ELCPartially AllowedELC NO. E001 OF 2024· [2026] KEELC 800 (KLR)

Nyaku Limited v Metropolis Star Labs Kenya Ltd & 2 others; Gheewa & another (Interested Parties) (Environment and Land Case E001 of 2024) [2026] KEELC 800 (KLR)

Environment and Land Court
12 February 2026
1,113 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~4 min to read original · ~4 min brief

The bottom line

#

The Environment and Land Court in Kajiado ruled it cannot decide company ownership disputes—those go to the High Court's Commercial Division—and paused the land case until that court finishes.

What this practically means

#

Executive summary

#
The Plaintiff sued the 1st Defendant seeking declarations that its tenancy is illegal and amounts to trespass, plus injunctive reliefs restraining the 2nd and 3rd Defendants from making unilateral decisions concerning the suit property. At interlocutory stage the 3rd Defendant, a company director, had earlier failed to strike out the suit for want of a board resolution, and later filed the instant application. The Plaintiff opposed, arguing the validity of the impugned AGM had already been determined by the High Court's Commercial Division and that this court lacked jurisdiction over the corporate issues raised. The court framed two issues: whether leave to amend the defence should issue, and whether it had jurisdiction over the company resolutions and AGM validity. On jurisdiction, the court held that under Article 162(2)(b) of the Constitution and Section 13 of the Environment and Land Court Act, 2011, it is confined to environment and land disputes and has no remit over directorship, board or shareholder resolutions, corporate authority and internal governance, which fall within the Commercial Division's domain, already seized of related suits. Finding that all parties were in effect inviting it into matters pending before the Commercial Division, the court stayed the ELC proceedings pending conclusion of HCC COMMERCIAL E075 of 2024. On amendment, relying on Order 8 Rules 3 and 5 of the Civil Procedure Rules, it granted the Defendant leave to amend its defence within 21 days, with corresponding leave to the other parties, subject to a caveat that amendments must not touch issues already before the Commercial Court. The 2nd Defendant had also withdrawn prayers challenging the appointment of Ike and Co Advocates, a ruling being awaited on 27th February 2026.

Key legal issues

#
01

Jurisdiction of the ELC over corporate/AGM resolution disputes

Holding

The court lacks jurisdiction to determine the validity of company resolutions and AGM decisions; these fall within the Commercial Division's domain.

Reasoning

The court traced its jurisdiction to Article 162(2)(b) and Section 13 of the Environment and Land Court Act, 2011, which confine it to environment and land disputes. Corporate issues of directorship, board resolutions and internal governance do not fall within that scope, and the Commercial Division is already seized of related matters, so all parties were effectively asking this court to venture into issues pending there.

p. 5
02

Leave to amend the defence

Holding

Leave granted under Order 8 Rules 3 and 5 of the Civil Procedure Rules, with a caveat that amendments must not touch issues pending before the Commercial Court.

Reasoning

Order 8 Rules 3 and 5 empower the court at any stage to allow amendments to determine the real question in controversy or correct defects, on just terms. In the interests of expeditious determination once the stay lapses, the court granted leave to the Defendant with corresponding leave to other parties, restricting amendments to matters outside the Commercial Division's purview.

p. 7

Legal principles established

#
  • The Environment and Land Court has no jurisdiction over internal company governance, directorship or the validity of corporate resolutions; those matters belong to the High Court's Commercial Division.
  • Where capacity issues are pending before the High Court, the ELC may stay its proceedings pending their determination.

Court orders

#
  1. 1.The Defendant is granted leave to amend their Defence; Amended Defence to be filed within 21 days
  2. 2.Corresponding leave is granted to the other parties to amend their pleadings
  3. 3.The proceedings are hereby stayed pending the conclusion of HCC COMMERCIAL E075 of 2024

Authorities

#

Legislation

  • Constitution of KenyaArticle 162(2)(b)
  • Constitution of KenyaArticles 42, 69 and 70
  • Environment and Land Court ActSection 13(1), (2), (3), (4)
  • Civil Procedure RulesOrder 8 Rule 3; Order 8 Rule 5; Order 1 rules 9 and 10; Order 24 rules 3, 4, 5 and 6
Jurisdiction invoked
Article 162(2)(b) of the Constitution and Section 13 of the Environment and Land Court Act, 2011

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Nyaku Limited v Metropolis Star Labs Kenya Ltd & 2 others; Gheewa & another (Interested Parties) (Environment and Land Case E001 of 2024) [2026] KEELC 800 (KLR)", Case Analysis (2026). ELC NO. E001 OF 2024. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2026/800/eng@2026-02-12

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.