ELRCPartially AllowedCause No. 1970 of 2015 (Application dated 22.9.2015)· [2016] KEELRC 1537 (KLR)

Ann Wambui Kamuiru v Kenya Airways Limited [2016] KEELRC 1537 (KLR)

Employment and Labour Relations Court
8 March 2016
3,459 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~14 min to read original · ~4 min brief

The bottom line

#

Kenya's Employment Court ruled Kenya Airways' disciplinary process against its employee was rushed and flawed, and ordered the company to redo it properly.

What this practically means

#

Executive summary

#
The Claimant, a Marketing Manager (East Africa and JV) at Kenya Airways, filed a notice of motion dated 22 September 2015 under Sections 12 and 20 of the Employment and Labour Relations Court Act seeking interim orders restraining the Respondent from continuing disciplinary action commenced by a show cause letter dated 23 July 2015 and a panel hearing held on 18 September 2015, and from terminating, demoting or otherwise adversely acting against her. She argued that the process breached Clause 17 of the Respondent's HR Policies and Manual: no investigation and report preceded the formal process, the informal disciplinary procedure was bypassed, she was not furnished with all evidence, and the panel included her immediate boss, Jackline Muhati, whom she had complained against, breaching natural justice. The Respondent, through a Replying Affidavit of David Rimberia, denied bias, asserting compliance with its Disciplinary Procedures and that the hearing was fair and unobjected to. The Court framed two issues: whether the disciplinary process breached the law and the Respondent's own rules, and whether the Court can intervene before conclusion of an internal disciplinary process. It held that employers must ensure due process, fair hearing and natural justice, and that courts intervene in flawed processes not to stop them but to correct course. Finding no evidence of the informal disciplinary process, the Court declared the process hurried and irregular and directed the Respondent to initiate proper processes under the law and HR Manual within 30 days.

Key legal issues

#
01

Breach of the employer's HR Manual disciplinary procedure

Holding

The disciplinary process was flawed because the employer skipped the informal disciplinary procedure and went straight to formal process

Reasoning

The Respondent's HR Policies Manual prescribes two forms of disciplinary handling: informal procedure for minor misconduct and formal procedure for gross misconduct or failure to improve after informal counselling. The Claimant contended the formal process was initiated without exhausting the informal one. The Court found no evidence that any informal disciplinary process ever took place, which showed the ongoing process was flawed in one way or another.

p. 7
02

Court's power to intervene in ongoing internal disciplinary procedures

Holding

The Court has power to intervene where the process is marred with irregularities, but the intervention is corrective, not prohibitive

Reasoning

Relying on Rebecca Ann Maina & 2 Others v JKUAT and Aviation & Allied Workers Union v Kenya Airways, the Court held that courts will not interfere with proper internal disciplinary processes unless satisfied the process is marred with irregularities or stage-managed towards dismissal. Finding the process hurried and flawed, the Court directed the Respondent to initiate proper processes under the law and its HR Manual within 30 days.

p. 7

Legal principles established

#
  • An employer who commences disciplinary proceedings must ensure due process, fair hearing and due regard to natural justice; courts will not interfere with proper internal disciplinary processes unless marred by irregularities or stage-managed towards dismissal
  • The court's intervention in flawed disciplinary processes is corrective rather than prohibitive

Court orders

#
  1. 1.Declared the disciplinary process initiated against the Applicant hurried and marred with irregularities
  2. 2.Directed the Respondent to correct the process by initiating proper processes as per the law and their HR Manual within 30 days
  3. 3.Each party at liberty to apply

Authorities

#

Legislation

  • Employment and Labour Relations Court ActSections 12, 20
  • Industrial Court (Procedure) RulesRule 16

Cases cited (2)

  • Rebecca Ann Maina & 2 Others vs. JKUAT
    Industrial Cause No. 1789/2013
  • Aviation & Allied Workers Union vs. Kenya Airways Limited
    Cause 324/2012
Jurisdiction invoked
Sections 12 and 20 of the Employment and Labour Relations Court Act, Rule 16 of the Industrial Court (Procedure) Rules

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Ann Wambui Kamuiru v Kenya Airways Limited [2016] KEELRC 1537 (KLR)", Case Analysis (2016). Cause No. 1970 of 2015 (Application dated 22.9.2015). Source: https://new.kenyalaw.org/akn/ke/judgment/keelrc/2016/1537/eng@2016-03-08

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.