ELCDismissedEnvironment and Land Petition (Nairobi), 2024

Kassam & 12 others v Shah & 16 others (Environment and Land Petition E007 of 2024) [2025] KEELC 5354 (KLR)

Environment and Land Court
17 July 2025
20,244 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~81 min to read original · ~4 min brief

The bottom line

#

What this practically means

#

Executive summary

#
The Petitioners, owners and residents of Muthaiga Valley (Anahita) Apartments on L.R No. 209/871/13, City Park Drive, Parklands, petitioned against high-rise residential developments by the 4th Respondent on neighbouring parcels L.R Nos 209/871/11 and 209/871/14. They sought declarations that the county development permissions, change of user approvals, NEMA EIA licenses, NCA compliance certificates and riparian pegging were irregular, null and void, together with injunctions, mandatory decommissioning and restoration orders, and damages, alleging violations of Articles 10, 35, 42 and 47 of the Constitution. The court framed nine issues. It held the Petition competent as raising substantive constitutional questions, and upheld the 9th-11th Respondents' affidavit as duly authorized. It declined to determine ownership of the suit properties, the Petitioners having pleaded no title claim. It held that approvals issued in the names of predecessors in title were at most voidable, applying the presumption of regularity; that the use of repealed-law forms, absent formal applications, absence of a County Director and of county or local plans did not invalidate permissions, especially as the development was nearly complete; that NCA certificates were valid; that the EIA licenses were lawfully issued for medium-risk projects with sufficient public participation by questionnaires; that construction of 112 units against a licence for 98 breached a licence condition already addressed by an enforcement order but did not invalidate the licence; that the 10-metre riparian pegging under repealed 2007 Rules was lawful; and that no Article 35 violation was shown. Photographic evidence failed to establish causal nexus to the alleged environmental harm in the absence of expert evidence. The Petition was dismissed with each party bearing their own costs.

Questions the Court framed

#

The issues the Court set itself to decide, in its own words.

  1. 1.Whether the Petition is competent
  2. 2.Whether the 9th-11th Respondents' Replying Affidavit is fatally defective
  3. 3.Whether the 4th Respondent is the legitimate owner of L.R Nos 209/871/11 and 209/871/14
  4. 4.Whether the issuance of the approvals and licenses in the names of persons other than the 4th Respondent rendered them invalid
  5. 5.Whether the licenses and approvals allowing the construction on the suit property were issued in violation of the Petitioners' rights to a clean and healthy environment
  6. 6.Whether the excavation and construction activities on the suit property infringe or threaten the Petitioners' right to a clean and healthy environment
  7. 7.Whether the pegging and marking undertaken by the 15th Respondent on the riparian reserve next to L.R No 209/871/11 was illegal and/or irregular
  8. 8.Whether the Petitioners' rights to information as guaranteed under Article 35 of the Constitution were violated
  9. 9.What are the appropriate remedies, if any

Key legal issues

#
01

Competency of the constitutional Petition

Holding

The Petition is competent as it raises substantive constitutional questions on Articles 10, 35, 42 and 47, going beyond mere procedural or administrative grievances

Reasoning

Applying the Anarita Karimi Njeru principle and the definition of a constitutional question, the court found the Petition identified the constitutional provisions said to be infringed and the manner of infringement, particularly the alleged violation of the right to a clean and healthy environment under Article 42 arising from irregular approvals. The objection that the Petition was a disguised appeal against development permissions was rejected.

p. 21
02

Authority of the deponent of the 9th-11th Respondents' Replying Affidavit

Holding

The affidavit was validly sworn; an express averment of authority is presumed valid absent rebuttal

Reasoning

Relying on Spire Bank Limited and Smartshop Limited, the court held that where a deponent states he is duly authorized, a bare denial without evidence to the contrary is insufficient. Mr. Masinde expressly stated he had authority, and the Petitioners adduced no evidence rebutting it.

p. 22
03

Ownership of the suit properties by the 4th Respondent

Holding

The court declined to determine ownership as no relief on title was pleaded; parties are bound by their pleadings

