Juliette Mugambi & Another v Summerville Properties Limited
The bottom line
#What this practically means
#Executive summary
#Questions the Court framed
#The issues the Court set itself to decide, in its own words.
- 1.Whether the Plaintiffs/Applicants have met the threshold for leave to amend the Plaint
Key legal issues
#Whether the proposed amendments introduce a new cause of action
The amendments do not introduce a new cause of action; they arise from the same construction activities underlying the original suit and merely particularise consequences suffered
The original cause of action arose from construction on L.R. No. 28428/80 affecting the Plaintiffs' property. The proposed amendments concern expenses for alternative accommodation and repairs flowing from the same activities, which occurred while the case was pending. The amendment confers no automatic advantage, as the Plaintiffs must still prove their case on a balance of probabilities.
Whether the lateness of the application (matter certified ready for hearing) bars the amendment
Lateness does not oust the court's jurisdiction; amendments may be allowed at any stage before judgment where no prejudice is demonstrated
The Respondent argued the application came after certification for hearing and would delay the suit. The court held this contradicts the purpose of amendment, that certification does not remove jurisdiction, and that this was an opportune moment since hearing had not commenced. No prejudice was demonstrated by the Respondent.
Legal principles established
#- Amendments to pleadings may be made at any time before judgment with sufficient cause, provided no prejudice is caused to the opposing party
- An amendment adding or substituting a new cause of action is permissible if it arises out of the same or substantially the same facts as a cause of action already claimed
Court orders
#- 1.The Notice of Motion dated 28th January, 2026 is allowed as prayed
- 2.The Plaintiff is to file and serve the amended Plaint within 7 days
- 3.The Respondent is to file an amended Defence, if need be, within 7 days upon service
The bench
#One judgment of the whole court — no separate or dissenting opinions.
Wrote the judgment
- Jurisdiction invoked
- Original civil jurisdiction of the Environment and Land Court; Article 159(2)(d) of the Constitution of Kenya, 2010 invoked on procedural technicalities
Quotable passages
#Verbatim from the judgment, each located to the page it appears on in the official PDF — so these can be cited and checked directly.
Consequently, I find that the Notice of Motion dated 28 th January, 2026, has merit and is therefore allowed as prayed. The Plaintiff is to file and serve the amended Plaint within 7 days; the Respondent is to file an amended Defence, if need be, within 7 days upon service.
This would be a perfect time to allow the amendment before the commencement of the hearing of the suit.
The amendment will not automatically give the plaintiffs an advantage, as the plaintiffs must prove their case on a balance of probabilities.
The person applying for amendment must be acting in good faith.
Issues in the judgment
#Property location inconsistently described across the judgment
Chronology anomaly: suit numbered E132 OF 2026 with motion dated January 2026 decided September 2026
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Juliette Mugambi & Another v Summerville Properties Limited", Case Analysis (2026). ELCLC NO. E132 OF 2026. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2026/5947/eng@2026-09-30
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.