ELRCPartially AllowedCause (not stated in judgment text; Industrial Court claim filed 12th February 2014)· [2018] KEELRC 2208 (KLR)

Tailors and Textile Workers Union v Global Apparels (EPZ) Limited [2018] KEELRC 2208 (KLR)

Industrial Court of Kenya (Employment and Labour Relations Court)
27 February 2018
2,339 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~9 min to read original · ~4 min brief

The bottom line

#

A Kenyan employment court awarded factory workers a 5% pay rise after their union and employer couldn't agree, rejecting demands for more.

What this practically means

#

Executive summary

#
The Claimant union filed this suit on 12th February 2014 seeking a general wage increment and an effective date and duration for a Collective Bargaining Agreement with the Respondent, an EPZ cut-make-trim apparel manufacturer. The parties, through a conciliator appointed by the Ministry of Labour, agreed on all but two clauses of the CBA: general wage increment and the effective date. The Union sought a 10% increment above the Government Wages Order for each of two years, arrears payable within 30 days with 16% interest, and a security bond of Kshs. 8,000,000 citing the collapse of sister EPZ firms whose directors fled without paying benefits. It also asked the court to treat the Respondent's failure to comply with a prior award in Cause No. 106 of 2006 as contempt. The Respondent offered only 0.5%, citing a cash crunch, loss of contractors after the post-election violence, competition from Asian manufacturers, and its dependent CMP business model; it produced only 2011/2012 financial returns. The court considered the report of the Central Planning and Monitoring Unit showing growth in unionisable staff, labour costs and the wage bill up to 2014. It awarded a 5% general wage increment, with effect from signing of the CBA within 30 days, and in default, effective within 30 days of judgment. The 10% demand, the security bond, the contempt plea and the 16% interest claim were not granted. The judgment was delivered by Hon. Lady Justice Hellen Wasilwa on 27th February 2018.

Key legal issues

#
01

General wage increment for the 2005/2007 CBA period

Holding

A 5% wage increment awarded, midway between the Union's 10% demand and the Respondent's 0.5% offer

Reasoning

The court considered the CPMU report showing growth in unionisable staff, labour cost and the wage bill up to 2014, the Respondent's claims of financial hardship and competition, and the inflationary trend. The Respondent filed only 2011/2012 returns. Balancing these, the court found 5% appropriate rather than the Union's 10% or the Respondent's 0.5%.

p. 3
02

Effective date of the CBA

Holding

Effective date is upon signing of the CBA, to be within 30 days, failing which the increment takes effect within 30 days of the judgment

Reasoning

The parties had agreed 35 (or 33, per the Respondent) clauses but disagreed on the effective date. The Union sought retrospective effect given 11 years of static wages; the Respondent sought the date of the award. The court chose a date tied to signing of the CBA within 30 days, with a default position tied to the judgment date.

p. 3
03

Whether a security bond should be ordered

Holding

No security bond ordered

Reasoning

The Union sought a Kshs. 8,000,000 bond citing closures of MRC, Rising Sun and Mirage and directors fleeing without paying benefits. The Respondent submitted it is a separate and distinct legal entity with no plans of shutting down. The court made no such order in the final orders.

p. 3

Legal principles established

#
  • Section 15(5) of the Industrial Court Act (now repealed), synonymous with Section 15(5) of the Employment and Labour Relations Act, is a guide and not a substitute for the court's own decision on the economic circumstances before it
  • Where parties agree on a CBA save for limited clauses, the court may award on the disputed clauses after considering the parties' economic circumstances and reports

Court orders

#
  1. 1.A general wage increment of 5% is awarded
  2. 2.The effective date of the CBA shall be upon signing of the Collective Bargaining Agreement, which should be within 30 days
  3. 3.In default of signing within 30 days, the increment takes effect within 30 days from the date of the judgment

Authorities

#

Legislation

  • Industrial Court ActSection 15(5)
  • Employment and Labour Relations ActSection 15(5)

Cases cited (2)

  • Cause No. 106 of 2006 (award by Hon. Justice Isaac E. K. Mukunya delivered 16th November 2007)
  • High Court Petition No. 43 of 2008
Jurisdiction invoked
Reference of a trade dispute to the Industrial Court for arbitration following failure of conciliation under the Labour Relations Act; Section 15(5) of the Industrial Court Act No. 20 of 2011 (now repealed, synonymous with Section 15(5) of the Employment and Labour Relations Act) cited as a guide.

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Tailors and Textile Workers Union v Global Apparels (EPZ) Limited [2018] KEELRC 2208 (KLR)", Case Analysis (2018). Cause (not stated in judgment text; Industrial Court claim filed 12th February 2014). Source: https://new.kenyalaw.org/akn/ke/judgment/keelrc/2018/2208/eng@2018-02-27