Skip to content
AI-generated case briefs sourced from Kenya Law · Not legal advice
AI-generated case brief
Case Brief · caselaw.co.ke
Supreme CourtDismissedApplication 24 of 2019

Langata Development Co Ltd v Dames & another

Supreme Court of Kenya
4 September 2020
556 words in judgment
View original judgmentRead on Kenya LawDownload the judgment (PDF) Watch case
AI-assisted case brief
·~2 min to read original · ~4 min brief

The bottom line

#

Supreme Court denies Langáta's appeal extension for unexplained delay.

What this practically means

#

Langáta Development Company wanted to appeal a Court of Appeal decision but filed late. The Supreme Court said they did not give a good reason for the delay, so it refused to extend the time for filing the appeal. The company also had to pay the other side's legal costs.

Executive summary

#
This is a ruling by a five-judge bench of the Supreme Court of Kenya on an application by Langáta Development Company Limited. The applicant sought two main orders: first, leave to have its Notice of Appeal deemed as lodged within time (extension of time), and second, certification that the intended appeal raises matters of general public importance. The application arose from a judgment of the Court of Appeal delivered on 26th February 2019. The applicant argued that the Supreme Court had jurisdiction to extend time under rule 53 of the Supreme Court Rules and that the matter met the criteria for certification as set out in Hermanus Phillipus Steyn v Giovanni Gnecchi Ruscone. The respondent opposed the application, arguing that the Supreme Court lacked jurisdiction to review the Court of Appeal's decision on certification, that the application was incompetent due to absence of a Notice of Appeal, and that the issues were private in nature. The Supreme Court held that the applicant had not satisfactorily explained the inordinate delay in filing the Notice of Appeal, and therefore declined to exercise its discretion to enlarge time. Consequently, the Court found that the application for certification had no basis and did not consider it. The Court disallowed the Notice of Motion and ordered the applicant to bear the costs of the application.

Questions the Court framed

#

The issues the Court set itself to decide, in its own words.

  1. 1.Whether the applicant has satisfactorily explained the inordinate delay to warrant exercise of the Court's discretion to enlarge time for filing a Notice of Appeal.
  2. 2.Whether the application for certification as a matter of general public importance should be considered.

Key legal issues

#
01

Whether the Supreme Court has jurisdiction to extend time for filing a Notice of Appeal under rule 53 of the Supreme Court Rules.

Holding

The Court implicitly assumed jurisdiction to consider the application for extension of time but declined it on the merits due to lack of satisfactory explanation for the delay.

Reasoning

The Court noted that the applicant invoked rule 53 of the Supreme Court Rules, which gives the Court jurisdiction to extend time. However, after considering the application and noting that the applicant had not satisfactorily explained the inordinate delay, the Court declined to exercise its discretion to enlarge time. The Court did not find it necessary to consider the application for certification as a matter of general public importance because the leave to file a Notice of Appeal was declined.

02

Whether the Supreme Court can review a decision of the Court of Appeal on certification as a matter of general public importance.

Holding

The Court did not reach this issue because the application for leave to file a Notice of Appeal was declined, rendering the certification application moot.

Reasoning

The Court stated that having declined the application for leave to file a Notice of Appeal, the application for certification had no legs to stand on and was not considered. The Court did not address the respondent's argument that the Supreme Court does not have jurisdiction to review the decision of the Court of Appeal on certification.

Legal principles established

#
  • An applicant for extension of time must convincingly explain the entire delay.
  • The Supreme Court has discretion to extend time under Rule 53 of its Rules.
  • If the extension is denied, related applications (like certification) become moot.
  • Costs follow the event; the losing applicant pays the respondent's costs.
  • The court will not presume good cause; the burden is on the applicant.

Court orders

#
  1. 1.The Notice of Motion dated 31st July 2019 is disallowed.
  2. 2.The Applicant shall bear the costs of the application.

The bench

#

One judgment of the whole court — no separate or dissenting opinions.

Philomena Mbete Mwilu
P. M. MwiluDCJ
Currently serving
majority
majority
Smokin Charles Wanjala
S. C. WanjalaSCJ
Currently serving
majority
Njoki Susanna Ndungu
Njoki NdunguSCJ
Currently serving
majority
Isaac Lenaola
I. LenaolaSCJ
Currently serving
majority
On appeal from
Court of Appeal
Jurisdiction invoked
Article 163(4)(b) of the Constitution of Kenya, 2010

Relief refused

#

Leave to have the Notice of Appeal lodged be deemed to have been lodged within time

The applicant has not satisfactorily explained the inordinate delay to warrant exercise of this Court’s discretion to enlarge time

Certification as a matter of general public importance

The application for certification has no legs to stand on because the leave to file a Notice of Appeal was declined

Costs

The Applicant shall bear the costs of the application.

Quotable passages

#

Verbatim from the judgment, each located to the page it appears on in the official PDF — so these can be cited and checked directly.

Having considered the Application, and noting that the Applicant has not satisfactorily explained the inordinate delay to warrant exercise of this Court’s discretion to enlarge time, we do decline to allow the application for leave to file a Notice of Appeal.
p. 2 Extension of time
Having reached this conclusion then, the application for certification has no legs to stand on and we do not find it necessary to consider it.
p. 2 Certification as moot
The Notice of Motion dated 31st July 2019 is disallowed.
p. 2 Final orders
The Applicant shall bear the costs of the application.
p. 2 Costs order

Key timeline

#
2019-02-26
Court of Appeal delivers judgment against Langáta Development Company.
2019-07-31
Langáta files Notice of Motion seeking extension of time and certification.
Unknown
Supreme Court ruling disallowing the application and ordering costs.

Practical implications

#
For lawyers

Prove delay explanations thoroughly

When seeking extension of time, provide a detailed, credible reason for every day of delay. The court will not stretch its discretion. Generic or vague excuses lead to dismissal and costs. Prepare a sworn affidavit accounting for the entire period.

For businesses

Timely appeals are critical

If you lose a case, act fast on appeals. Missing the deadline requires a compelling justification; unexplained delays, even short ones, can forfeit your appeal rights. Also, you risk paying the opponent's costs if the extension is denied.

For individuals

Explain delays clearly to court

As an individual appealing a decision, you must file within the set time. If you are late, you must give a clear, honest reason for the delay. Without a good explanation, the court will likely reject your request and you may have to pay the other side's legal fees.

Frequently asked questions

#
What is the Supreme Court's rule on extending time for filing a Notice of Appeal in Kenya?+

Under Rule 53 of the Supreme Court Rules, the court can extend the time limit. However, the applicant must provide a satisfactory explanation for the delay. The court has discretion to grant or refuse the extension.

Can the Supreme Court of Kenya review a Court of Appeal certification decision?+

In this case, the Supreme Court did not decide that issue because the extension of time was denied first. The question remains open. The Court of Appeal's certification was not reviewed.

What happens if you fail to explain a delay in filing an appeal in Kenya?+

The court is likely to dismiss your application for extension of time. You lose the chance to appeal and may be ordered to pay the other party's costs. The explanation must cover the entire period of delay.

Who bears the costs when an extension of time application is denied in Kenya?+

The applicant who loses the application typically bears the respondent's costs. In this case, Langáta Development Company was ordered to pay costs, which is standard practice in such rulings.

Cite this brief

#

Cite this brief

Caselaw, "Langata Development Co Ltd v Dames & another", Case Analysis (2020). Application 24 of 2019. Source: https://new.kenyalaw.orghttps://new.kenyalaw.org/akn/ke/judgment/kesc/2020/31/eng@2020-09-04

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.