue of costs is at the discretion of the court as provided under the above section. The basic rule on attribution of costs is that costs follow the event....... It is well recognized that the principle costs follow the event is not to be used to penalize the losing party; rather it is for compensating the successful party for the trouble taken in prosecuting or defending the case.” 134. In conclusion, the Defendants submitted that the Plaintifi’s claim was contradictory in that on one hand, the Plaintifi was seeking Kshs. 118,500,000/- allegedly owed to it by the 2nd Defendant in respect of several apartments sold to him by the Plaintifi while on the other hand, the Plaintifi is seeking the cancellation of the titles in respect of apartments A11, A12, B3, B5 and B6 for the reason that the apartments were acquired fraudulently. The Defendants submitted that the Plaintifi cannot have it both ways; seeking the recovery of Kshs. 118,500,000/- and the cancellation of the titles on account of alleged fraud. The Defendants urged the court to dismiss the Plaintifi’s claim and to enter judgment for the Defendants as prayed in their counter-claim. Analysis and determination. 135. From the pleadings, the following in my view are the issues arising for determination in this suit and the counter-claim; https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 30
page 30 of 45
1. Whether the 1st Defendant breached the contract dated 26th July 2011 between the 1st Defendant and the Plaintifi by failing to complete the construction works within the agreed period. 2. Whether the Plaintifi is entitled to the sum of Kshs. 140,000,000/- at the rate of Kshs. 10,000,000/- per month from 30th March 2013 up to 31st May 2014 as agreed damages for the 1st Defendant’s delay in accordance with the agreement dated 25th April 2012. 3. Whether the 2nd Defendant unlawfully obtained and refused to release the title deed for L.R No. 4858/11(the suit property) unless Plaintifi signed sale agreements and sub-leases for apartments that had not been paid for by the 2nd Defendant and if so, whether the Plaintifi sufiered loss to the tune of Kshs. 14,000,000/- which the Plaintifi is entitled to recover from the 2nd Defendant as a result of the said unlawful action by the 2nd Defendant. 4. Whether the 2nd Defendant caused apartments C1, A4 and B4 to be registered in his name fraudulently without paying for the same. 5. Whether the Plaintifi is entitled to the sum of Kshs. 18,500,000/- from the 2nd Defendant in respect of apartments A9, A10, B6 and B5. 6. Whether the Plaintifi is entitled to the sum of Kshs. 29,000,000/- from the 2nd Defendant in respect of apartments B4 and B3. 7. Whether the Plaintifi is entitled to the sum of Kshs. 10,500,000/- from the 2nd Defendant in respect of apartments C1 and C4. 8. Whether the Plaintifi is entitled to the sum of Kshs. 11,500,000/- comprising of the sum of Kshs. 6,000,000/- that the 2nd Defendant received from the Plaintifi’s buyers of the apartments promising to incorporate additional features in the apartments like swimming pool and gymnasium which the 2nd Defendant did not remit to the Plaintifi and a sum of Kshs. 5,500,000/- which the 2nd Defendant received from potential buyers that he also never remitted to the Plaintifi. 9. Whether the Plaintifi is entitled to the sum of Kshs. 9,750,000/- that was paid to the 2nd Defendant in cash. 10. Whether the Plaintifi is entitled to the sum of Kshs. 8,000,000/- from the 2nd Defendant being the balance of the purchase price for apartment C7. 11. Whether the Plaintifi is entitled to the sum of Kshs. 3,000,000/- being the balance of the purchase price for apartment C10. 12. Whether the Plaintifi is entitled to the sum of Kshs. 5,000,000/- from the 2nd Defendant being the costs of the swimming pool that was built and demolished at the instance of the 2nd Defendant. 13. Whether the Plaintifi is entitled to the sum of Kshs. 2,900,000/- from the 2nd Defendant being the legal costs incurred in the removal of caveats and in the sale agreements. 14. Whether the Plaintifi is entitled to the other reliefs sought in the plaint. 15. Whether the termination of the contract between the Plaintifi and the 1st Defendant by the Plaintifi on 31st May 2014 was unlawful. https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 31
page 31 of 45
16. Whether the 1st Defendant is entitled to the sum of Kshs. 5,300,000/- from the Plaintifi arising from the variations of contract and extra work. 17. Whether the 1st Defendant is entitled to the sum of Kshs. 20,295,102/- from the Plaintifi as monies due and owing. 18. Whether the Plaintifi has denied the 2nd Defendant quiet access and peaceful possession of apartments B3, B4, B5, B6, A4, A11, A12, C1, C9 and C11 in breach of the sale agreements and sub-leases between the Plaintifi and the 2nd Defendant in respect of the said apartments. 19. Whether the 2nd Defendant has sufiered loss to the tune of Kshs. 17,700,000/- as a result of the said acts by the Plaintifi in relation to the said apartments and Block D. 20. Whether the 2nd Defendant is entitled to the sum of Kshs. 4,400,000/- from the Plaintifi for the Plaintifi’s failure to install solar system and intercom. 21. Whether the 2nd Defendant is entitled to the sum of Kshs. 33,848,236/- from the Plaintifi for additional works that were done by the apartment owners. 22. Whether the Defendants are entitled to the other reliefs sought in the counter-claim. 23. Who is liable for the costs of the suit and the counter-claim? Whether the 1st Defendant breached the contract dated 26th July 2011 between the 1st Defendant and the Plaintifi by failing to complete the construction works within the agreed period. 136. It is common ground that under the contract dated 26th July 2011, the construction of the apartments on the suit property was to commence on 27th July 2011 and was to be completed on 19th October 2012. It is also common ground that for various reasons, the completion date for the project was extended from time to time with the last extension being given on 16th May 2014. According to that extension, the 1st defendant was to complete the works by 30th May 2014 in default of which the Plaintifi was to be at liberty to terminate the contract. It is not disputed that the 1st Defendant did not complete the construction works by 30th May 2014. The 1st Defendant had put forward several reasons for its failure to complete the works as agreed. I have noted from the evidence on record that those reasons were taken into account and informed the various extensions that were extended to the 1st Defendant. It is my finding therefore that the 1st Defendant breached the contract dated 26th July 2011 by failing to complete the works within the agreed timeline. Whether the Plaintifi is entitled to the sum of Kshs. 140,000,000/- at the rate of Kshs. 10,000,000/per month from 30th March 2013 up to 31st May 2014 as agreed damages for the 1st Defendant’s delay in accordance with the agreement dated 25th April 2012. 137. I am in agreement with the 1st Defendant that this payment is not due to the Plaintifi. The claim is based on the agreement between the Plaintifi and the 1st Defendant made on 24th April 2012 under which the 1st Defendant agreed to pay to the Plaintifi agreed damages of Kshs. 10,000,000/- per month with efiect from 1st April 2013 if the construction of the apartments was not completed by March 2013. I am in agreement with the 1st Defendant that the Plaintifi waived its rights under the agreement made on 24th April 2012 and evidenced by the letter dated 25th April 2012 when it agreed to extend the completion period from time to time after the 1st Defendant failed to complete the construction by 31st March 2013 with the last of such extensions being granted on 16th May 2014. The Plaintifi having extended the completion period until 30th May 2014 cannot be permitted to go back to the agreement https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 32
