Skip to content
AI-generated case briefs sourced from Kenya Law · Not legal advice
AI-generated case brief
Case Brief · caselaw.co.ke
ELCPartially AllowedNot stated in the judgment (plaint dated 8th January, 2024)· [2026] KEELC 1384 (KLR)

Gigiri Mart Limited v ATC Kenya Operations Limited (Environment and Land Case E008 of 2024) [2026] KEELC 1384 (KLR)

Environment and Land Court
10 March 2026
5,762 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~23 min to read original · ~4 min brief

The bottom line

#

A Kenyan landowner failed to evict a telecom tenant because it never proved the tenant breached the lease or that force majeure validly ended it.

What this practically means

#

Executive summary

#
The plaintiff, registered owner of LR No. 12814, sued the defendant (a lessee holding a ten-year lease from Telkom Kenya Limited commencing 21st January 2019) for eviction, demolition of its telecommunications mast, a permanent injunction, general damages of Kshs.30,000,000 for trespass and constitutional compensation, alleging the defendant frustrated the lease by failing to pay rent and that a termination and eviction notice dated 6th December 2022 validly ended the lease. The defendant denied breach, asserting a valid lease and counterclaiming for a permanent injunction restraining interference with its lawful occupation. The court framed two issues: whether the plaintiff proved its case, and whether the counterclaim was merited. Applying the principle that courts cannot re-write contracts, the court found the defendant not in breach of clause 5.1: the plaintiff failed to notify the defendant of its registration as new owner, and the email trail showed the defendant promptly seeking the lease, title and banking details and paying rent once verified. On clause 12.2, the Water Resources Authority letter about riparian encroachment was addressed to a third party, never brought to the defendant's attention, and was used by the plaintiff as an avenue to relocate the mast; no force majeure event was proved. The termination notice was therefore invalid. The plaint was dismissed with costs; the counterclaim was allowed and a permanent injunction issued restraining the plaintiff from interfering with the defendant's lawful occupation, use and quiet possession of the suit property, with costs of the counterclaim awarded to the defendant. Damages for trespass were unavailable as they were not pleaded among the counterclaim prayers.

Key legal issues

#
01

Whether the defendant breached clause 5.1 of the lease by failing to pay rent

Holding

The defendant was not in breach; the plaintiff failed to bring its registration as the new owner to the defendant's attention in time, and the defendant promptly acted to resolve outstanding rent

Reasoning

The lease was originally with Telkom Kenya. The sale agreement was between Jambo Credit and Telkom, who nominated the plaintiff, registered only on 10th December 2021, without notice to the defendant. The email trail from March 2023 shows the defendant requesting the lease, title and banking details and paying rent once verified, albeit less withholding tax and escalation. The delay and confusion over payment were attributable to the plaintiff's failure to notify.

p. 8
02

Whether the lease stood terminated under clause 12.2 (force majeure) following the Water Resources Authority letter dated 18th November, 2021

Holding

No force majeure event was proved; the letter was addressed to a third party, not the defendant, and was never brought to the defendant's attention

Reasoning

Clause 12.2 requires a force majeure circumstance beyond a party's control rendering performance impossible, expressly excluding inability to pay rent. The WRA letter was addressed to In One Consultancy Limited regarding a site visit; the defendant was not informed of the visit or findings and never saw the letter. The court found the letter was used by the plaintiff as an avenue to relocate the mast, having earlier expressed a desire to do so, especially since NEMA had in 2017 found the property's environmental reports satisfactory.

p. 9
03

Whether the plaintiff proved its claim for eviction, injunction and damages

Holding

The plaintiff failed to prove its case on a balance of probabilities; the plaint was dismissed

Reasoning

With no breach of clause 5.1 and no basis for invoking clause 12.2, the termination notice dated 6th December 2022 was unjustified and the defendant was not a trespasser. The defendant remained entitled to quiet possession under the valid lease running to 21st January 2029. The plaintiff's constitutional claims (Articles 27 and 40) necessarily failed as no unlawful occupation was established.

04

Whether the defendant's counterclaim was merited and competent

Holding

The counterclaim succeeded; a permanent injunction was issued restraining the plaintiff from interfering with the defendant's lawful occupation, use and quiet possession of the suit property

Reasoning

The defendant held a valid lease for ten years from 21st January 2019, granting exclusive, quiet and peaceful use. No valid termination having occurred, the defendant was entitled to enforcement of that right. However, its claim for damages for trespass was not pursued among the prayers and therefore could not be awarded.

p. 10

Legal principles established

#
  • A court of law cannot re-write a contract between the parties; parties are bound by the terms of their contract unless coercion, fraud or undue influence are pleaded and proved
  • The doctrine of force majeure excuses contractual performance only for events beyond the parties' control not foreseen at the time of contracting, and its interpretation depends on the wording and events delineated by the parties in their contract

Court orders

#
  1. 1.The plaint dated 8th January, 2024 is dismissed with costs to the defendant
  2. 2.The defendant's counterclaim dated 26th January, 2024 is allowed, and a permanent injunction is issued restraining the plaintiff from interfering with the defendant's lawful occupation, use and quiet possession of the suit property
  3. 3.The defendant (plaintiff in the counterclaim) is awarded the costs of the counterclaim
Jurisdiction invoked
Original civil jurisdiction of the Environment and Land Court over a dispute relating to land and a lease over LR No. 12814

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Gigiri Mart Limited v ATC Kenya Operations Limited (Environment and Land Case E008 of 2024) [2026] KEELC 1384 (KLR)", Case Analysis (2026). Not stated in the judgment (plaint dated 8th January, 2024). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2026/1384/eng@2026-03-10

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.