AI-generated case brief
Case Brief · caselaw.co.ke
ELCPartially AllowedNot stated in judgment (notice of motion dated 10th March 2025)· [2026] KEELC 3052 (KLR)

Ibrahim & another v County Government of Garissa & 4 others (Land Case E008 of 2025) [2026] KEELC 3052 (KLR)

Environment and Land Court
21 May 2026
2,482 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~10 min to read original · ~4 min brief

The bottom line

#

A Kenyan land court halted construction on disputed Garissa plots until trial, ruling that stopping early avoids wasting public money on land that may not be the government's.

What this practically means

#

Executive summary

#
The plaintiffs, registered proprietors of Garissa Municipality/Block 111/465 and 466, moved the court by notice of motion dated 10th March 2025 seeking temporary injunctions restraining the defendants from entering, constructing or dealing in the suit properties, a court-conducted site visit, a joint survey, and costs. They alleged that the 4th defendant (Garissa Primary School) had long contested their titles, that the 1st to 3rd defendants advertised and commenced a stadium/pavilion construction on the parcels using public funds, and that trespass and intimidation occurred. The defendants opposed, contending the land forms part of land reserved for Garissa Primary School, that the plaintiffs' titles were irregularly acquired, and that the project served the public interest. The court noted that a construction stoppage order issued on 26th March 2025 and varied on 24th June 2025 had remained in force, and that a court-ordered County Surveyor survey had rendered the joint-survey prayer spent. Applying the Giella, Mrao and Nguruman principles, and noting survey reports confirming fencing of portions of the plaintiffs' parcels and the Treasury-funded nature of the project, the court found that avoiding wastage of public resources justified preserving the status quo. It extended the interim injunction pending the hearing of the suit, declined the locus visit as premature, and directed that costs abide the outcome of the suit. Dated, signed and virtually delivered on 21st May 2026 by S. M. Kibunja, ELC Judge.

Key legal issues

#
01

Whether plaintiffs established a prima facie case, irreparable harm and balance of convenience for a temporary injunction

Holding

Injunction granted to preserve the status quo: the interim stoppage order of 26th March 2025 (as varied on 24th June 2025) was extended pending the hearing of the suit, protecting plaintiffs' parcels 465 and 466 while allowing development on undisputed school land

Reasoning

The court applied the principles in Giella, Mrao and Nguruman. Survey reports confirmed parts of the plaintiffs' titled parcels had been fenced off for the project. The court weighed the public-interest nature of the Treasury-funded development: allowing construction on disputed portions risked demolition and wastage of public resources if plaintiffs succeeded, while restraint preserved resources if defendants won. Justice was best served by maintaining the status quo.

p. 5
02

Whether a locus visit should be ordered at the interlocutory stage

Holding

Refused as premature; liberty to apply at hearing

Reasoning

The court found that parties had not yet presented witness evidence, and two survey reports already filed could assist the court; the evidential value of a visit could not yet be assessed, so the prayer would be reconsidered once the hearing commenced.

p. 5

Legal principles established

#
  • Costs follow the event unless the court orders otherwise on good reasons, under Section 27 of the Civil Procedure Act
  • Where development on contested land uses public resources, maintaining the status quo pending trial better serves justice by avoiding wastage of public resources

Court orders

#
  1. 1.The application is found to have merit and the temporary injunction sought in prayers (b) and (c) is granted in the terms of the injunction order issued on 26th March 2025 as varied on 24th June 2025, pending the hearing and determination of the suit
  2. 2.Prayer (d) for a locus visit is not granted at this stage, with liberty to move the court once hearing commences
  3. 3.Prayer (e) for a joint survey is spent, having been effected by the County Surveyor's court-ordered survey
  4. 4.Costs of the application to abide the outcome of the suit

Authorities

#

Legislation

  • Civil Procedure ActSection 27

Cases cited (3)

  • Giella versus Casman Brown & Company Limited
    [1973] EA 358
  • Mrao Limited versus First American Bank of Kenya Limited & 2 Others
    [2003] KECA (KLR) 125
  • Nguruman Limited versus Jan Bonde Nielsen & 2 Others
    [2014] eKLR
Jurisdiction invoked
Original civil jurisdiction of the Environment and Land Court over disputes relating to title/occupation of land (interlocutory notice of motion in a pending suit)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Ibrahim & another v County Government of Garissa & 4 others (Land Case E008 of 2025) [2026] KEELC 3052 (KLR)", Case Analysis (2026). Not stated in judgment (notice of motion dated 10th March 2025). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2026/3052/eng@2026-05-21

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.