Kenya Electricity Transmission Company Limited v Biego & 19 others (Environment and Land Case 96 of 2021) [2026] KEELC 3046 (KLR)
The bottom line
#Kenya's land court ordered Nandi landowners compensated and restrained from blocking KETRACO's power line, with a 40-metre easement registered after title deeds are produced.
What this practically means
#Executive summary
#Key legal issues
#Effect of the partial settlement agreement adopted as a court order
The partial settlement agreement dated 8th November 2024, adopted on 23rd July 2025, is a binding consent order or partial judgment binding only the parties to it and cannot be varied or set aside without sufficient reason
The court held that the agreement involved only the plaintiff and the 10th, 11th, 13th, 14th, 16th to 20th defendants and binds only those parties. Having been voluntarily entered into and duly adopted as a court order, it cannot be varied or set aside without sufficient reason. The court relied on its inherent powers under section 3A of the Civil Procedure Act and Article 159(2)(b), (c) and (d) of the Constitution to render a partial consent judgment.
Whether the plaintiff's claim was proved against the defendants
The plaintiff's claim was established on a balance of probabilities through the partial settlement agreement and the uncontroverted evidence of PW1
The defendants did not testify. PW1's evidence, including exhibits 1 to 34, established valuation, offers and payments, with non-payments attributable to non-registration of the easement. In cross-examination PW1 admitted the defendants were not called to the meetings, yet the court found the claim proved on a balance of probabilities, relying on the authorities cited including Park Towers and Kirugi v Kabiya.
Relief to be granted, including priority between registration of the easement and compensation
Judgment was entered in terms of the partial settlement agreement; the easement is to be registered within fourteen days upon production of original title deeds, and compensation to follow thereafter
The court granted an assessment of just compensation as per the settlement, a permanent injunction against interference with the plaintiff's works, and ordered registration of a 40-metre easement upon production of title deeds, with compensation thereafter. On costs, guided by the proviso to section 27(1) of the Civil Procedure Act and Jasbir Singh Rai, each party was to bear its own costs.
Legal principles established
#- A settlement agreement adopted by the court becomes a binding consent order or judgment which the court cannot vary or set aside without sufficient reason
- A partial settlement agreement operates as a valid and enforceable partial judgment binding only the parties to it, pending determination of the main suit
- The onus is always on the plaintiff to prove his or her case on a balance of probabilities
- Where trespass is proved, a party need not prove any specific damage or loss to be awarded damages; the court assesses damages on the unique facts of each case
Court orders
#- 1.An assessment of just compensation payable to the Defendants as stated in the partial settlement agreement (paragraphs 28, 29 and 30)
- 2.Permanent injunction against the Defendants, either by themselves, their agents or employees, from interfering with the works of the Plaintiff
- 3.An order that the Registrar of Lands Nandi County does register an Easement measuring 40 meters wide in favour of the plaintiff (KETRACO) against the 1st to 16th suit parcels of land within fourteen (14) days upon production of the original title deeds by the respective defendants and thereafter, compensation be made forthwith
- 4.Parties to bear their own costs of the suit
- Jurisdiction invoked
- Original civil jurisdiction under the Environment and Land Court Act over disputes relating to land in Nandi County; Article 159(2)(b), (c) and (d) of the Constitution of Kenya 2010 on adoption of mediated settlement
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Kenya Electricity Transmission Company Limited v Biego & 19 others (Environment and Land Case 96 of 2021) [2026] KEELC 3046 (KLR)", Case Analysis (2026). . Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2026/3046/eng@2026-05-19
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.