Reasoning

The Petition was not grounded on a claim for revocation or rectification of title, and the Petitioners asserted no competing ownership. Citing David Sironga Ole Tukai and IEBC v Mutinda Mule, the court confined itself to issues properly pleaded and declined to entertain abstract ownership claims.

p. 23
04

Validity of approvals and licenses issued in names other than the 4th Respondent

Holding

The approvals were issued to entities in the chain of title; the irregularity at most renders the approvals voidable, not null and void

Reasoning

The court found the approvals were issued to persons/entities in the chain of title, consistent with the 4th Respondent's explanation of delays in updating records. There was no evidence of deliberate misleading, no allegation the developments were on other parcels, and the 4th Respondent was registered as owner in 2024.

p. 24
05

Irregularities in development permissions (repealed law forms, missing applications, absent County Director and plans)

Holding

None of these irregularities invalidated the permissions; the presumption of regularity was not rebutted and public participation was adequate

Reasoning

Forms cited the repealed Physical Planning Act 1996, but the issuing authority did not disown the approvals and Article 159(2)(d) enjoins disregard of technicalities. The regulatory authorities affirmed receipt of applications. Newspaper notices and signboards satisfied Sections 58(7) and (8) PLUPA. Absence of county plans and of a County Director cannot nullify CECM authority, especially where development was nearly complete. Under the 2021 Development Control Policy the zone permits up to 20 floors and the approvals were within this.

p. 30
06

Validity of NCA compliance certificates

Holding

The NCA certificates were valid; alleged inconsistencies and fraud were not substantiated

Reasoning

The court found the project registration numbers reconciled (one pertained to an additional floor, another to L.R 209/871/11), differences between certificates merely reflected additional fields, and fraud allegations without proof fail the strict standard of proof. The sharing of the NCC-CPF Plan No AV-209 was not shown to be statutorily invalid.

p. 31
07

Validity of NEMA EIA licenses and adequacy of public participation

Holding

The EIA licenses were validly issued after development approvals; the projects were medium-risk requiring project reports, and public participation was sufficient

Reasoning

The licenses were issued after county approvals; constructing 112 units instead of 98 was a license-condition violation addressed by an enforcement order but did not retroactively convert the project to high-risk or invalidate the license. Questionnaires distributed locally met the threshold for medium-risk projects under EMCA and the 2003 Regulations, applying the British American Tobacco public participation framework.

p. 36
08

Alleged environmental harm and infringement of Article 42 rights

Holding

No conclusive finding of environmental violation; photographic evidence did not establish causal nexus and no expert reports were adduced

Reasoning

Photographs of effluent, darkened rooms and blocked access did not show the harm originated from the 4th Respondent's developments. Claims of structural damage, light obstruction and encroachment are technical and required expert opinion which was not provided; the architect's report relied on was admittedly inconclusive.

p. 36
09

Legality of the riparian pegging by the 15th Respondent

Holding

The pegging at 10 metres under the repealed Water Resources Management Rules, 2007 was lawful as the successor 2021 Rules had no delineation provision and the 2025 Regulations restored the same standard

Reasoning

Though conducted under repealed Rules, at the material time the 2021 Rules contained no riparian delineation provision. The 15th Respondent is the sole lawful agency for delineation, its follow-up site visits confirmed compliance, the Gitathuru/Mathare naming discrepancy was immaterial as the rivers interconnect, and the 2024 Cabinet 30-metre policy was prospective and general.

p. 38
10

Alleged violation of the right to information under Article 35

Holding

No violation found; the limb appeared abandoned, and the evidence showed substantial correspondence and information provided

Reasoning

The claim was not pursued in submissions. The record showed the 9th-11th, 12th, 14th and 15th Respondents corresponded with and provided information to the Petitioners regarding the developments, so no denial of information was established.

