Kenya Engineering Workers Union v Elite Trailers Limited [2013] KEELRC 715 (KLR)
The bottom line
#A Kenyan union lost its wage-implementation claim because it brought no pay slips, computations or affidavits proving workers were underpaid.
What this practically means
#Executive summary
#Key legal issues
#Burden of proof on the Union to demonstrate non-implementation of the Collective Bargaining Agreement wage rates
The claim failed because the Union adduced no evidence of the alleged arrears or underpayment
The Court accepted that the parties adopted the CBA between the Minor Engineering Employers Group and the Union. The Union asserted underpayment, but the Respondent exhibited a schedule showing arrears paid in August 2008 and pleaded that wages were adjusted. The Union offered no computation of arrears, no pay slips and no affidavits, so the Court could not conclude that the Respondent failed to implement the agreed rates. The claim was dismissed with no order as to costs.
Legal principles established
#- A party alleging non-implementation of CBA wage rates must place before the Court material, such as a computation of arrears, pay slips or affidavits, upon which the claim can be evaluated
Court orders
#- 1.The Cause is dismissed
- 2.No order as to costs
- 3.The Deputy Registrar is directed to return this file to Nairobi after delivery of this judgment
- Jurisdiction invoked
- Jurisdiction as Industrial Court seized of the trade dispute referred under the Labour Relations framework; not expressly cited in the judgment
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Kenya Engineering Workers Union v Elite Trailers Limited [2013] KEELRC 715 (KLR)", Case Analysis (2013). Not stated in judgment. Source: https://new.kenyalaw.org/akn/ke/judgment/keelrc/2013/715/eng@2013-08-23
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.