The bottom line

#

A Kenyan court converted a negotiated Kshs.77,000 settlement into an enforceable judgment payable in instalments after a worker's unfair termination claim.

What this practically means

#

Executive summary

#
This was a first-instance employment dispute before the Industrial Court at Mombasa, Cause No. 412 of 2013, in which Lawrence Kosgey claimed against Portnet Engineering Services T/A Gee & Pikii Limited over unfair and unlawful termination of employment. The Claimant filed his Statement of Claim on 26th November 2013 and the Respondent filed its Statement of Response on 15th January 2014. The matter did not proceed to a full hearing on the evidence. On 3rd March 2015, advocates for the respective parties informed the Court that they had reached a settlement, whose terms were: judgment entered for the Claimant for Kshs.77,000 all inclusive; payment in six equal monthly instalments of Kshs.12,833 effective 30th April 2015 and on the 30th day of each succeeding month; and in default, the Claimant to be at liberty to execute. The Court, per Rika J, expressed satisfaction that the proposed terms of settlement were fair, adequate, regular and made in accordance with the law, and ordered an award entered in terms of the parties' proposal. The award was dated and delivered at Mombasa on 3rd March 2015, with Benjamin Kombe as Court Assistant; Mr. Magia holding brief for Mr. Mwarandu appeared for the Claimant and Mr. Wachira for the Respondent. No costs order was separately made, the award being all inclusive, and no authorities were cited.

Key legal issues

#
01

Adoption of a consent settlement in an unfair and unlawful termination claim

Holding

The Court adopted the parties' settlement as an award, entering judgment for the Claimant for Kshs.77,000 all inclusive, payable in instalments, with liberty to execute in default.

Reasoning

The dispute over unfair and unlawful termination was resolved by the advocates on 3rd March 2015 through agreed terms: an all-inclusive award of Kshs.77,000 payable in six equal monthly instalments of Kshs.12,833 beginning 30th April 2015, with execution in default. The Court, exercising its supervisory role over settlements, was satisfied the terms were fair, adequate, regular and lawful, and adopted them as its order.

p. 2

Legal principles established

#
  • The Court may adopt consented settlement terms as an award where satisfied they are fair, adequate, regular and made in accordance with the law.

Court orders

#
  1. 1.Judgment entered for the Claimant for Kshs.77,000 all inclusive, payable in 6 equal monthly instalments of Kshs.12,833 effective 30th April 2015 and on the 30th day of each succeeding month
  2. 2.In default of payment, the Claimant be at liberty to execute
  3. 3.Award entered in terms of the Parties' proposal
Jurisdiction invoked
Jurisdiction of the Industrial Court over disputes in employment (issue in dispute: unfair and unlawful termination)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Lawrence Kosgey v Portnet Engineering Services t/a Gee & Pikii Limited [2015] KEELRC 1347 (KLR)", Case Analysis (2015). Cause No. 412 of 2013. Source: https://new.kenyalaw.org/akn/ke/judgment/keelrc/2015/1347/eng@2015-03-03

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.