page 32 of 45
of 24th April 2012 to claim damages from the 1st Defendant. The damages were payable for breach and by extending the completion period, the breach was waived and similarly the consequential damages. It is therefore my finding that the sum of Kshs. 140,000,000/- claimed by the Plaintifi from the 1st Defendant as damages for failure to complete the construction by 31st March 2013 is not payable. Whether the 2nd Defendant unlawfully obtained and refused to release the title deed for L.R No. 4858/11(the suit property) unless Plaintifi signed sale agreements and sub-leases for apartments that had not been paid for by the 2nd Defendant and if so, whether the Plaintifi sufiered loss to the tune of Kshs. 14,000,000/- which the Plaintifi is entitled to recover from the 2nd Defendant as a result of the said unlawful action by the 2nd Defendant. 138. It is common ground that L.R No. 4858/11(the suit property) was originally owned by Mr. Wangethi Mwangi and Mrs. Lizzie Wangui Wangethi (hereinafter referred to as “the Wangethis”). It is also common ground that the Wangethis were being represented by J.G. Wathigo & Company Advocates and that the Wangethis handed over to the said firm the Grant No. I.R. 91673 (the title deed) in respect of the suit property at the point when the suit property was to be transferred to the Plaintifi. Apart from their names being mentioned severally by both parties, the Wangethis never participated in these proceedings either as parties or witnesses. It has therefore not come out clearly as to the instructions that they gave to J.G. Wathigo & Company Advocates in relation to the said title deed save for the instructions for the property to be transferred to the Plaintifi and the user thereof being changed. The fact that J.G.Wathigo & Co. Advocates was initially acting only for the Wangethis is clear from the letter dated 7th July 2011 addressed to P.J.Kakad & Co. Advocates by J.G.Wathigo & Co. Advocates (DEXH.2) through which the latter forwarded to the former the said title deed on the instructions of the Wangethis so that P.J.Kakad & Co. Advocates could register the transfer of the suit property in favour of the Plaintifi and also complete the change of user from a single dwelling house to multidwelling house. According to the letter, the title deed was forwarded to P.J.Kakad & Co. Advocates on certain undertakings that the firm was to give to J.G.Wathigo & Company Advocates. This shows that J.G.Wathigo & Company Advocates and P.J.Kakad & Co. Advocates were acting for difierent clients or protecting difierent interests. In a letter dated 1st April 2012 by P.J.Kakad & Co. Advocates to Kiruti & Co. Advocates(at page 55 of PEXH.1), P.J.Kakad & Co. Advocates when called upon to release the said title deed indicated that the firm held the same on the undertaking it had given to the firm of J.G.Wathigo & Company Advocates. It is not very clear from the evidence on record on whose behalf P.J.Kakad & Co. Advocates was acting. In the letter (DEXH.2) referred to above, there is indication that his fee was to be paid by the 2nd Defendant which means he may have been acting for the 2nd Defendant. What is clear however is that the title deed for the suit property was handed over to J.G.Wathigo & Company Advocates by the Wangethis and that the same was to be dealt with in accordance with the Wangethis’ instructions. I have seen in the Plaintifi’s additional bundle of documents a copy of an e-mail dated 29th May 2012 from Mr. Wangethi Mwangi to Dr. Mbira Gikonyo(PW1) in which he reprimanded PW1 over his e-mail dated 24th May 2012 to J.G. Wathigo over the alleged release of the title deed for the suit property to the 2nd Defendant. In the e-mail, Mr. Wangethi Mwangi assured PW1 that the title was in the possession of J.G. Wathigo & Co. Advocates. From the evidence on record (See the letter at page 429 of DEXH.5), the title deed was released to I&M Bank Advocates, Kiruti & Company Advocates by P.J.Kakad & Company Advocates on 14th November 2012 having been authorized to do so by J.G. Wathigo & Co. Advocates through a letter dated 24th August 2012(See page 426 of DEXH.5). 139. From the foregoing, there is no evidence that the 2nd Defendant unlawfully obtained and refused to release the title deed for L.R No. 4858/11(the suit property) unless the Plaintifi signed sale agreements https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 33
page 33 of 45
and sub-leases for apartments that the 2nd Defendant had not been paid for. I am of the view that if indeed the 2nd Defendant unlawfully obtained the title deed for the suit property, the issue should have been taken up by the Wangethis with their advocates, J.G. Wathigo & Co. Advocates to whom they had delivered the said title. There is no evidence that the Wangethis raised such issue with J.G. Wathigo & Co. Advocates. In the circumstances, I am not satisfied that the Plaintifi has proved that the 2nd Defendant obtained and held the titled deed for the suit property illegally. The Plaintifi is therefore not entitled to the alleged loss sufiered by the Plaintifi in the sum of Kshs. 14,000,000/- as a result of the alleged illegal retention of the said title deed by the 2nd Defendant. In any event, the Plaintifi did not prove how the said sum of Kshs. 14,000,000/- claimed was arrived at. There is no evidence in the form of a certificate from the bank or otherwise showing that the Plaintifi paid the said amount as interest. It is my finding that the Plaintifi is not entitled to the said sum of Kshs. 14,000,000/-. Whether the 2nd Defendant caused apartments C1, A4 and B4 to be registered in his name fraudulently without paying for the same. 140. The Plaintifi has contended that it did not execute any agreement of sale or lease in favour of the 2nd Defendant and its associates in respect of apartments C1, A4 and B4 and that the leases executed in favour of the 2nd Defendant for the said apartments were fraudulent. The Plaintifi has contended that no payments were made for the apartments and if any was made, it was part payment. 141. With regard to apartments C1 and A4, the Plaintifi has claimed that an agreement was reached between the Plaintifi and the 2nd Defendant on 16th April 2013 in which a loan of Kshs. 22,000,000/- that had been advanced to the Plaintifi by the 2nd Defendant was converted to a deposit for the purchase of apartments C1 and A4. It was also part of the agreement that the Plaintifi would refund to the 2nd Defendant the said sum of Kshs. 22,000,000/- if apartments C1 and A4 were not completed and transferred to the 2nd Defendant. The Plaintifi has contended that in the circumstances, no payment was made for these apartments. The Plaintifi has contended that the 2nd Defendant did not prove the existence of the said loan of Kshs. 22,000,000/-. 