ELRCDismissedML & SP/DOSHS/WIBA/KBU/296/2024 (Appeal)· [2025] KEELRC 1524 (KLR)

Omuchele v Shreerang Enterprises Limited (Employment and Labour Relations Appeal E256 of 2024) [2025] KEELRC 1524 (KLR)

Employment and Labour Relations Court
23 May 2025
1,582 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~6 min to read original · ~4 min brief

The bottom line

#

The Employment and Labour Relations Court confirmed that Kenyan work injury compensation must use a 96-month multiplier and the wages stated in the DOSH Form 1.

What this practically means

#

Executive summary

#
The appellant, injured on 3rd June 2023 when he fell from the second storey of a building at the respondent's Kikuyu work site, claimed work injury compensation before the Director of Occupational Safety and Health Services (DOSH). On 24th June 2024 the Director designated 100% disability and awarded Kshs. 1,209,600 using monthly earnings of Kshs. 11,700 and a 96-month multiplier. After the appellant's objection, the Director on 5th August 2024 vacated that Demand for Payment and issued an Amended one using monthly earnings of Kshs. 15,201.65. The appellant then appealed to this Court, seeking variation of the decision to reflect a multiplier of 312 months and adoption of the Amended Demand for Payment as judgment. The appeal was canvassed by written submissions; only the appellant filed. The court, guided by Selle v Associated Motor Boat Co. and Mbogo v Shah, identified the issue as whether the appeal was merited. It held that section 30 of the Work Injury Benefits Act mandates compensation for permanent disablement on the basis of ninety-six months earnings, that the Director's jurisdiction is confined to WIBA, and that no different multiplier was applicable. On wages, the court held the Director was bound to apply the wages stated in Form 1 (Kshs. 450 per day as a casual), and that any claim of underpayment lies before the Court, not the Director. The appeal was dismissed, the DOSH award of 24th June 2024 was upheld and adopted as the judgment of the Court, the respondent was ordered to settle Kshs. 1,209,600 by deposit with DOSH within 30 days, with no orders as to costs, and the file was marked closed.

Key legal issues

#
01

Correct multiplier under section 30 of WIBA

Holding

The statutorily mandated multiplier of 96 months applies; no different multiplier could be adopted outside section 30 of WIBA

Reasoning

Section 30(1) of WIBA provides that compensation for permanent disablement shall be calculated on the basis of ninety-six months earnings subject to minimum and maximum amounts set out in the Third Schedule. The Director draws his assessment powers from WIBA, and acting contrary to section 30 would exceed his jurisdiction. The court therefore held that the Director correctly applied the 96-month multiplier and refused the appellant's request for 312 months.

p. 4
02

Applicable wages in the computation

Holding

The Director is bound to apply the wages disclosed in DOSH/Form 1, which stated the appellant was a casual earning Kshs. 450 per day

Reasoning

The appellant alleged he was a general labourer entitled to minimum wage of Kshs. 15,201. Form 1 did not state he was a general labourer, and the wages disclosed were not denied as having been paid at the time of injury. The court held that claims of underpayment/unfair labour practices lie before the Court, not the Director, who has no jurisdiction outside WIBA. The Director therefore rightly applied the Form 1 wages.

p. 4
03

Appellate interference with the Director's decision

Holding

The court found no basis to disturb the DOSH award, applying the Mbogo v Shah principle on non-interference with discretionary decisions

Reasoning

Guided by Selle v Associated Motor Boat Co. and Mbogo v Shah, the court reconsidered the material but found the Director's assessment legally sound both on the multiplier and the wages. The appeal was therefore dismissed and the original award of 24th June 2024 upheld and adopted as the judgment of the Court.

p. 4

Legal principles established

#
  • Compensation for permanent disablement under WIBA must be calculated on the basis of ninety-six months earnings, and the Director's jurisdiction is confined to WIBA
  • Jurisdiction flows from the Constitution and/or legislation, and a tribunal acting outside its statutory framework would be without jurisdiction

Court orders

#
  1. 1.The appeal is dismissed for lack of merit
  2. 2.The award of DOSH of 24th June 2024 is upheld and adopted as judgment of the Court
  3. 3.The Respondent to settle the claim as awarded by DOSH on 24th June 2024 for the sum of Kshs. 1,209,600 by deposit of the total sum with the DOSH in 30 days
  4. 4.No orders as to costs in the appeal
  5. 5.The file is marked as closed

Authorities

#

Legislation

  • Work Injury Benefits Act (Chapter 236, Laws of Kenya)section 30; First Schedule; Third Schedule

Cases cited (3)

  • Selle v Associated Motor Boat Co.
    [1968] EA 123
  • Mbogo V Shah
    [1968] EA Page 93
  • Samuel Kamau Macharia & Another v Kenya Commercial Bank Limited & 2 others
    [2012] e KLR (paragraph 68)
On appeal from
Director of Occupational Safety and Health Services
ML & SP/DOSHS/WIBA/KBU/296/2024
Jurisdiction invoked
First appeal from the Director of Occupational Safety and Health Services under the Work Injury Benefits Act (Chapter 236, Laws of Kenya)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Omuchele v Shreerang Enterprises Limited (Employment and Labour Relations Appeal E256 of 2024) [2025] KEELRC 1524 (KLR)", Case Analysis (2025). ML & SP/DOSHS/WIBA/KBU/296/2024 (Appeal). Source: https://new.kenyalaw.org/akn/ke/judgment/keelrc/2025/1524/eng@2025-05-23

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.