The bottom line

#

What this practically means

#

Executive summary

#
The Claimant, Flora Njoki Mwangi, sued Family Bank Ltd for wrongful and unlawful termination, seeking terminal dues, damages of Kshs 7,388,499.99, a certificate of service, costs and interest. Together with the Memorandum of Claim she filed a motion under section 12 of the Industrial Court Act and rule 36 of the Industrial Court Rules, 2010, seeking to restrain the Bank from advertising, selling or realising two charged properties, Bahati/Kabatini/Block 1/6018 and Naivasha/Mwicirigi 4/4909. Ongaya J granted interim orders on 28 July 2014. The Respondent entered appearance, filed a replying affidavit contesting the competency of the application and a preliminary objection that the court lacked jurisdiction over property disputes. Before the preliminary objection was argued, the Claimant filed an Amended Memorandum of Claim and supplementary affidavit without leave, contending that pleadings had not closed. The court held, without determining the jurisdictional question, that the injunctive orders in the motion were not anchored on pleadings in a substantive suit, rendering the motion incompetent. It struck out the motion and vacated the interim orders granted on 28 July 2014. On procedure, the court held that pleadings closed on 21 August 2014 when no Response was filed as ordered, so both parties needed leave for out-of-time filings. However, applying the objectives of the Industrial Court Act and finding no injustice to the Respondent, the court admitted the Amended Memorandum of Claim, directed service, and ordered the Respondent to respond within 14 days. There was no order as to costs on the struck-out motion.

Key legal issues

#
01

Competency of the motion of 25 July 2014

Holding

The motion was incompetent and the interim orders granted on 28 July 2014 could not stand because they were not anchored on pleadings in a substantive suit.

Reasoning

The court found that the injunctive orders restraining disposal of the charged properties had no pleading basis, since the only pleadings on file were the Memorandum of Claim on termination and the motion itself. On that basis alone, without deciding the jurisdictional objection raised by the Respondent, the court struck out the motion and vacated the interim orders.

p. 2
02

Closure of pleadings and amendment without leave

Holding

Pleadings closed on 21 August 2014 when no Response was filed by the court-ordered date; the Claimant could not amend without leave.

Reasoning

The court held that the Claimant's submission that pleadings had not closed had no legal or factual foundation. The Respondent was ordered on 30 July 2014 to file a Response by 21 August 2014, and failing that, pleadings closed. Both parties were then obliged to seek leave for out-of-time filings, though the court admitted the amendment in furtherance of the objectives of the Industrial Court Act.

p. 2

Legal principles established

#
  • Interim injunctive relief must be anchored on pleadings in a substantive suit; a motion unsupported by pleadings is incompetent.
  • Once the time for filing a Response lapses without a Response, pleadings close and a party must seek leave with sufficient reasons to amend or file out of time.

Court orders

#
  1. 1.The motion dated 25 July 2014 struck out
  2. 2.The interim orders granted on 28 July 2014 vacated
  3. 3.The Amended Memorandum of Claim admitted, to be served upon the Respondent
  4. 4.The Respondent to file and serve a Response within 14 days of service
  5. 5.No order as to costs on the motion

Authorities

#

Legislation

  • Industrial Court Actsection 12
  • Industrial Court Rules, 2010rule 36
  • Industrial Court (Procedure) Rules, 2010
Jurisdiction invoked
Section 12 of the Industrial Court Act and rule 36 of the Industrial Court Rules, 2010

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Flora Njoki Mwangi v Family Bank Limited [2014] KEELRC 1365 (KLR)", Case Analysis (2014). Memorandum of Claim filed 28 July 2014 (motion dated 25 July 2014). Source: https://new.kenyalaw.org/akn/ke/judgment/keelrc/2014/1365/eng@2014-10-17

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.