142. For apartment C1, the Plaintifi has contended that in the lease at pages 140 to 156 of DEXH. 5 in favour of Kankrai Ratilalchand Shah and Niketan Ratilal Shah, the consideration for the apartment is given as Kshs. 12,000,000/-. The Plaintifi has contended that no evidence of payment of the said amount has been produced by the 2nd Defendant and the purported purchasers. The Plaintifi has contended that the apartment is still registered in the name of the Plaintifi and that the 2nd Defendant has no basis for claiming the same. 143. In their response, the Defendants have contended that the Plaintifi had requested for a loan of Kshs. 22,000,000/- from the 2nd Defendant to be paid back on 28th February 2013. The Defendants have contended that the Plaintifi was unable to repay the said loan and interests on time, and as such, it wrote to the 2nd Defendant on the 16th April 2013 (See letter at page 39 of the DEXH.4) requesting that the loan be converted to a deposit for apartments C1 and A4 which the 2nd Defendant accepted. 144. The Defendants have contended that the 2nd Defendant was approached by Kanakrai Ratilal Chand Shah who was interested in purchasing apartments C1 and A4 which were being sold at Kshs. 14,000,000/- each. The Defendants have contended that the said apartments were sold by the 2nd Defendant to Kanakrai Ratilal Chand Shah and the 2nd Defendant was paid the full purchase price. The Defendants have contended that the Plaintifi’s claim that the purchasers of the two apartments ought to have presented evidence to show payment to itself or to the 2nd Defendant was unfounded as the 2nd Defendant has explained how he acquired the said apartments. https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 34
page 34 of 45
145. With regard to apartment B4, the Plaintifi has denied that apartment B2 was given to James Wathigo by the Plaintifi in settlement of his fees. The Plaintifi has also denied that the number for apartment B2 changed to B4. The Plaintifi has contended that in the sale agreement dated 27th December 2011 between the Plaintifi and Hitesh Morjaria the consideration for apartment B4 is given as Kshs. 9,000,000/-(See pages 26 to 39 of DEXH.5). The Plaintifi has contended that this sale agreement contradicts the evidence given by the 2nd Defendant and DW1 in which they have claimed that apartment B2 was swapped for apartment B4. The Plaintifi has contended that no payment was received for this apartment B4 and that the 2nd Defendant produced no evidence of payment. 146. In response to the foregoing, the Defendants have contended that the directors of the Plaintifi gave James Gatune Wathigo advocate apartment B2 as payment for his legal fees. The Defendants have contended that James Gatune Wathigo advocate did not want to keep the apartment and as such sold the same to the 2nd Defendant with the full knowledge of the directors of the Plaintifi and was paid the full purchase price of Kshs. 13,500,000/- by the 2nd Defendant. The Defendants have contended that the Plaintifi confirmed through a letter dated 2nd November 2011 that apartment B2 was sold to the 2nd Defendant and that the same was paid for in full. 147. In the agreement dated 16th December 2013 between the Plaintifi, the 2nd Defendant and Mr. and Mrs. Wangethi (Wangethis), the parties agreed that in respect of apartments C1 and A4, there was an outstanding sum of Kshs. 2,500,000/- due and payable to the Plaintifi. For apartment B4, it was agreed that there was an outstanding sum of Kshs. 500,000/- due and payable to the Plaintifi on account of apartments B6, A11, A12 and B4. I am convinced upon perusing the agreements dated 16th April 2013 and 16th December 2013 that the 2nd Defendant paid a sum of Kshs. 22,000,000/- as a deposit for apartments C1 and A4 and that as at 16th December 2013 there was a sum of Kshs. 2,500,000/only due to the Plaintifi in respect of apartments C1 and A4. The Plaintifi has not persuaded me that the leases dated 20th November 2013 in respect of apartments C1 and A4 were fraudulent. In the agreement dated 16th April 2013 (page 173 of DEXH. 5), the Plaintifi admitted that the 2nd Defendant had advanced to it a loan of Kshs. 22,000,000/- and agreed that the loan be converted to a deposit for apartments C1 and A4. The leases in respect of apartments C1 and A4 were executed thereafter by the Plaintifi in favour of Kanakrai Ratilal Shah and Niketan Ratilal Shah. In the agreement dated 16th December 2013 entered into by the parties subsequent to the agreement dated 16th April 2013 and the leases dated 20th November 2013, the Plaintifi admitted that the only outstanding amount in respect of apartments C1 and A4 was Kshs. 2,500,000/-. The Plaintifi did not at all raise the issue of fraud. It is my finding that no fraud has been proved in respect of the agreement and leases executed by the Plaintifi for apartments C1 and A4. 148. With regard to apartment B4, I am in agreement with the 2nd Defendant that due to the additional one fioor that was added to the building that was being put up on the suit property, the numbers assigned to some apartments changed. There is however no evidence placed before the court showing that apartment B2 changed to B4 or that apartment B2 was swapped for apartment B4 for whatever reason. There is also no evidence that the Plaintifi gave J.G.Wathigo Advocate apartment B2 as payment for his legal fees. There is no evidence of an agreement between the Plaintifi and J.G.Wathigo Advocate to that efiect. There is also no evidence that J.G.Wathigo Advocate owned apartment B2 before he purportedly sold the same to the 2nd Defendant. What the 2nd Defendant produced in court as evidence of ownership of apartment B2 by J.G.Wathigo Advocate was a letter dated 3rd June 2014 from J.G.Wathigo Advocate to P.J.Kakad & Co. Advocates confirming that the 2nd Defendant had purchased apartment B2 from him and that the apartment was swapped for apartment B4. There is also the agreement for sale between J.G.Wathigo Advocate and the 2nd Defendant dated 2nd November 2011. According to the agreement https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 35
page 35 of 45
dated 27th December 2011 between the Plaintifi and Hitesh Morjaria and Vijay Morjaria (page 26 DEXH.5), the Plaintifi sold apartment B4 to the Morjarias at Kshs. 9,000,000/-. The Plaintifi is also said to have acknowledged the sale of the apartment to the 2nd Defendant on 2nd November 2011. According to the lease in respect of the same apartment dated 3rd May 2013 between the same parties, the stand premium is given as Kshs. 14,000,000/-. It is not clear here why the 2nd Defendant would have purchased the apartment again from the Plaintifi on 27th December 2011 having purchased the same from J.G.Wathigo on 2nd November 2011. I have also noted from the agreement between the parties made on 16th December 2013 that apartments B2 and B4 are listed separately and that for apartment B4 there was an outstanding payment of Kshs. 500,000/- to cover the balances for apartments B6, A11, A12 and B4 while for apartment B2, there was an outstanding amount of Kshs. 15,000,000/-. It is my finding from the foregoing that apartments B2 and B4 are separate apartments and that apartment B2 was not swapped for apartment B4 as there is no evidence to that efiect. It is also my finding that there is no proof that J.G.Wathigo Advocate owned apartment B2 or that the same was given to him by the Plaintifi. 