Gichuhi & 4 others v Services & another (Environment and Land Case 410 of 2018) [2025] KEELC 8256 (KLR)
The bottom line
#Kenya's Environment and Land Court allowed a late surveyor's report into a land case, confirming courts will bend deadlines when fairness demands it.
What this practically means
#Executive summary
#Key legal issues
#Whether leave should be granted to file a surveyor's report out of time after pleadings closed
Leave granted; the court has jurisdiction to allow introduction of a document even after trial has begun where justice requires and no prejudice results.
Order 50 Rule 6 confers a discretion to enlarge time even after expiry. The Applicant obtained the report in August 2024 during unsuccessful settlement negotiations, explaining the timing. The court weighed fairness to both sides: the Plaintiff(s) may cross-examine on the new document and may themselves file a further survey report, so no prejudice arises. Justice favoured admission of the evidence.
Whether the Nairobi Regional Surveyor should be summoned to give expert opinion
Summons ordered to issue for the Nairobi Regional Surveyor to attend court and give an expert opinion on documents prepared by his office.
The relief was sought in the Notice of Motion and, having found the report vital and admissible, the court granted the consequential order compelling the Regional Surveyor to attend and speak to the documents prepared by his office, thereby enabling the court to test and benefit from the expert material.
Legal principles established
#- The court's discretion to enlarge time under Order 50 Rule 6 may be exercised even after expiry of the fixed time, where the justice of the case requires, provided no party is prejudiced.
- In an application for enlargement of time, the primary consideration is that justice is served for all parties and that they are allowed to present their case.
Court orders
#- 1.Leave is granted to the 1st Defendant to file and serve the Regional Surveyor's Report dated 16th August 2024 and the accompanying documents within 14 days from the date hereof
- 2.Summons to issue to the Nairobi Regional Surveyor to attend court and give an expert opinion on the documents prepared by his office
- 3.The Plaintiff(s) are given liberty to file and serve a Survey Report within 14 days of service by the Applicant
- 4.The Respondents are awarded the costs of the application
- Jurisdiction invoked
- Articles 50(1) and 159 of the Constitution; Sections 1A, 1B and 3A of the Civil Procedure Act; Order 51 Rule 1 and Order 50 Rule 6 of the Civil Procedure Rules
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Gichuhi & 4 others v Services & another (Environment and Land Case 410 of 2018) [2025] KEELC 8256 (KLR)", Case Analysis (2025). . Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2025/8256/eng@2025-11-24