High CourtPartially AllowedMiscellaneous Application No. 431 of 2019

Set and Sit Contractors Ltd v Mare Nostrum Limited

High Court of Kenya
21 May 2020
7,174 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~29 min to read original · ~4 min brief

The bottom line

#

Kenyan courts strongly uphold arbitral awards, meaning challenging them based on factual errors or procedural disagreements is extremely difficult.

What this practically means

#

Executive summary

#
This ruling by W. A. Okwany J of the High Court at Nairobi determined two concurrent applications arising from a construction dispute over a tourist resort built under a Building Agreement dated 12th August 2013. Set and Sit Contractors Ltd (the Contractor) sought recognition and enforcement of a Final Arbitral Award dated 5th August 2019 awarding it USD 1,258,231.67 with simple interest at 14% per annum from 28th August 2015. Mare Nostrum Ltd (the Owner) sought to set aside the award under Section 35 of the Arbitration Act, alternatively remittal for corrective action, arguing the arbitrator violated its right to be heard by relying on undisclosed site-visit observations, imposed his own percentage-completion methodology, disregarded both parties' expert evidence, failed to give reasons, and exceeded the scope of the reference. The court considered the setting-aside application first. On scope, it found the arbitrator determined only the agreed issues and did not go on a frolic of his own. On public policy, applying Christ for All Nations v Apollo Insurance, it held the owner received notice, called six witnesses and filed submissions; the agreed site visit became part of the evidence and the arbitrator's observations need not be cross-examined; the arbitrator gave reasons for rejecting both experts' reports; and errors of fact or law cannot constitute a conflict with public policy, which leans towards finality of arbitral awards. The setting-aside application was dismissed with costs to the contractor, and the recognition and enforcement application was allowed with costs.

Key legal issues

#
01

Whether the arbitrator exceeded the scope of the reference

Holding

The arbitrator determined only the issues in the agreed list of issues and did not go beyond the scope of reference

Reasoning

The court compared the agreed list of issues dated 22nd June 2017 with the arbitrator's determinations and found each issue was addressed. The award of USD 1,258,231.67 was within the amounts claimed. The owner failed to show the arbitrator went on a frolic of his own dealing with matters unrelated to the dispute.

p. 6
02

Whether reliance on undisclosed site-visit observations violated the right to be heard and offended public policy

Holding

No violation: the site visit was agreed, the site became evidence, and the arbitrator's findings flowed from evidence, legal principles and the contract, not solely his observations

Reasoning

The owner received notice, called six witnesses and filed submissions. The court held that requiring an arbitrator's observations to be cross-examined would make the arbitrator a witness. The arbitrator gave reasons for rejecting both experts' reports and applied a percentage-completion methodology grounded in legal principle (ERDC Group v Brunel University) and the contract bills of quantities.

p. 7
03

Whether the award was contrary to public policy under Section 35(2)(b)(ii)

Holding

The award was not inconsistent with the Constitution, laws, national interest, justice or morality; the owner's complaint amounted to an impermissible appeal on errors of fact and law

Reasoning

Applying Christ for All Nations v Apollo Insurance, the court found the impugned findings neither an affront to the Constitution nor inimical to justice and morality. It would be contra-public policy to allow an owner who admittedly did not pay its contractor to retain the benefit of the works. Errors of fact or law are not grounds for setting aside.

p. 10
04

Whether the arbitrator failed to give reasons under Section 32(3) of the Act

Holding

The arbitrator provided reasons for his findings, including his rejection of both parties' expert reports

Reasoning

The court quoted the arbitrator's explanation that neither expert provided a scientific methodology for completion percentages, and that the tribunal would rely on other evidence and the contract. The court found the challenge untenable since the arbitrator is the master of the facts.

p. 9

Legal principles established

#
  • Once parties agree to a site visit, the site becomes part of the evidence like any other evidence, and an arbitrator's observations thereon need not be subjected to cross-examination by the parties
  • An error of fact or law by an arbitrator cannot be said to be inconsistent with the public policy of Kenya; public policy leans towards finality of arbitral awards
  • To show that an arbitrator went beyond the scope of the reference, the applicant must show beyond doubt that the arbitrator went on a frolic of his own

Court orders

#
  1. 1.Dismissal of the application dated 4th November 2019 with costs to the contractor
  2. 2.Allowance of the application dated 26th September 2019 with costs to the Contractor
  3. 3.Recognition and enforcement of the Final Arbitral Award dated 5th August 2019 as a judgment of the court
Jurisdiction invoked
Section 35 of the Arbitration Act, 1995 (recourse to the High Court against an arbitral award)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Set and Sit Contractors Ltd v Mare Nostrum Limited", Case Analysis (2020). Miscellaneous Application No. 431 of 2019. Source: 

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.