149. There is also no evidence in support of the Plaintifi’s contention that the sale agreement dated 27th December 2011 between the Plaintifi and Hitesh Morjaria and Vijay Morjaria in respect of apartment B4 was fraudulent. The agreement was drawn by the firm of Mulondo, Oundo, Muriuki & Company Advocates which was acting for the Plaintifi. The agreement was executed by the directors of the Plaintifi. The Plaintifi has also not denied executing the agreement dated 16th December 2013 in which it agreed to discharge apartment B4 on receipt of a sum of Kshs. 500,000/- to cover the balances in respect of apartments B6, A11, A12 and B4. It is therefore my finding that the 2nd Defendant lawfully purchased apartment B4 from the Plaintifi and that there was an outstanding amount of Kshs. 125,000/-(1/4 of Kshs. 500,000/-) to be paid by the 2nd Defendant to cover the amount due on that apartment. 150. I wish to add that there is no evidence before the court showing that the leases in respect of apartments C1, A4 and B4 have been registered. The issue of the same having been registered fraudulently does not therefore arise. Whether the Plaintifi is entitled to the sum of Kshs. 18,500,000/- from the 2nd Defendant in respect of apartments A9, A10, B5 and B6. 151. The Plaintifi has contended that it received a sum of Kshs. 9,000,000/- as the purchase price for apartment B5 leaving a balance of Kshs. 6,000,000/- which arose due to change in design. The Plaintifi has contended further that it was paid a sum of Kshs. 9,000,000/- for apartment B6 leaving a balance of Kshs. 6,000,000/- which also came about due to a change of design that was paid for by the Plaintifi. For apartments A10 and A9, the Plaintifi has contended that the 2nd Defendant has not raised any claim in respect thereof. 152. On their part, the Defendants have contended that the 2nd Defendant together with Hitesh Morjaria entered into a sale agreement dated 18th April 2011 with the Plaintifi for the purchase of duplex apartments B5, A10 and A9 at a consideration of Kshs. 31,500,000/= and paid a deposit. The Defendants have submitted that in the course of construction, the numbering of the apartments were changed as a result of which apartment B5 changed to B6, A10 to A11 and A9 to A12. The Defendants have contended that by a letter dated 22nd November 2012, the Plaintifi acknowledged receipt of a sum of Kshs. 3,000,000/- from the 2nd Defendant in full and final payment for apartment number B6, A11 and A12. The Defendants have contended that the Plaintifi was aware that the apartment numbers had changed and acknowledged payment of the purchase price for the same. https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 36
page 36 of 45
153. The Defendants have contended that the Plaintifi thereafter executed; a lease over apartment B6(B5) dated 3rd May 2013 in favour of the 2nd Defendant, a lease over apartment A11(A10) dated 3rd May 2013 in favour of Hitesh Morjaria and a lease over apartment A12(A9) dated 3rd May 2013 in favour of Ashok Dhirajlal Sanghani and Sujata Ashok Sanghani. The Defendants have contended that the leases over the said apartments were all registered on 12th July 2013. 154. The Defendants have contended that clause 2.1.3 of the sale agreement between the parties in respect of the said apartments provided that the purchasers were to pay Kshs. 3,000,000/- on the completion date. The Defendants have contended that this amount was paid gradually and only a balance of Kshs. 500,000/- remains outstanding, a fact that was acknowledged in the reconciliation of accounts done by the parties and captured in the agreement dated 16th December 2013. The Defendants contended that the 2nd Defendant remains able and willing to pay the said sum of Kshs, 500,000/- upon completion. 155. From the evidence on record, I am satisfied that the Plaintifi sold to Hitesh Morjaria and the 2nd Defendant apartments A9, A10 and B5 (A12, A11 and B6) on 18th April 2011 following an ofier that was made by the Plaintifi to Hitesh Morjaria and the 2nd Defendant on 2nd March 2011. I am in agreement with the 2nd Defendant that apartment numbers for apartment A9, A10 and B5 changed to A12, A11 and B6 respectively. In view of the terms of the agreement between the parties dated 16th December 2013, I am in agreement with the 2nd Defendant that only a sum of Kshs. 375,000/-(3/4 of Kshs. 500,000/-) remains due and payable by the 2nd Defendant and Hitesh Morjaria in respect of apartments A9(A12), A10(A11) and B5(B6). The Plaintifi which had acknowledged receipt of the full purchase price in a letter dated 22nd November 2012 claims the additional sum of Kshs. 18,500,000/on account of change of design of the apartments. The Plaintifi has not proved this claim. The Plaintifi has not established that the 2nd Defendant and Hitesh Morjaria are liable to pay for the said changes. Furthermore, neither the changes nor the costings thereof were submitted in evidence. 156. Apart from apartment B5 that was sold to Hitesh Morjaria and the 2nd Defendant that changed to apartment B6 referred to above in respect of which I have found that there is a total sum of Kshs. 375,000/- (for apartments A9(A12), A10(A11), B5(B6) due and owing to the Plaintifi, I am not satisfied that there was any other apartment B5 that was sold to Hitesh Morjaria and the 2nd Defendant for Kshs. 11,000,000/- and in respect of which a sum of Kshs. 9,000,000/- was paid leaving a balance of Kshs. 6,000,000/-. If there was such an apartment, then I believe that it can only be what the 2nd defendant referred to in his evidence as apartment B4 that the 2nd Defendant and Hitesh Morjaria purchased on 27th December 2011(See the sale agreement at page 26 and lease at page 89 of DEXH. 5) which I have referred to earlier. The 2nd defendant had led evidence that apart from apartment B2 that he swapped for apartment B4, the 2nd defendant and Hitesh Morjaria had also purchased apartment originally numbered B4 whose number changed to B5. It appears that it is this apartment B4 that the Plaintifi has referred to as apartment B5. I have held that only a sum of Kshs. 125,000/-(1/4 of Kshs. 500,000/-) is due and payable on account of apartment B5(B4). It is worth noting that the sum of Kshs. 6,000,000/- claimed by the Plaintifi as the balance due under this apartment B5(former B4) is not mentioned in the agreement dated 16th December 2013 as due and payable to the Plaintifi. Whether the Plaintifi is entitled to the sum of Kshs. 29,000,000/- from the 2nd Defendant in respect of apartments B3 and B4. 157. The Plaintifi has contended that the purchaser of apartment B3 owes the Plaintifi Kshs. 14,500,000/-. The Plaintifi has contended that the sale agreement for the apartment is not dated and the consideration is given as Kshs. 14,500,000/-. The Plaintifi has submitted that the lease in respect of https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 37
page 37 of 45
