#Kenya's Employment Court can force an employer to deposit the claimed amount in court if there's a real risk it won't pay an award.
What this practically means
#Executive summary
#Key legal issues
#Whether security for the claim amount should be ordered where the employer is allegedly relocating out of the jurisdiction
The court found the Claimant's fears well founded, noting an arguable case and the Respondent's reluctance to pay undisputed dues and undisclosed divestiture plans, and ordered the deposit.
The court was satisfied that the claim was arguable. It also noted that it took a court order for the Respondent to pay admitted dues, and that the Respondent had lost Kenyan contracts and was moving into South Sudan without disclosing the extent of divestiture or its financial health. Those circumstances justified securing the claim sum by deposit in court.
Legal principles established
#- An employee who advances an arguable case and shows a real fear that the employer may not be able to satisfy an award may obtain security-for-claim in the form of a deposit in court
Court orders
#- 1.The Respondent to deposit the sum of Kshs. 396,092 in Court within thirty (30) days from the date of the Ruling
- 2.Costs of the application to be in the cause
- Jurisdiction invoked
- Original employment and labour relations jurisdiction under the Industrial Court Act (Article 162(2) of the Constitution not expressly cited in judgment)
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Festus Kirema Muthuku v Mellech Engineering & Construction Ltd [2013] KEELRC 889 (KLR)", Case Analysis (2013). Not stated in judgment. Source: https://new.kenyalaw.org/akn/ke/judgment/keelrc/2013/889/eng@2013-11-13
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.