ELCPartially AllowedELCLPET. NO. E012 OF 2024· [2026] KEELC 5106 (KLR)

Gakuru & 2 others (Suing on their own Behalf and on Behalf of JWA Thika Subcounty)) v County Government of Kiambu & 3 others (Environment and Land Petition E012 of 2024) [2026] KEELC 5106 (KLR)

Environment and Land Court
15 July 2026
7,072 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~28 min to read original · ~4 min brief

The bottom line

#

A Kenyan court ruled that even a major national housing project must obey court orders, holding the Housing Principal Secretary in contempt and halting construction in Thika.

What this practically means

#

Executive summary

#
This ruling of the Environment and Land Court at Thika determines two applications arising from a petition challenging the Thika Musitani affordable housing project on Thika Municipality Block 11/343. The 2nd Respondent, the Principal Secretary for Housing, sought to review and set aside a ruling of 4/11/2025 that found him in contempt of an order of 20/05/2025 halting construction, arguing he was never personally served. The Court rejected this, holding that service on the Ministry's registry with receiving stamps was effective and that internal administrative neglect cannot shield an official from accountability. His application succeeded only in obtaining an order fast-tracking the main petition for expedited hearing; the contempt finding was affirmed, though personal appearance in court to show cause was dispensed with, with a stern caution. The Petitioners' application of 26/03/2026, prompted by the contractor's re-entry onto the site on 25/03/2026, succeeded: the Court issued a further mandatory injunction restraining all construction pending determination of the petition, placed enforcement under the OCS Thika, put the Inspector General of Police on notice, and empowered arrest of trespassers. Coercive orders were denied against the 1st Respondent County Government as it had divested possession and control to the 2nd Respondent. Although the Petitioners' affidavit sworn by their advocate was found procedurally defective, the Court acted on the Deputy Registrar's independent site visit findings. Critically, the Court held that no project magnitude, contract sum or Presidential Directive can override the Constitution, court orders, public participation and the rule of law.

Key legal issues

#
01

Proper service on a government ministry and validity of the contempt finding

Holding

Service was properly effected; the Principal Secretary was personally liable despite claiming documents never reached his desk

Reasoning

The Court relied on the official receiving stamps on the order dated 27/05/2025 bearing the 2nd Respondent's stamp of 28/05/2025 and the Attorney General's stamp of 30/05/2025. It held that delivery to the official registry with a receiving stamp satisfies the petitioner's obligation, and to hold otherwise would reward internal administrative neglect and make service on government a practical impossibility.

p. 26
02

Whether the magnitude of a national housing project justifies abdication of judicial enforcement

Holding

No; the right to housing cannot be pursued at the expense of fair process, public participation and the rule of law

Reasoning

The Court held that Article 43(1)(b) is a justiciable socio-economic right subject to progressive realization, but no right exists in isolation. A Presidential Directive does not override the Constitution, and Article 10 binds all State organs to the rule of law and participation. Judicial superintendence of constitutional compliance is not obstruction of development.

p. 30
03

Competence of an Advocate's affidavit deposing to contentious facts

Holding

Such an affidavit is fundamentally defective and worthless, but here the defect went to probative value, not admissibility, since independent evidence sufficed

Reasoning

Relying on Republic v Attorney General ex parte South and Central (Thika) Investments Ltd and Life Insurance Corporation of India v Panesar, the Court agreed an Advocate cannot straddle the bar and witness box. However, the institutional stamps, site visit report and Mulandi's depositions independently grounded the findings, so weight rather than admissibility was affected.

p. 28
04

Whether coercive orders can lie against a party divested of possession and control

Holding

They cannot lie against the 1st Respondent, but they properly lie against the 2nd Respondent as implementing agency in operational command

Reasoning

The Court accepted that the County Government had handed over the site before the suit and exercised no operational authority, so injunctive or coercive orders could not issue against it. The 2nd Respondent, as implementing agency for the Affordable Housing Board in full operational command, remained properly subject to a mandatory injunction and OCS-enforced stop order.

p. 29

Legal principles established

#
  • Every person against whom a court order is made must obey it until it is discharged
  • Service on a government ministry is complete upon delivery to the official registry and receipt of a receiving stamp; internal routing failures do not defeat service
  • A Presidential Directive and project magnitude cannot override the Constitution or immunize a project from judicial scrutiny or court orders
  • Court orders are coercive directives, not requests

Court orders

#
  1. 1.The 2nd Respondent's Application dated 12/02/2026 allowed only to the extent that the Main Petition dated 26/08/2024 is fast-tracked for an expedited full hearing; to the extent it seeks to set aside the Ruling of 4/11/2025 and the contempt finding, it is dismissed
  2. 2.The 2nd Respondent, the Principal Secretary, State Department for Housing, is found to be in contempt of Court for willful disobedience of the Court's Order
  3. 3.The requirement for the Principal Secretary to personally appear in Court to show cause why he should not be committed to civil jail is dispensed with, with a strong caution against future non-compliance
  4. 4.The Application dated 26/03/2026 by the 1st and 2nd Petitioners is allowed; a further mandatory injunction restraining the 2nd Respondent, its agents, servants, contractors and sub-contractors from carrying out any construction on Thika Municipality Block 11/343 pending hearing and determination of the Petition
  5. 5.The Officer Commanding Station, Thika Police Station, is directed and empowered to enforce the stop-order, ensure no construction takes place, and arrest and arraign any person found trespassing or constructing in violation
  6. 6.The Inspector General of Police is put on notice and directed to facilitate the OCS Thika in execution of the orders
  7. 7.Costs of both Applications to be borne by the 2nd Respondent and to be in the cause

Authorities

#

Legislation

  • Constitution of KenyaArticle 43(1)(b)
  • Constitution of KenyaArticle 50
  • Constitution of KenyaArticles 10 and 108
  • Civil Procedure Act (Cap 21)Sections 1A, 1B and 3A
  • Environment and Land Court Act, 2011Section 13
  • Civil Procedure Rules, 2010Order 51 Rule 1
  • Civil Procedure RulesOrder 19 Rule 3
  • Civil Procedure RulesOrder 18, Rule 3(1)
  • Oaths and Declarations Act (Cap 15)Section 35

Cases cited (5)

  • Raila Odinga & Others v. William Ruto & Others (with the Law Society of Kenya as Amicus Curiae)
    [2022] KESC
  • Republic v Attorney General [Sued for and on behalf of the Ministry of Lands] & 2 Others Ex Parte South and Central [Thika] Investments Limited
    [2015] KEHC 7560 (KLR)
  • Life Insurance Corporation of India v Panesar
    [1967] EA 614
  • Hadkinson v Hadkinson
    [1952] 2 All ER 567
  • Econet Wireless Kenya Limited v Minister for Information & Communication of Kenya & Another
    [2005] 1 KLR 828
Jurisdiction invoked
Sections 1A, 1B and 3A of the Civil Procedure Act (Cap 21), Section 13 of the Environment and Land Court Act, 2011, and Order 51 Rule 1 of the Civil Procedure Rules, 2010

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Gakuru & 2 others (Suing on their own Behalf and on Behalf of JWA Thika Subcounty)) v County Government of Kiambu & 3 others (Environment and Land Petition E012 of 2024) [2026] KEELC 5106 (KLR)", Case Analysis (2026). ELCLPET. NO. E012 OF 2024. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2026/5106/eng@2026-07-15

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.