the apartment is dated 3rd May 2013 and the same is in favour of Mitesh and Payal Thakkar. The Plaintifi has contended that the consideration for the lease is given as Kshs. 14,000,000/-. The Plaintifi has contended that there is also acknowledgment of payment of Kshs. 14,500,000/-. The Plaintifi has contended that no payment was received for this apartment and that the 2nd Defendant produced no evidence of payment. 158. With regard to apartment B4, the Plaintifi has contended that there is a sale agreement dated 27th December 2011 between the Plaintifi and, Hitesh Morjaria and the 2nd Defendant. The Plaintifi has contended that the consideration is given in the agreement as Kshs. 9,000,000/-. The Plaintifi has contended that this sale agreement contradicts the evidence given by the 2nd Defendant and DW1 in which they have claimed that apartment B2 was swapped for apartment B4. The Plaintifi has contended that no payment was received for this apartment. 159. On their part, the Defendants have contended that a lease agreement was entered into between the Plaintifi and, Mitesh Nitinbhai Thakkar and Payal Mitesh Thakkar in respect of apartment B3 at a consideration of Kshs. 14,500,000/=. The Defendants have contended that the lease was registered in favour of the purchasers. The Defendants have contended that the Plaintifi also acknowledged receipt of the purchase price for the apartment. The Defendants have contended that the Plaintifi is in the circumstances estopped from claiming more money for the apartment. 160. With regard to apartment B4, the Defendants have reiterated that the directors of the Plaintifi gave apartment B2 that was swapped for apartment B4 to James Gatune Wathigo advocate. The Defendants have reiterated further that James Gatune Wathigo advocate sold the apartment to the 2nd Defendant for Kshs. 13,500,000/- and was paid in full by the 2nd Defendant. 161. With regard to apartment B3, I am satisfied from the evidence on record that the apartment was sold by the Plaintifi to Mitesh Nitinbhai Thakkar and Payal Mitesh Thakkar at a consideration of Kshs. 14,500,000/- and that the Plaintifi was paid the said sum of Kshs. 14,500,000/- by the duo on or about 30th October 2012. The apartment is not one of those in respect of which there was an outstanding payment as at the date of the agreement between the parties made on 16th December 2013. There is no evidence that the Plaintifi executed the agreement of sale, the acknowledgment of payment and the lease in respect of the apartment dated 3rd May 2013 through duress or misrepresentation. The Plaintifi was not the weaker party in the transaction and I cannot understand why the Plaintifi could not seek redress in court to avert the alleged blackmail. The payment for the apartment was acknowledged through a letter dated 30th October 2012 while the lease in respect of the apartment was registered on 12th July 2013. This suit was filed on 17th June 2014. I wonder why the Plaintifi would wait for almost 1½ years after acknowledging receipt of payment and almost 1 year after registration of the lease to claim that it was blackmailed to acknowledge the payment that it never received and that it signed the lease without consideration. It is my finding that the apartment was paid for in full and no more payment is due to the Plaintifi in respect of apartment B3. 162. For apartment B4, I have already made a finding that apartment B2 and B4 are separate and distinct apartments and that the Plaintifi did not give apartment B2 to J.G.Wathigo advocate in settlement of his fees. I have also held that the number for this apartment B4 was subsequently changed to apartment B5 in respect of which the plaintifi also raised a claim. Since there is no relationship between apartment B2 and apartment B4, the 2nd Defendant and Hitesh Morjaria are bound by the agreement dated 27th December 2011 between them and the Plaintifi to pay the consideration of Kshs. 9,000,000/- in respect of apartment B4. As mentioned earlier, according to the agreement between the parties dated 16th December 2013, the 2nd Defendant owed the Plaintifi a sum of Kshs. 500,000/- that was to cover the balances in respect of apartments B6, A11, A12 and B4. It is my finding therefore that the Plaintifi is https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 38
page 38 of 45
not entitled to the sum of Kshs. 29,000,000/- claimed as due in respect of apartments B3 and B4. The Plaintifi is not entitled to any payment for apartment B3 while for apartment B4, the amount due is Kshs. 125,000/- (¼ of Kshs. 500,000/-). Whether the Plaintifi is entitled to the sum of Kshs. 10,500,000/- from the 2nd Defendant in respect of apartments C1 and C4. 163. I have stated earlier in the judgment that upon perusing the agreements dated 16th April 2013 and 16th December 2013, I am convinced that the 2nd Defendant paid a sum of Kshs. 22,000,000/- as a deposit for apartments C1 and A4 and that as at 16th December 2013 there was a sum of Kshs. 2,500,000/only due and payable to the Plaintifi in respect of apartments C1 and A4. In the circumstances, it is my finding that there is no basis for the Plaintifi’s claim for Kshs. 10,500,000/- in respect of these apartments. Whether the Plaintifi is entitled to the sum of Kshs. 11,500,000/- from the 2nd Defendant comprising of Kshs. 6,000,000/- received by the 2nd Defendant from the Plaintifi ’s buyers of the apartments promising to incorporate additional features in the apartments like swimming pool and gymnasium which the 2nd Defendant did not remit to the Plaintifi and the sum of Kshs. 5,500,000/- which the 2nd Defendant received from potential buyers that he also never remitted to the Plaintifi. 164. In his evidence, PW1 claimed that the 2nd Defendant obtained a sum of Kshs. 6,000,000/- from persons who wished to purchase apartments from the Plaintifi promising them that he was capable of adding additional features to the suit property such as swimming pool and a gym. PW1 stated that the 2nd Defendant did not remit this amount to the Plaintifi. PW1 claimed further that the 2nd Defendant received a further sum of Kshs. 5,500,000/- from two buyers of the apartments that he also failed to remit to the Plaintifi. PW1 did not give the particulars of these payments. The names of the persons from whom the 2nd Defendant received the alleged payments were not pleaded in the plaint nor the details of the amounts received from each and when the same was received. Some names are given in the further witness statement and amounts mentioned but without particulars of what the payments were for, when they were made and evidence of payment. Due to the foregoing, I find the Plaintifi’s claim for Kshs. 11,500,000/- not proved. Whether the Plaintifi is entitled to the sum of Kshs. 9,750,000/- that was paid to the 2nd Defendant in cash. 165. PW1 stated in his evidence that the Plaintifi paid to the 2nd Defendant a total sum of Kshs. 9,735,000/in cash in repayment of the loan that the 2nd Defendant had advanced to the Plaintifi. PW1 stated that the 2nd Defendant refused to acknowledge receipt of these cash payments. In its plaint, the Plaintifi claimed from the 2nd Defendant a sum of Kshs. 9,750,000/- being cash payments received from the Plaintifi. Again, no particulars of these payments were given in the plaint or in evidence. PW1 did not tell the court when the payments were made and where. There was also no explanation why a large sum of Kshs. 9,750,000/- would be paid in cash. It is my finding that this claim for Kshs. 9,750,000/- was also not proved. The claim is not maintainable in the circumstances. Whether the Plaintifi is entitled to the sum of Kshs. 8,000,000/- from the 2nd Defendant being the balance of the purchase price for apartment C7. 166. The Plaintifi has contended that apartments C9 and C7 were sold to Ramesh Thakkar and/or nominee on 19th January 2012 at a total consideration of Kshs. 36,000,000/-. The Plaintifi has contended that https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 39
page 39 of 45
