ELCDismissedNotice of Motion application dated 12th February, 2026 in a suit concerning Plot No. 29437/133 Kwale· [2026] KEELC 3872 (KLR)

Colfax Holdings Ltd v Kenya Railways Corporation (Environment and Land Case E048 of 2024) [2026] KEELC 3872 (KLR)

Environment and Land Court
17 June 2026
4,894 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~20 min to read original · ~4 min brief

The bottom line

#

Kenya's Environment and Land Court ruled that withdrawing a land dispute in good faith after it was resolved does not force the withdrawing party to pay the other side's costs.

What this practically means

#

Executive summary

#
This ruling of the Environment and Land Court at Kwale (L.L Naikuni J) determined a Notice of Motion dated 12th February 2026 by Kenya Railways Corporation seeking costs of the suit after Colfax Holdings Limited withdrew its claim for mesne profits of Kshs. 5,928,000 plus punitive damages for alleged encroachment on Plot No. 29437/133 Kwale. The defendant argued that under Section 27 of the Civil Procedure Act costs follow the event and that the plaintiff's withdrawal made it the successful party, relying on Rai v Rai among other authorities. The plaintiff countered that the suit was withdrawn in good faith after the boundary dispute was resolved when fence posts within the railway corridor were repositioned following a site verification, that the jurisdictional objection was never determined, and that no party had won. The court framed three issues: the merit of the application, entitlement to costs of the withdrawn suit, and costs of the application. Applying Section 27 and the factors in Cecilia Karuru Ngayu v Barclays Bank, the court held that the stage and manner of termination are relevant; the withdrawal before hearing was appropriate, reasonable and fair once the temporary fence was removed, and no survey report was needed to remove a temporary fence. Adopting Devram Dattan v Dawda and Kirugi v Jan Japan, it held punitive costs would deter litigants from abandoning futile claims. The application was dismissed with each party bearing its own costs.

Key legal issues

#
01

Whether withdrawal of a suit makes the defendant the successful party entitled to costs

Holding

No - withdrawal at an early stage after the factual dispute was resolved does not make the defendant a successful party for costs purposes

Reasoning

The court applied Section 27 of the Civil Procedure Act and the Cecilia Karuru Ngayu factors, holding that the stage and manner of termination matter. The plaintiff withdrew before hearing because the alleged encroachment was addressed by removal of a temporary fence; there was no determination on the merits, no survey report was necessary for removal of a temporary fence, and the withdrawal was appropriate, reasonable and fair. Awarding costs would punish good-faith withdrawal and discourage parties from seeking judicial remedies.

p. 9
02

Whether good reason existed to deny the applicant costs

Holding

Yes - the good-faith withdrawal after clarification of the boundary dispute constituted good reason to order each party to bear its own costs

Reasoning

Relying on Devram Dattan v Dawda, the court held the discretion is judicial and fact-based. The claim became futile once the fence alignment corresponded with the corridor boundary; it would serve no purpose to penalise a litigant for abandoning a futile claim. The court adopted the Kirugi v Jan Japan dictum that costs of withdrawn moot proceedings must be treated differently from a determination on the merits, and costs must not discourage parties from approaching the courts.

p. 10

Legal principles established

#
  • Costs are discretionary and follow the event unless the court for good reason otherwise orders
  • The stage and manner of termination of proceedings are relevant factors in exercising the discretion on costs
  • Parties should not be deterred by punitive costs orders from withdrawing claims rendered futile by change of circumstances

Court orders

#
  1. 1.That the Notice of Motion application dated 12th February, 2026 be and is hereby found to lack merit and thus be dismissed outrightly
  2. 2.That each party to bear their own costs on the Notice of Motion application dated 12th February, 2026
Jurisdiction invoked
Original civil jurisdiction of the Environment and Land Court under the Constitution of Kenya, 2010 and Section 27 of the Civil Procedure Act, Cap. 21 on costs

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Colfax Holdings Ltd v Kenya Railways Corporation (Environment and Land Case E048 of 2024) [2026] KEELC 3872 (KLR)", Case Analysis (2026). Notice of Motion application dated 12th February, 2026 in a suit concerning Plot No. 29437/133 Kwale. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2026/3872/eng@2026-06-17

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.