Registered Officials and Trustees of Life Transforming Centre v Darajani Hotel Limited & another (Environment and Land Appeal E051 of 2024) [2026] KEELC 1670 (KLR)
The bottom line
#What this practically means
#Executive summary
#Key legal issues
#Whether the Tribunal had jurisdiction over an appeal concerning noise pollution control
The Tribunal had no jurisdiction; control of noise pollution is a devolved function under Part 2, Section 3 of the Fourth Schedule to the Constitution, outside NEMA's mandate, and the respondents' appeal was not founded on a NEMA decision under Section 129 of EMCA
Part 2 of the Fourth Schedule devolves 'control of air pollution, noise pollution, other public nuisance' to county governments. Although NEMA once held this mandate under EMCA, the 2010 Constitution expressly shifted it. The respondents' appeal did not fall under Section 129(1) since no licence, fee or restoration order was involved, and under Section 129(2) any appeal had to concern a matter within NEMA's mandate, which noise pollution no longer is. The proceedings were therefore a nullity.
Whether the Tribunal erred in allowing the appeal on the merits
It was unnecessary to consider the merits because a decision rendered without jurisdiction is a nullity regardless of its correctness
Having found the Tribunal lacked jurisdiction, the court held that the merits became immaterial: whether right or wrong, the Tribunal's decision was void. Jurisdiction goes to the foundation of the adjudication, so no merits analysis was required.
Who shall bear costs of the appeal
Despite the general rule that costs follow the event, each party was ordered to bear its own costs because the Tribunal, not the parties, was at fault for proceeding without jurisdiction
Costs are discretionary and under the proviso to Section 27 of the Civil Procedure Act follow the event, per Hussein Janmohamed & Sons v Twentsche Overseas Trading Co. Ltd. However, since the error lay with the Tribunal in entertaining a matter without jurisdiction, it would be unjust to penalize either party; each party was directed to bear its own costs in both proceedings.
Legal principles established
#- The promulgation of the Constitution of Kenya, 2010 shifted control of noise pollution from NEMA to the county governments under Part 2 of the Fourth Schedule
- Tribunal proceedings and decisions made without jurisdiction are a nullity
- Section 129 of EMCA refers to positive administrative decisions of NEMA, not mere inaction or neglect
Court orders
#- 1.The appeal be and is hereby allowed.
- 2.The judgment of the National Environment Tribunal dated 19.11.2024 in NET Appeal No. E007/2023 is hereby set aside in its entirety.
- 3.Each party shall bear its own costs of the instant appeal and the appeal before the Tribunal.
- On appeal from
- National Environment Tribunal
- Tribunal Appeal No. E007/2023 – Darajani Hotel Ltd and Bridge Hotel Ltd v National Environment Management Authority & 3 Others
- Jurisdiction invoked
- Appeal from the National Environment Tribunal under the Environmental Management and Coordination Act, 1994 (EMCA)
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Registered Officials and Trustees of Life Transforming Centre v Darajani Hotel Limited & another (Environment and Land Appeal E051 of 2024) [2026] KEELC 1670 (KLR)", Case Analysis (2026). Not stated in the judgment text (memorandum of appeal dated 17.12.2024, amended 21.03.2025). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2026/1670/eng@2026-03-19
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.