p. 39

Legal principles established

#
  • Allegations of fraud must be specifically pleaded, particularized and strictly proved; proof must meet a higher threshold than ordinary civil cases but not the criminal standard
  • In the absence of clear evidence to the contrary, administrative actions of public officials are presumed regular, lawful and reasonable
  • A procedural misstep does not nullify an otherwise regular process unless it affects substance, causes prejudice, or contravenes a mandatory statutory requirement
  • Development permissions issued in the name of a predecessor in title, without the registered owner's consent under Section 58(4) PLUPA, are voidable rather than null and void
  • Environmental and structural harm claims such as encroachment, structural damage and light obstruction are technical and require expert evidence; photographs alone cannot establish causal connection
  • The legal requirement for public participation in medium-risk EIA projects is that the opportunity to participate must be meaningfully afforded, not that every member of the public must respond

Court orders

#
  1. 1.The Petition dated 28th March, 2024 is dismissed
  2. 2.Each party shall bear their own costs

The bench

#

One judgment of the whole court — no separate or dissenting opinions.

majority

Wrote the judgment

Jurisdiction invoked
Article 22 and Article 70 of the Constitution; Section 13 of the Environment and Land Court Act

Relief refused

#

All twenty reliefs sought, including declarations that the development permissions, change of user approvals, EIA licenses, NCA certificates of compliance were null and void, permanent injunction, mandatory decommissioning and restoration orders, and general damages

The Petitioners failed to discharge the burden of proof; irregularities identified were procedural and not substantive; the presumption of regularity was not rebutted; no cogent expert evidence linked the developments to the alleged environmental harm

p. 39

Costs

As this is a public interest matter, each party shall bear their costs.

Quotable passages

#

Verbatim from the judgment, each located to the page it appears on in the official PDF — so these can be cited and checked directly.

In conclusion, this court finds that the Petition dated 28th March, 2024 wholly lacks merit and the same is dismissed.
p. 39Disposition - dismissal of the Petition
As this is a public interest matter, each party shall bear their costs.
p. 39Costs order
The idea is that, in the absence of clear evidence to the contrary, administrative actions should be presumed to be regular, lawful, and reasonable.
p. 28Presumption of regularity
Unless a procedural misstep afiects the substance or outcome of a decision, causes prejudice, or contravenes a mandatory statutory requirement, it cannot be the basis for nullifying an otherwise regular process.
p. 27Procedural irregularity and nullification
The legal requirement is not that every member of the public must respond, but that the opportunity to participate must be meaningfully afiorded.
p. 36Public participation standard
This is a violation of the license condition for which an enforcement order has been issued. It does not retroactively convert the original development into a high-risk project, nor does it invalidate the licence itself.
p. 33Effect of exceeding licensed unit numbers on EIA licence
The allegations presented in the Petition, as summarized above, do indeed raise substantive constitutional questions that warrant judicial inquiry.
p. 21Competency of the constitutional Petition

Issues in the judgment

#
minor

The deponent of the 9th-11th Respondents' Replying Affidavit is named inconsistently in the judgment

minor

The same deponent is later referred to as Wilfred Masinde

minor

The 12th Respondent's Director-General is referred to as 'Ms Mamo' in one passage despite being elsewhere described as male ('Mr. Mamo')

minor

Contradictory references to the court's earlier decision: cited as Millennium Gardens Management Limited vs Metricon Home Nairobi Company Limited but also as 'Millennium Gardens Management Limited vs Metricon Home Nairobi Company Limited' with differing citation formats for the same decision [2024] KEELC 6040

Key timeline

#

Practical implications

#

Frequently asked questions

#

Later judgments citing this (3)

#

Judgments in the corpus that rely on this one. Where the Court said how it treated the authority, that is shown.

Cite this brief

#

Cite this brief

Caselaw, "Kassam & 12 others v Shah & 16 others (Environment and Land Petition E007 of 2024) [2025] KEELC 5354 (KLR)", Case Analysis (2025). Environment and Land Petition (Nairobi), 2024. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2025/5354/eng@2025-07-17

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.