ELCPartially AllowedELC Petition No. E004 of 2025· [2026] KEELC 4924 (KLR)

Mbae v County Builders Ltd & 3 others (Environment and Land Petition E004 of 2025) [2026] KEELC 4924 (KLR)

Environment and Land Court
20 July 2026
4,134 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~17 min to read original · ~4 min brief

The bottom line

#

Kenya's Environment and Land Court allowed a road-construction environmental case to proceed and ordered the county government to release its assessment records, though building work continues.

What this practically means

#

Executive summary

#
The petitioner commenced a petition on 25/9/2025 alleging that the respondents began constructing the Katharaka-Mukui-Mumbuni Road to bitumen standards without a proper environmental impact assessment licence and without public participation, in violation of Articles 10, 42, 69, 70 and 174 of the Constitution, and sought declarations, injunctions, restoration, compensation and damages. Two matters fell for determination: the 2nd and 4th respondents' preliminary objection dated 27/10/2025 seeking to strike out the petition, and the petitioner's notice of motion dated 22/9/2025 seeking interlocutory conservatory and disclosure orders. On the preliminary objection, the court rejected all four grounds: the dominant issue was enforcement of the Article 42 right to a clean and healthy environment, not a tender dispute for the PPARB; under Article 70(3) the petitioner needed neither personal loss nor third-party authorization to sue; the reliefs fell within the ELC's jurisdiction under Article 162(2)(b) and Section 13 of the ELC Act; and inadmissibility of evidence is a trial issue, not a basis for striking out a petition in limine. On the application, the court declined the conservatory order because the road serves the public and an EIA Licence dated 17/12/2025 rendered current works prima facie lawful, holding damages would remedy any prior illegality. However, it ordered the 2nd, 3rd and 4th respondents to avail certified copies of the EIA Report, EIA Licence and public participation records within 30 days, the 3rd respondent having ignored the application and the proponent having exhibited no such records. Costs of the objection went to the petitioner; costs of the application were reserved to the petition.

Key legal issues

#
01

Exhaustion of statutory remedies (PPARB, Water Act Tribunal, National Environment Tribunal)

Holding

The dominant issue in the petition is enforcement of the right to a clean and healthy environment under Article 42, not a tender dispute, so the PPARB and other statutory fora were not the exclusive avenue

Reasoning

The objectors relied on Sections 27 and 28 of the PPADA, but the court held the PPARB's jurisdiction covers tendering and asset disposal disputes. Reading the petition, the gravamen is alleged environmental and constitutional violations in project implementation, not evaluation or award of a tender, hence no exhaustion was required.

p. 8
02

Locus standi of the petitioner

Holding

Ground 2 rejected; under Article 70(3) no demonstration of loss or injury or third-party authorization is required

Reasoning

The court applied Article 70(3) and the Supreme Court's pronouncement in Export Processing Zones Authority, holding that environmental harm is a public harm and a petitioner need not show personal injury nor obtain authorization from the co-operative or water project to sue.

p. 10
03

Jurisdiction of the ELC over the reliefs sought

Holding

The reliefs fall within Article 162(2)(b) and Section 13 of the ELC Act

Reasoning

Although some prayers referenced tender standards and administrative action, the court held all reliefs fell within the broad jurisdiction of the ELC under Article 162(2)(b) and Section 13 of the Environment and Land Court Act; ground 3 failed.

p. 12
04

Interlocutory conservatory order

Holding

Refused; a prima facie EIA Licence existed and halting public road works was not in the public interest

Reasoning

Applying the Munya criteria from the Supreme Court, the court weighed the public-law character of conservatory orders. The road serves the general public and the respondents had an EIA Licence dated 17/12/2025, so continuance was prima facie lawful; damages would remedy any prior illegality.

p. 17
05

Compelling availment of EIA and public participation records

Holding

Granted against the 2nd, 3rd and 4th respondents in terms of prayer (e), compliance within 30 days

Reasoning

The County Government, the project proponent, did not exhibit the ESIA study report or public participation notices, NEMA ignored the application, and only the contractor exhibited a report; the court found this warranted an interlocutory disclosure order.

p. 18

Legal principles established

#
  • A litigant enforcing Article 42 need not demonstrate personal loss or injury to have locus standi
  • Where works commenced without an EIA Licence, the only redress mechanism available is a suit in a court of law
  • Inadmissibility of evidence is a trial issue, not a ground for striking out a petition in limine

Court orders

#
  1. 1.The preliminary objection dated 27/10/2025 is rejected and dismissed with costs for lack of merit
  2. 2.The application dated 22/9/2025 succeeds partially against the 2nd, 3rd and 4th respondents in terms of prayer (e); the three respondents shall comply within 30 days
  3. 3.Costs of the application shall be in the petition
Jurisdiction invoked
Article 162(2)(b) of the Constitution and Section 13 of the Environment and Land Court Act

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Mbae v County Builders Ltd & 3 others (Environment and Land Petition E004 of 2025) [2026] KEELC 4924 (KLR)", Case Analysis (2026). ELC Petition No. E004 of 2025. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2026/4924/eng@2026-07-20

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.