ELCDismissedNot stated in the judgment (Notice of motion dated 23rd July 2025, amended 22nd September 2025)

Mzee (Suing on Behalf of Jacaranda Avenue Residents' Association) v Multi Auto Parkhaus Limited & another; CEC Member, Built Environment and Urban Planning & 3 others (Interested Parties) (Environment and Planning Civil Case E013 of 2025) [2025] KEELC 7894 (KLR)

Environment and Land Court
6 November 2025
4,405 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~18 min to read original · ~4 min brief

The bottom line

#

A Lavington resident's bid to stop a commercial construction failed because he lacked evidence; neighbours challenging developments must back claims with documents at the start.

What this practically means

#

Executive summary

#
The Plaintiff, on behalf of residents of Jacaranda Avenue Estate, moved the Environment and Land Court by notice of motion seeking a declaration that a 2018 change of use approval for plot L.R No. 3734/1459, off James Gichuru Road, Lavington had expired, supervision and restoration orders against the regulators, disclosure of public participation records, and a permanent injunction stopping construction of a commercial office block. The Plaintiff alleged reliance on a lapsed change of user, construction before NCA approval, conflicting approvals, flawed public participation, and violations of constitutional rights. The Defendants obtained development permission from Nairobi City County and an EIA licence from NEMA, asserted full compliance and adequate public participation, and raised a preliminary objection that the ELC lacked original jurisdiction because the suit should first have gone to the National Environment Tribunal under EMCA and the Physical and Land Use Planning Liaison Committee under PLUPA. The court applied the exhaustion doctrine and its exceptions, noting counsel for the 1st Interested Party confirmed the Liaison Committee had not sat since 26 November 2024, that the suit raised mixed issues (change of use, development permission and EIA licence), and that the court's original jurisdiction under Article 162 cannot be ousted by statute. The preliminary objection was dismissed. On the application, the court found triable issues but no prima facie case: the effect of expiry of the change of user on subsequent approvals was a substantive question for trial, irreparable harm was pleaded without factual basis, and no special circumstances justified a mandatory injunction. The supervisory and restoration prayers were declined as premature. Both the preliminary objection and the application were dismissed with each party bearing their respective costs.

Questions the Court framed

#

The issues the Court set itself to decide, in its own words.

  1. 1.Whether or not there is merit in the preliminary objection (lack of original jurisdiction / failure to exhaust statutory remedies)
  2. 2.Whether or not the application succeeds

Key legal issues

#
01

Whether the court lacks jurisdiction for failure to exhaust statutory remedies under EMCA and PLUPA

Holding

The preliminary objection fails; the exhaustion doctrine does not oust the court's original jurisdiction where the Liaison Committee is defunct and the suit raises mixed issues

Reasoning

The 1st Interested Party confirmed the Liaison Committee had not sat since 26 November 2024, leaving the court as the only avenue for justice. The suit also raised mixed questions - challenging change of use, development permission and EIA licence together - and the court's original jurisdiction under Article 162 cannot be ousted by statute, so exhaustion would not offer an adequate remedy.

p. 8
02

Whether the plaintiff established a prima facie case and irreparable harm for interlocutory/mandatory injunction

Holding

No; the plaintiff raised triable issues but not a prima facie case, and pleaded harm only in general terms

Reasoning

The alleged expiry of the change of user and its effect on subsequent approvals is a substantive legal question requiring full evidence at trial. The plaintiff produced no document proving the area remained purely residential, and merely listed alleged environmental violations without factual basis, failing the Giella threshold and the special-circumstances requirement for mandatory injunctions.

Legal principles established

#
  • A preliminary objection must raise a pure point of law on the assumption that all facts pleaded by the other side are correct
  • The Environment and Land Court has original jurisdiction over land and environmental disputes, not limited to constitutional petitions, and such original jurisdiction cannot be ousted by statute
  • An interlocutory applicant must show some basis in fact for alleged violations, not merely list them, to establish irreparable harm

Court orders

#
  1. 1.The preliminary objection is dismissed
  2. 2.The plaintiff's amended notice of motion dated 23rd July 2025 (as amended) is dismissed
  3. 3.Each party to bear their respective costs

The bench

#

One judgment of the whole court — no separate or dissenting opinions.

majority

Wrote the judgment

Jurisdiction invoked
Article 162(2)(b) of the Constitution and Section 13 of the Environment and Land Court Act, No. 19 of 2011

Relief refused

#

Declaration that the change of use of 7/3/2018 is expired and the intended construction is unlawful, null and void

The import of the expiry of a change of use licence on subsequent approvals is a substantive legal question requiring determination at trial, not at the interlocutory stage

p. 9

Order compelling the 1st and 2nd Interested Parties to supervise the Defendants and restore the plot to its former state

No pleading of glaring refusal or negligence by the Interested Parties; the prayer was premature

p. 9

Permanent injunction restraining construction

No prima facie case established and no special circumstances for mandatory injunction

p. 9

Costs

Each party to bear their respective costs

Quotable passages

#

Verbatim from the judgment, each located to the page it appears on in the official PDF — so these can be cited and checked directly.

Accordingly, the preliminary objection fails and is dismissed.
p. 8preliminary objection on jurisdiction/exhaustion
I conclude that the applicant has failed to persuade court to grant both the orders of the temporary and mandatory order of injunction.
p. 9interlocutory and mandatory injunction refused
Both are dismissed with an order that each party bear their respective costs.
p. 9disposition and costs
courts ought to be fora of last resort and not the first port of call the moment a storm brews.
p. 7exhaustion doctrine
the High Court may, in exceptional circumstances, find that exhaustion requirement would not serve the values enshrined in the Constitution or law and permit the suit to proceed before it.
p. 7exceptions to exhaustion requirement

Issues in the judgment

#
minor

No suit/petition case number is stated anywhere in the judgment

minor

The identity of the 2nd Defendant is never disclosed in the judgment

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Mzee (Suing on Behalf of Jacaranda Avenue Residents' Association) v Multi Auto Parkhaus Limited & another; CEC Member, Built Environment and Urban Planning & 3 others (Interested Parties) (Environment and Planning Civil Case E013 of 2025) [2025] KEELC 7894 (KLR)", Case Analysis (2025). Not stated in the judgment (Notice of motion dated 23rd July 2025, amended 22nd September 2025). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2025/7894/eng@2025-11-06

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.