apartment C9 is registered in the name of Ramesh Thakkar and Anila Thakkar. The Plaintifi has contended that it was paid in full for the two apartments by the purchasers thereof and it has no claim regarding the same. The Plaintifi has contended that the 2nd Defendant has no basis for his claim in respect of apartment C9 as he has no power of attorney from the purchasers. 167. The Defendants on their part have contended that the Plaintifi had in its submissions admitted receipt of Kshs. 36,000,000/- for the two apartments; C9 and C7. The Defendants have submitted that the 2nd Defendant has no claim over the apartments save for his wish that Ramesh Thakkar and Anila Ramesh Thakkar be declared as the owners of the two apartments. 168. In view of the position taken by both parties in their submissions, there is no basis for the Plaintifi’s claim for Kshs. 8,000,000/- in respect of apartment C7. Whether the Plaintifi is entitled to the sum of Kshs. 3,000,000/- being the balance of the purchase price for apartment C10. 169. The Plaintifi did not make submissions in respect of this claim. The Defendants on the other hand only mentioned apartment C10 in passing. I have not seen a sale agreement or a lease in respect of this apartment. I have however noted from the agreement dated 16th December 2013 that there was an outstanding amount of Kshs. 3,000,000/- due and payable by the 2nd Defendant to the Plaintifi in respect of this apartment. The Plaintifi is entitled to this amount in the circumstances. Whether the Plaintifi is entitled to the sum of Kshs. 5,000,000/- from the 2nd Defendant being the costs of the swimming pool that was built and demolished at the instance of the 2nd Defendant. 170. In his evidence, PW1 stated that the 2nd Defendant took money from some of the purchasers of the apartments promising that he would put up a swimming pool and a gym in the suit property. PW1 stated that after the swimming pool was put up, the 2nd Defendant insisted that the same be demolished thereby occasioning a loss of Kshs. 3,500,000/- to the Plaintifi. In its plaint, the Plaintifi claimed a sum of Kshs. 5,000,000/- as the loss sufiered for putting up and demolishing the swimming pool. The evidence tendered by the Plaintifi regarding the loss and the quantum of loss pleaded difier. In any event, no evidence was placed before the court showing that the alleged swimming pool was constructed on the instructions of the 2nd Defendant and that the 2nd Defendant ordered its demolition. The court was also not told why the 2nd Defendant wanted the swimming pool demolished. The costs of the construction of the swimming pool was not given neither did the Plaintifi tender evidence of the costs for its demolition. It is therefore not clear how the figures of Kshs. 3,500,000/- and Kshs. 5,000,000/- were arrived at. It is my finding in the circumstances that this claim is not proved by the Plaintifi. Whether the Plaintifi is entitled to the sum of Kshs. 2,900,000/- from the 2nd Defendant being legal costs incurred in caveats and sale agreements. 171. No particulars of this claim of Kshs. 2,900,000/- were given by the plaintifi. No fee notes/invoices or evidence of payment thereof were tendered in evidence. The Plaintifi did not demonstrate that the caveat that was lodged by the 2nd Defendant against the title of the suit property was unlawful. The 2nd Defendant was a purchaser of several apartments put up on the suit property that had not been transferred to him. I am in agreement with the 2nd Defendant’s submission that it had suficient interest in the suit property to support a caveat. In any event, if the Plaintifi felt that the caveat was wrongfully put against the title, it had a right to seek its removal which it never did. The claim is also made in https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 40
page 40 of 45
respect of “sale agreements”. It has not been established how the 2nd Defendant is liable for the costs that the Plaintifi may have spent on the said sale agreements. I find this claim not proved. Whether the Plaintifi is entitled to the other reliefs sought in the plaint. 172. I have at the beginning of this judgment set out in detail the reliefs sought by the Plaintifi. I have already made a finding that the 1st Defendant breached the contract dated 26th July 2011 by failing to complete the construction work within the agreed timeline. The parties had agreed that if the 1st Defendant failed to complete the construction by 30th May 2014, the Plaintifi would be entitled to terminate the contract. Following the 1st Defendant’s failure to complete the said works by 30th May 2014, the Plaintifi terminated the contract through a letter of termination dated 31st May 2014. The termination was in the circumstances lawful. Since the 1st Defendant’s services had been terminated, it was supposed to handover the site to the Plaintifi together with whatever was on site save for its equipment and machinery in accordance with clause 38.4.1 of the contract. The 1st and 2nd Defendants had no right in the circumstances to barricade the entry to the apartments and to take away the keys of the apartments save for those keys that may have been handed over to the 2nd Defendant for those apartments that were purchased by the 2nd Defendant and his associates and for which payment had been made or in respect of which they were entitled to be in possession pursuant to the various agreements of sale between the parties. 173. Due to the foregoing, the Plaintifi is entitled to a mandatory injunction compelling the Defendants to return the keys for the apartments on the suit property save for those apartments the court has held to have been purchased and paid for by the 2nd Defendant and his associates and those that the 2nd Defendant and his associates are entitled to remain in possession pursuant to the terms of the agreements of sale between the parties. The Plaintifi is also entitled to an injunction to restrain the Defendants from selling, transferring or charging the apartments on the suit property save for the apartments the court has held to have been purchased and paid for by the 2nd Defendant and his associates. The Plaintifi is also entitled to an injunction to restrain the Defendants from interfering with the Plaintifi’s possession of the said apartments save for the apartments purchased and paid for by the 2nd Defendant and his associates. 174. As for the claim for Kshs. 140,000,000/- I have held that the Plaintifi is not entitled to the same. As for the claim for Kshs. 112,150,000/-, I have held that the Plaintifi is only entitled to a total sum of Kshs. 6,000,000/- the particulars of which are as follows: The Plaintifi is entitled to a sum of Kshs. 375,000/- being the balance of the purchase price for apartments A9(A12), A10(A11) and B5(B6), Kshs. 125,000/- being the balance of the purchase price for apartment B4, Kshs. 2,500,000/- being the balance of the purchase price for apartments C1 and A4 and Kshs. 3,000,000/- being the balance of the purchase price for apartment C10 making a total of Kshs. 6,000,000/-. I have held that the Plaintifi is not entitled to any payment claimed in respect of apartments B3, C7 and C9. I have also rejected the Plaintifi’s claim in respect of buyer’s funds, interest at bank, funds paid to the 2nd Defendant in cash, the costs for constructing and demolishing the swimming pool and legal costs on caveats and sale agreements. 175. I have held earlier that the Plaintifi failed to prove that the leases for apartments C1, A4 and B4 were issued and registered through blackmail and fraud. In the plaint, the Plaintifi has claimed the balance of the purchase price alleged to be due on these apartments. As correctly submitted by the Defendants, the Plaintifi cannot claim the balance of the purchase price on alleged fraudulent leases. Having found that fraud in the execution of the said leases and their registration were not proved, I find no basis for declaring the registration of the leases for those apartments fraudulent and for cancelling the same. https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 41
