Skip to content
AI-generated case briefs sourced from Kenya Law · Not legal advice
AI-generated case brief
Case Brief · caselaw.co.ke
ELRCDismissedNotice of Motion dated 29th June 2023 (ELRC, Nyeri)· [2024] KEELRC 66 (KLR)

Ndungu v Segera Limited (Cause E008 of 2022) [2024] KEELRC 66 (KLR)

Employment and Labour Relations Court
26 January 2024
2,437 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~10 min to read original · ~4 min brief

The bottom line

#

A Kenyan court confirmed an omitted claim can be reviewed, but still dismissed the worker's overtime and rest day claims for lack of evidence and delay.

What this practically means

#

Executive summary

#
Following a judgment of 26th May 2023 in which the court declared the claimant's dismissal unfair and awarded him Kshs. 552,420 as compensatory damages, the claimant moved the court by Notice of Motion dated 29th June 2023 seeking review of the judgment on the ground that his claims for overtime (Kshs. 4,347,000) and twenty-four rest days (Kshs. 294,624), pleaded in paragraph 27 of the Memorandum of Claim, had been left undetermined. He relied on Rule 33 of the ELRC Rules and Order 45 of the Civil Procedure Rules, invoking the doctrine of error apparent on the face of the record. The respondent opposed, arguing the decretal sum and taxed costs had been paid in full, the application was an afterthought, and the claimant, being management staff, was not entitled to overtime and had produced no supporting material. The court found the application was brought after unreasonable delay since the claimant waited for settlement of the decree before seeking more, but nonetheless considered the merits. It confirmed that the failure to determine the overtime and rest day claims was a mistake or error apparent on the face of the record meeting the review threshold. However, on determining the omitted claims itself, the court found the overtime claim lacked material particulars, was exaggerated, and lacked proof of management authorisation required by clause 5 of the appointment letter, while the rest day claim was unsupported and inconsistent with an undisputed payment of Kshs. 116,622 for off days. The court declined to vary the judgment and dismissed the application with costs.

Key legal issues

#
01

Whether the application was brought after unreasonable delay

Holding

The application was brought after unreasonable delay; the claimant waited for settlement of the decree and costs before seeking more, making it an afterthought, though the court still considered its merits.

Reasoning

The court noted judgment was delivered on 26th May 2023 and the application dated 29th June 2023. The respondent argued the delay was inordinate since the decretal sum and taxed costs had been paid in full. The court agreed that the claimant, if dissatisfied, should have challenged the decree first rather than waiting for settlement before returning to court for more.

p. 3
02

Whether the failure to determine the overtime and rest day claims was an error apparent on the face of the record

Holding

Yes - the court confirmed it had not determined the claims for overtime and rest days, and that failure was a mistake or error apparent on the face of the record meeting the review threshold.

Reasoning

Relying on National Bank of Kenya v Ndungu Njau and Nyamogo and Nyamogo v Kogo, the court held that an error or omission apparent on the face of the record is one that is self-evident and requires no elaborate argument. The omission of the pleaded claims in paragraph 27 of the Memorandum of Claim from the judgment was obvious and announced itself clearly.

p. 3
03

Whether the claimant proved his claim for overtime

Holding

No - the claim for overtime lacked material particulars, was exaggerated, and was not proved; in particular there was no proof of the management authorisation required by clause 5 of the appointment letter.

Reasoning

Clause 5 of the appointment letter required overtime to be first approved by management, and no such authorisation was produced. The claim covered almost four years yet email complaints of workload related only to the period from 2020. The pleaded claim assumed no leave was ever taken, which was not the case. Being a special damages claim, it had to be specifically pleaded and proved on a balance of probabilities.

p. 5
04

Whether the claim for 24 rest days not taken was proved

Holding

No - the claim failed for lack of material particulars and supporting evidence; the claimant had already been compensated Kshs. 116,622 for off days per his June 2021 payslip, which he never factored into his pleadings.

Reasoning

The claimant assessed 24 rest days at Kshs. 294,624, being double daily wages, but produced no cogent proof of the number of days. The respondent's production of the June 2021 payslip showing compensation for off days was undisputed and unreconciled by the claimant. The burden was on the claimant to plead specifically and adduce evidence; he could not rely on the respondent's default.

p. 5

Legal principles established

#
  • A claim for overtime work is a claim for special damages which must be specifically pleaded and proved by the claimant on a balance of probabilities; the claimant cannot prove his claim through the respondent's default in adducing evidence.
  • Failure by a court to determine a claim pleaded before it constitutes a mistake or error apparent on the face of the record capable of grounding review.

Court orders

#
  1. 1.The request to vary the judgment of 26th May 2023 was declined
  2. 2.The application was dismissed with costs

Authorities

#

Legislation

  • Civil Procedure Actsections 1A, 1B, 3A, 80
  • Civil Procedure RulesOrder 9 rule 9; Order 45 rules 1, 2 and 3
  • Employment and Labour Relations Court Rules, 2016Rule 33(1); Rule 28(3)
  • Employment Actsection 27(2)

Cases cited (3)

  • National Bank of Kenya v Ndungu Njau
    [1997] eKLR
  • Martin Muleshe Shiroko v Wanjohi Consulting Engineers Limited
    [2016] eKLR
  • Nyamogo and Nyamogo v Kogo
    [2001] EA 174
Jurisdiction invoked
Rule 33 of the Employment and Labour Relations Court Rules, 2016; sections 1A, 1B, 3A, 80 of the Civil Procedure Act; Order 45 rules 1, 2 and 3 of the Civil Procedure Rules

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Ndungu v Segera Limited (Cause E008 of 2022) [2024] KEELRC 66 (KLR)", Case Analysis (2024). Notice of Motion dated 29th June 2023 (ELRC, Nyeri). Source: https://new.kenyalaw.org/akn/ke/judgment/keelrc/2024/66/eng@2024-01-26

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.