ELCPartially AllowedNot stated in the judgment· [2025] KEELC 4468 (KLR)

Kenya Electricity Transmission Co Ltd (K) v Hacienda Development Ltd; Kenya Power & Lighting Co Ltd (Interested Party) (Enviromental and Land Originating Summons E024 of 2024) [2025] KEELC 4468 (KLR)

Environment and Land Court
12 June 2025
1,766 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~7 min to read original · ~4 min brief

The bottom line

#

A Mombasa court allowed KETRACO to continue building a power line on private land in Mombasa, ruling that losing electricity services cannot be fairly repaid with money alone.

What this practically means

#

Executive summary

#
The plaintiff, KETRACO, moved the court by notice of motion dated 18.12.2024 seeking a temporary injunction restraining the defendant from interfering with construction of the 132kV Rabai–New Bamburi–Kilifi electricity transmission line on the defendant's parcel, Title Number 10279/II/MN, Mombasa County, plus police assistance in execution. KETRACO relied on KPLC's wayleave and written permission, and warned of daily idling charges under a government contract with a Spanish contractor. The defendant, an affordable-housing developer, disputed that the works were on the wayleave, alleged a deviation from the agreed route, and sought survey, valuation and compensation first. The defendant also filed a notice of motion dated 31.01.2025 seeking review, variation or setting aside of interim orders granted on 14.01.2025, contending the extracted order failed to capture a consent and contained an error apparent on the face of the record. The court framed three issues: review, injunction and costs. On review, it found no consent existed on the material date and no error on the face of the record, holding that dissatisfaction with the injunction was a matter for appeal. On the injunction, applying Giella v Cassman Brown, the court found a prima facie case (the deviation issue being for trial), and held that monetary compensation cannot adequately compensate loss of utilities; balance of convenience did not arise. The defendant's review application was dismissed with costs; the plaintiff's application was allowed in terms of orders 3 and 4 with costs in the cause; pre-trial directions were fixed for 09.07.2025.

Key legal issues

#
01

Review of interim orders

Holding

The defendant failed to establish a reviewable error; the extracted order reflected the court's actual ruling.

Reasoning

The court found no record of any consent on 14.01.2025; the defendant's own advocate had opposed extension of interim orders on that date. The extracted order mirrored Order No. 2 of the plaintiff's motion, so there was no error on the face of the record. Any grievance about the merits of the injunction lay on appeal, not review.

p. 3
02

Interim injunction principles

Holding

The plaintiff established a prima facie case and irreparable loss; balance of convenience need not be reached.

Reasoning

There was credible material of a power wayleave through the suit property and KPLC's written permission to KETRACO. Any alleged deviation could be determined at trial, with compensation as a remedy. Loss of utilities cannot adequately be compensated by monetary damages, satisfying the second Giella principle.

p. 4
03

Costs

Holding

The plaintiff's application allowed with costs in the cause; the defendant's review dismissed with costs.

Reasoning

Applying Section 27 of the Civil Procedure Act and the guidance in Giella v Cassman Brown, costs follow the event; where an injunction application is allowed, costs are in the cause.

p. 4

Legal principles established

#
  • Monetary compensation cannot be adequate compensation for loss of utilities.
  • A party dissatisfied with an interim injunction must appeal, not seek review.
  • Costs follow the event under the proviso to Section 27 of the Civil Procedure Act.

Court orders

#
  1. 1.The defendant's notice of motion dated 31.01.2025 is dismissed with costs.
  2. 2.The plaintiff's notice of motion dated 18.12.2024 is allowed in terms of orders Nos. 3 and 4 thereof with costs in the cause (temporary injunction restraining interference with construction works on Title Number 10279/II/MN and police assistance in compliance).
  3. 3.The matter is fixed for pre-trial directions on 09.07.2025.

Authorities

#

Legislation

  • Constitution of KenyaArticle 40(3)
  • Land Act, 2012 (Act No. 6 of 2012)Sections 139, 149, 150
  • Civil Procedure Act (Cap 21)Sections 1A, 1B, 3A, 27
  • Civil Procedure Rules 2010Order 40 Rule 1

Cases cited (2)

  • Giella vs Cassman Brown & Co. Ltd
    [1973] EA 358
  • Hussein Janmohamed & Sons –vs- Twentsche Overseas Trading Co. Ltd
    [1967] EA 287
Jurisdiction invoked
Article 40(3) of the Constitution of Kenya; Sections 139, 149 and 150 of the Land Act, 2012; Sections 1A, 1B and 3A of the Civil Procedure Act and Order 40 Rule 1 of the Civil Procedure Rules 2010

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Kenya Electricity Transmission Co Ltd (K) v Hacienda Development Ltd; Kenya Power & Lighting Co Ltd (Interested Party) (Enviromental and Land Originating Summons E024 of 2024) [2025] KEELC 4468 (KLR)", Case Analysis (2025). Not stated in the judgment. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2025/4468/eng@2025-06-12

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.