page 41 of 45
Whether the termination of the contract between the Plaintifi and the 1st Defendant by the Plaintifi on 31st May 2014 was unlawful. 176. I have already determined this issue. I have found that the 1st Defendant breached the contract between it and the Plaintifi and as such the Plaintifi was entitled to terminate the contract. I am satisfied that the termination notice dated 31st May 2014 that was served upon the 1st Defendant complied with clause 38.2 of the contract. Before that notice was issued, the 1st Defendant had been given 14 days notice by the project architect to complete the works that were remaining. The Plaintifi’s notice of termination was given within 14 days after the expiry of the architect’s notice. The termination of the contract was therefore lawful. Whether the 1st Defendant is entitled to the sum of Kshs. 5,300,000/- from the Plaintifi due to variations of contract and extra work. 177. It is not clear how this amount was arrived at. The claim is in the nature of special damages. It ought to have been pleaded with necessary particulars and strictly proved. I am in agreement with the 1st Defendant that 1st Defendant did extra work and was entitled to be paid for the same. It has however not been explained how this sum of Kshs. 5,300,000/- for extra work was arrived at. There is no valuation to support the same or the particulars of the work that was done. I have noted from the record that some of the extra work was done at the request of the 2nd Defendant in respect of “his apartments”. It is not clear therefore what extra work was done on account of the Plaintifi and what was done for the 2nd Defendant. Save for stating that the amount was for variations and extra work, the 1st Defendant said no more. It is my finding that the claim has not been proved and as such is not payable. Whether the 1st Defendant is entitled to the sum of Kshs. 20,295,102/- from the Plaintifi as monies due and owing. 178. This claim is said to be for the amount due and owing to the 1st Defendant on the contract. As at the time the 1st Defendant’s services were terminated on 31st May 2014, the 1st Defendant was on site and was proceeding with the work. As at that stage, the 1st Defendant was entitled to an interim payment certificate for the work done as at 30th May 2014 and a final certificate after the completion of the remaining works. Before the Plaintifi handed over the work to another contractor, it had a duty to ensure that an interim payment certificate was prepared for the work done by the 1st Defendant as at the time of termination of its contract in accordance with clause 38.4.2 of the contract. After the work was completed by whichever contractor, the 1st Defendant would then be issued with the final certificate of payment. I have seen in the evidence produced by the 1st Defendant that it made several requests to the project quantity surveyor to value the work that it had done for the purposes of interim certificate No. 21 which requests were not attended to. From its statement of account at page 102 of DEXH. 3, the 1st Defendant has claimed a sum of Kshs. 11,816,880/- for interim certificate No. 21 and a sum of Kshs. 7, 521,672.00 for the final certificate No. 22 making a total of Kshs. 19,338,552/-. The Plaintifi has contended that these certificates which are based on the valuations made by the 1st Defendant are not payable because they were not certified by the project Quantity Surveyor and Architect. The Plaintifi has contended that the said Quantity Surveyor and Architect were not its agents but independent contractors and as such it was not answerable for their actions and omissions. It is common ground that the project was completed and the apartments occupied. I am of the view that it would be unfair to deny the 1st Defendant payment for the work done as a result of the failure on the part of the Plaintifi to have the work done by the 1st Defendant valued and certified by the Quantity Surveyor and the Architect employed by the Plaintifi in accordance with the terms of the contract between the parties. https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 42
page 42 of 45
The project Quantity Surveyor and the Architect were employed by the Plaintifi and as such took instructions from it. The Plaintifi cannot therefore claim that it is not liable for the said Quantity Surveyor’s and Architect’s failure to certify the work done by the 1st Defendant after the termination of its contract. Due to the failure on the part of the Plaintifi to have the work done by the 1st Defendant valued and the certificates issued after the termination of the 1st Defendant’s services and in the absence of any evidence challenging the valuation done by the 1st Defendant and an opportunity to carry out valuation due to changed circumstances, it is my finding that the 1st Defendant is entitled to a sum of Kshs. 19,338,552/- claimed under certificates No. 21 and 22 that were not certified by the Quantity Surveyor and Architect. The extra amount of Kshs. 956,550/- claimed by the 1st Defendant has not been proved and as such is not payable. Whether the Plaintifi has denied the 2nd Defendant quiet access and peaceful possession of apartments B3, B4, B6, A4, A11, A12, C1, C9 and C11 in breach of the sale agreements and sub-leases between the Plaintifi and the 2nd Defendant in respect of the said apartments. 179. From my analysis of the parties’ respective cases earlier, I have found that apartments A9(A12), A10(A11), B5(B6), B4(B5), C1, A4 and C10 have not been paid for in full by the 2nd Defendant and his associates while apartments B3, C7(C11) and C9 have been paid for in full. In the circumstances, the 2nd Defendant could not expect quiet possession of apartments A9(A12), A10(A11), B5(B6), B4(B5), C1, A4 and C10 in respect of which he had not finished payment. For apartments C9 and C11, the 2nd Defendant informed the court that he had no claim in respect thereof. It follows that the only apartment in respect of which the 2nd Defendant was entitled to quiet possession is apartment B3. Whether the 2nd Defendant has sufiered loss to the tune of Kshs. 17,700,000/- which the Plaintifi is liable for as a result of the said acts of the Plaintifi in relation to the said apartments and Block D. 180. At the trial, the 2nd Defendant told the court that he had no claim over Block D. With regard to the apartments referred to above, the only loss that the 2nd Defendant can claim is in respect of apartment B3. The 2nd defendant has claimed a sum of Kshs. 1,360,000/- as damages in respect of apartment B3. The 2nd Defendant’s associates having paid for apartment B3 in full, the Plaintifi had no reasonable cause for denying them quiet possession thereof. The 2nd Defendant’s said associates have been kept out of the property for several years. They are entitled to damages. The Plaintifi has not contended that the amount of damages claimed for the apartment is unreasonable. I will ward the 2nd Defendant a sum of Kshs. 1,360,000/- as damages sufiered for loss of use of the property. Whether the 2nd Defendant is entitled to the sum of Kshs. 4,400,000/- from the Plaintifi for the Plaintifi ’s failure to install solar system and intercom. 181. No basis was laid for this claim. No agreement was placed before the court between the Plaintifi and the 2nd Defendant for the installation of solar system and intercom. There was also no evidence of payment made to the Plaintifi for that purpose. I find no merit in this claim for Kshs. 4,400,000/-. Whether the 2nd Defendant is entitled to the sum of Kshs. 33,848,236/- from the Plaintifi for additional works that were undertaken by the apartment owners. 182. Like the earlier claim for Kshs. 4,400,000/- this claim was not proved. No particulars of the additional works were given neither were the apartments and the owners thereof disclosed. The breakdown of the https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 43
