Ex-parte Chamber Summons dated 11/5/2023 (Judicial Review)
The bottom line
#Kenya's High Court struck out a stalled application against the Government because the applicant lacked a Section 21 Certificate of Order, a mandatory step before enforcing judgments against the state.
What this practically means
#Executive summary
#Key legal issues
#Requirement of a Certificate of Order under Section 21 of the Government Proceedings Act
The application was struck out for want of the statutory certificate and for want of prosecution
The Chamber Summons had been pending since 11/5/2023 without prosecution. On perusal of the application and supporting documents, the court found no Certificate of Order against the Government, a mandatory prerequisite under Section 21 of the Government Proceedings Act for orders against the Government. The application was therefore struck out and the file closed.
Legal principles established
#- An application to enforce or execute against the Government requires a Certificate of Order under Section 21 of the Government Proceedings Act before it can proceed
Court orders
#- 1.The application dated 11/5/2023 is struck out
- 2.The file is closed
- 3.Applicant's Counsel to be notified via email
- Jurisdiction invoked
- Not stated in judgment (judicial review proceedings; Government Proceedings Act, Section 21 engaged)
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Ex-parte Chamber Summons dated 11/5/2023 (Judicial Review)", Case Analysis (2025). . Source: https://new.kenyalaw.org/akn/ke/judgment/kehc/
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.