Mwingi Court Residents Associations v Barasa t/a Gabasa (K) Enterprises & 3 others (Environment and Land Petition E016 of 2024) [2025] KEELC 6766 (KLR)

Environment and Land Court
2 October 2025
2,534 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~10 min to read original · ~4 min brief

The bottom line

#

Kenyan court cancelled a commercial development's approvals because neighbours were never consulted and the landowner's consent was missing.

What this practically means

#

Executive summary

#
Residents of Mwingi Court Estate, Kileleshwa, petitioned the Environment and Land Court against the construction of a commercial complex on Nairobi/Block 23/576 and 577, alleging violation of their property rights (Article 40) and right to a clean and healthy environment (Article 42). They sought declarations, permanent and mandatory injunctions, quashing of any EIA licence and change of user permissions, restoration orders, and damages. The 2nd Respondent, the registered owner, confirmed it had licensed the 1st Respondent strictly for residential use, disavowed any role in the development, and alleged the 1st Respondent breached the licence agreement. The court found no proof of Article 40 violation, since no interference with the Petitioners' titles was demonstrated, and held the Article 42 claim premature as the development was abandoned midway. However, it held that the change of user was irregularly granted because the registered owner's written consent, required under Section 58(4) of the Physical and Land Use Planning Act, was never obtained, and that public participation required by the EIA Regulations and Section 58 of EMCA was not proved, contravening Article 10(2). Restoration orders, monitoring injunctions, and damages were refused. The petition partially succeeded: prayers (a), (b), (f), (g) and (h) were dismissed, while prayers (c), (d) and (e) were granted. Applying public interest litigation principles, each party was ordered to bear its own costs. Judgment delivered virtually on 2nd October 2025 by A. Omollo, Judge.

Key legal issues

#
01

Violation of Article 40 property rights

Holding

Not proved; change of character of the environment is not synonymous with restricting the right to own property

Reasoning

The court found no evidence that Respondents intended to take away Petitioners' property or that the development interfered with their individual titles. The alleged change in character of the area and traffic impact did not amount to an arbitrary deprivation or restriction of the use and possession of their properties under Article 40.

p. 4
02

Lawfulness of change of user and development permissions

Holding

Irregularly obtained for want of the registered owner's written consent

Reasoning

The licence agreement with the 1st Respondent restricted the premises to residential use. Section 58(4) of PLUPA required the registered owner's written consent, which was never given. The burden lay on the 1st and 4th Respondents to justify the approval; the foundation of the change of user application was therefore wanting and the 4th Respondent ought not to have granted it.

p. 5
03

Public participation in the EIA process

Holding

Not undertaken; the approvals contravened Article 10(2) and Section 58 of EMCA

Reasoning

Under Rules 2 and 17 of the EIA Regulations 2003, the 1st Respondent was required to prepare a project report including public/stakeholder consultation. Since the Petitioners alleged they were not consulted, the 1st and 4th Respondents bore the burden of proving public participation. No such evidence was adduced, leaving the allegation unchallenged and grounding reliefs (d) and (e).

p. 5
04

Whether the approving authorities should be compelled to undertake public participation

Holding

No; the statutory duty of public participation rests on the project proponent, not the approving authority

Reasoning

Sections 58 of EMCA and 59 of PLUPA impose the duty to carry out public participation on the project proponent, while the approving authority's duty is only to ensure compliance. The court therefore declined to compel the 3rd and 4th Respondents to undertake public participation themselves.

p. 5

Legal principles established

#
  • Where an applicant for development permission is not the registered owner, the written consent of the registered owner must be obtained and provided at the time of application
  • An applicant for development permission must notify the public of the proposed development project
  • In public interest litigation, costs should not be imposed on a party who brought a case against a state and lost without private gain

Court orders

#
  1. 1.Prayers (a), (b), (f), (g) and (h) of the Petition are dismissed for lack of merit
  2. 2.Prayers (c), (d) and (e) are granted - a permanent injunction restraining the 1st and 2nd Respondents from continuing development on Nairobi/Block 23/576 and 577, and declarations that any EIA licence and any change of user development permissions in respect of the suit properties are illegal, null and void, to be quashed, revoked and/or expunged
  3. 3.Each party to bear their own costs of the Petition

Authorities

#

Legislation

  • Constitution of Kenya, 2010Articles 10, 22, 23, 40, 42, 47, 70, 162(2), 232(1), 258
  • Environmental Management and Coordination Act, No. 8 of 1999Sections 3, 58, 59
  • Physical and Land Use Planning Act, 2019Sections 57, 58(4), 58(7), 59
  • Environmental (Impact Assessment and Audit) Regulations, 2003Rules 2 and 17

Cases cited (1)

  • Harun Mwau and Others vs A. G. and Others
    [2012] eKLR
Jurisdiction invoked
Articles 22, 23, 70 and 258 of the Constitution and Article 162(2) (Environment and Land Court jurisdiction)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Later judgments citing this (1)

#

Judgments in the corpus that rely on this one. Where the Court said how it treated the authority, that is shown.

Cite this brief

#

Cite this brief

Caselaw, "Mwingi Court Residents Associations v Barasa t/a Gabasa (K) Enterprises & 3 others (Environment and Land Petition E016 of 2024) [2025] KEELC 6766 (KLR)", Case Analysis (2025). Petition dated 21st May 2024. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2025/6766/eng@2025-10-02

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.