page 43 of 45
claimed sum of said sum of Kshs. 33,848,236/- was also not given and the evidence that such costs was incurred. I find no basis for this claim. The 2nd Defendant is not entitled to amount claimed. Whether the Defendants are entitled to the other reliefs sought in the counter-claim. 183. I have set out earlier in the judgment, the reliefs claimed in the Defendants’ counter-claim. As I mentioned earlier, it is common ground that the construction works have been completed. In the circumstances, it would serve no purpose returning possession of the site to the 1st Defendant. In any event, I have held that the 1st Defendant’s contract was lawfully terminated. The 1st Defendant is therefore not entitled to go back to the site of the project that has been completed as there is nothing left for it to do there. For an order compelling the Plaintifi to give the 2nd Defendant access and peaceful vacant possession of apartments B3, B4, B5, B6, A4, A11, A12, C1, C9 and C11. As I stated earlier, the 2nd Defendant has not paid for A9(A12), A10(A11), B5(B6), B4(B5), C1 and A4 in full while the claim in respect of apartments C9 and C11 was abandoned as the dispute over the same had been resolved directly between the Plaintifi and the purchasers thereof. The 2nd Defendant is not entitled to possession of apartments A9(A12), A10(A11), B5(B6), B4(B5), C1 and A4 until they clear the outstanding balances save where the contracts between the parties provide to the contrary. The only apartment whose possession he is entitled to is apartments B3. The 2nd Defendant is however entitled to an injunction to restrain the Plaintifi from selling, charging or disposing of apartments A9(A12), A10(A11), B5(B6), B4(B5), C1 and A4 in respect of which they had entered into sale agreements with the Plaintifi and made payments on account of the purchase price. With regard to the retention money, since the project has been completed, it will serve no purpose to deposit the retention money in a join bank account in the names of the advocates on record for the parties. Since no justification has been given by the Plaintifi for the continued holding of the retention money, I will order that the same be released by the Plaintifi to the 1st Defendant forthwith. The claim for damages, lost opportunity or profit was not established. The Defendants are not entitled to the same. I have dealt with the Defendants’ other claims earlier; it is not necessary to repeat the same here. Who is liable for the costs of the suit and the counter-claim? 184. From the foregoing findings, there is no outright winner in this dispute. Section 27 of the Civil Procedure Act gives the court unfettered discretion on the issue of costs. In the circumstances of this case, I will order each party to bear its own costs. Conclusion: 185. In conclusion, I hereby make the following final orders in the matter; 1. The 1st Defendant shall return forthwith all the keys to the residential apartments on L.R No. 4858/11 known as Ringsview Apartments if the same are still in its possession save as otherwise indicated in this judgment. 2. The 2nd Defendant is retrained from charging, selling, disposing of or transferring apartments A12(A9), A11(A10), B6(B5), B4(B5), C1, A4 and C10 on L.R No. 4858/11 known as Ringsview Apartments until the 2nd Defendant and his associates clear the outstanding balances due to the Plaintifi on the same as determined by the court in this judgment. 3. An injunction is issued restraining the Defendants jointly and severally from dealing with or in any other way interfering with the possession and quiet enjoyment of the residential apartments on L.R No. 4858/11 known as Ringsview Apartments save for those apartments https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 44
page 44 of 45
that were purchased by the 2nd Defendant and his associates for which payments have been made in full or are in the process of being made in full in terms of this judgment. 4. Kshs. 375,000/- is awarded to the Plaintifi against the 2nd Defendant being the balance of the purchase price due on apartments A9(A12), A10(A11) and B5(B6). 5. Kshs. 125,000/- is awarded to the Plaintifi against the 2nd Defendant being the balance of the purchase price due on apartment B4(B5). 6. Kshs. 2,500,000/ is awarded to the Plaintifi against the 2nd Defendant being the balance of the purchase price due on apartments C1 and A4. 7. Kshs. 3,000,000/- is awarded to the Plaintifi against the 2nd Defendant being the balance of the purchase price due on apartment C10. 8. The Plaintifi shall give to the 2nd Defendant and his associates access to and quiet vacant possession of apartments B3 forthwith and apartments A12(A9), A11(A10), B6(B5), B4(B5), C1, A4 and C10 as soon as the 2nd Defendant and his associates pay the balances of the purchase price due in respect thereof in terms of orders 4, 5, 6 and 7 above. 9. An injunction is issued restraining the Plaintifi from charging, selling, transferring or dealing in any other manner with apartments B3 and, with apartments A12(A9), A11(A10), B6(B5), B4(B5), C1, A4 and C10 for a period of 45 days from the date hereof within which the 2nd Defendant and his associates shall pay the balance of the purchase price due in respect thereof in terms of orders 4, 5, 6 and 7 above. 10. Kshs. 21,895,218/- is awarded to the 1st Defendant against the Plaintifi being the retention money. 11. Kshs. 19,338,552/- is awarded to the 1st Defendant against the Plaintifi being the sum due and owing by the Plaintifi to the 1st Defendant on the contract dated 26th July 2011. 12. Kshs. 1,360,000/- is awarded to the 2nd Defendant against the Plaintifi as damages for loss of use of apartment B3. 13. The payments referred to in orders 4, 5, 6, 7, 10, 11 and 12 above shall be made within 45 days from the date hereof. 14. Interest shall accrue on the amounts awarded to all the parties herein at court rates at the expiry of 45 days from the date hereof until payment in full. 15. Each party shall bear its own costs of the suit and the counter-claim. DELIVERED AND DATED AT KISUMU ON THIS 9TH DAY OF FEBRUARY 2023 S.OKONG’O JUDGE Judgment delivered virtually through Microsoft Teams Video Conferencing Platform in the presence of: Ms. Ngonde for the Plaintifi Ms. Ashioya h/b for Dr. Mutubwa for the 1st and 2nd Defendants https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/591/eng@2023-02-09 45
page 45 of 45