ELCStruck OutNot stated in the judgment as provided· [2025] KEELC 5689 (KLR)

Meath & another (Suing on behalf of Cola CBO) v Makori (Environment and Land Case E011 of 2023) [2025] KEELC 5689 (KLR)

Environment and Land Court
31 July 2025
2,303 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~9 min to read original · ~4 min brief

The bottom line

#

A community group lost its case because it went straight to court instead of first using the official appeal channels for planning and environment disputes.

What this practically means

#

Executive summary

#
Cola Community Based Organization, whose members hold titles within LR. 20172 in Mavoko, Machakos County, sued the registered owner of Plot LR. No. 20172/50 seeking a permanent injunction against an allegedly unauthorised multi-residential high-rise and an order for its demolition, contending breach of special conditions of the title restricting construction to single-household buildings approved by the Commissioner of Lands and the local authority, and coverage limits of fifty per centum. The Defendant asserted he held a Mavoko Municipality Notification of Approval of Development Permission dated 12th January 2023 and a NEMA Environmental Impact Assessment License dated 12th April 2023 for a ground-plus-two building of eight two-bedroom units. The court first found the requisite approvals existed at the time of filing, noting the public notice of change of user published in The Nation on 5th July 2022, and that the plaintiff's claim that construction predated the approvals was unsupported by evidence. It then held that the plaintiff's grievance lay within statutory administrative remedies: appeals against county development permission decisions lie to the County Physical and Land Use Planning Liaison Committee under Sections 61(3), 78 and 80 of the Physical and Land Use Planning Act, 2019, and appeals against NEMA licensing decisions lie to the National Environment Tribunal under Section 129 of EMCA. Failing to exhaust those remedies, the plaintiff invoked the court's jurisdiction prematurely. The suit was struck out with costs on 31st July 2025.

Key legal issues

#
01

Whether the construction on LR. No. 20172/50 had the requisite approvals

Holding

The court found that the relevant approvals (Mavoko Municipality development permission dated 12 January 2023 and NEMA EIA licence dated 12 April 2023) existed at the time of filing the suit, and the plaintiff's assertion that construction began before approvals was unsupported by evidence

Reasoning

The Defendant produced the NEMA acknowledgement, the Municipality's Notification of Approval of Development Permission, the EIA Report and the NEMA License as exhibits. A public notice of change of user was published in The Nation on 5th July 2022 inviting objections. The plaintiff's claim that construction preceded the approvals was unsupported. NEMA and the County Government, the issuing authorities, were not parties to the suit.

p. 3
02

Whether the court's jurisdiction was invoked prematurely

Holding

Yes - the plaintiff was bound to exhaust the administrative remedies under Section 80 of the Physical and Land Use Planning Act, 2019 (appeal to the County Physical and Land Use Planning Liaison Committee) and Section 129 of EMCA (appeal to the NET) before approaching the court, and the court therefore had no jurisdiction

Reasoning

The Physical and Land Use Planning Act, 2019 vests development control in the county executive committee and provides a complaint and appeal mechanism to the County Liaison Committee, whose determination is filed in the Environment and Land Court as a judgment. EMCA Section 129 provides appeals to the NET against NEMA licensing decisions, including conservatory orders. These statutory channels had to be exhausted first.

p. 5

Legal principles established

#
  • Where a statute provides an administrative remedy for disputes over development permissions and EIA licences, that remedy must be exhausted before resorting to the Environment and Land Court
  • Under the repealed Physical Planning Act, disputes relating to land use and building permission were to be ventilated in the relevant Liaison Committees, and disputes relating to EIA licensing in the National Environment Tribunal
  • The jurisdiction of the Liaison Committee is triggered only by a decision of the approving authority, and the jurisdiction of the NET is invoked after NEMA has made a decision on an application

Court orders

#
  1. 1.The suit is struck off with costs
  2. 2.It is so ordered

Authorities

#

Legislation

  • Physical Planning Act (repealed)Section 33(3)
  • Physical and Land Use Planning Act, 2019Section 2
  • Physical and Land Use Planning Act, 2019Section 61(3)
  • Physical and Land Use Planning Act, 2019Section 76
  • Physical and Land Use Planning Act, 2019Section 78
  • Physical and Land Use Planning Act, 2019Section 80
  • Environment Management and Coordination Act (EMCA)Section 129(1) and (2)
  • Environment Management and Coordination Act (EMCA)Section 129(3)
Jurisdiction invoked
Original civil jurisdiction of the Environment and Land Court; the court declined jurisdiction for failure to exhaust statutory remedies under Section 80 of the Physical and Land Use Planning Act, 2019 and Section 129 of EMCA

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Meath & another (Suing on behalf of Cola CBO) v Makori (Environment and Land Case E011 of 2023) [2025] KEELC 5689 (KLR)", Case Analysis (2025). Not stated in the judgment as provided. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2025/5689/eng@2025-07-31