Samatar & 13 others v Delta Holdings Limited & 2 others (Environment & Land Case E085 of 2024) [2025] KEELC 3749 (KLR)
The bottom line
#Kenya's Environment and Land Court in Mombasa sent a property dispute to arbitration and froze development plans, but refused to block all land dealings.
What this practically means
#Executive summary
#Key legal issues
#Competency of the suit due to allegedly defective authority and verifying affidavits
The objection was a curable procedural technicality; plaintiffs granted leave to regularize within 30 days.
The 3rd defendant raised the competency objections for the first time in written submissions, not in the grounds of opposition, depriving plaintiffs of a chance to respond. The court held the defects curable under Article 159(2)(d) of the Constitution and Section 19(1) of the ELC Act, favouring substantive justice over form, and granted leave to regularize.
Whether the dispute should be referred to arbitration
Yes; the leases contained an arbitration clause and the 3rd defendant conceded arbitrability.
Clause 21 of the leases required disputes to be referred to arbitration under the Arbitration Act 1995. Although the 3rd defendant initially contended there was no arbitrable dispute, it conceded in submissions that the arbitration clause existed and that the real question was whether the subject matter was at risk. The court was satisfied the dispute was referable to arbitration.
Whether interim measures of protection should issue pending arbitration
Yes, by way of status quo preservation and injunction against alteration of plans, but no blanket inhibition.
Applying CMC Holdings and Safaricom, the court found the subject matter was under threat: the 3rd defendant claimed exclusive rights over common areas and denied plaintiffs' locus, demonstrating a serious threat to plaintiffs' investments. However, a blanket inhibition would cause undue hardship by preventing registration of partial discharges of unsold units.
Legal principles established
#- Procedural technicalities affecting pleadings are curable under Article 159(2)(d) of the Constitution and Section 19(1) of the ELC Act.
- Interim measures of protection under Section 7 of the Arbitration Act require an arbitration agreement, a threat to the subject matter, and assessment of the appropriate measure and its duration.
Court orders
#- 1.The dispute among the parties is referred to arbitration in accordance with the arbitration clauses contained in the lease agreements.
- 2.An interim measure of protection is granted for preservation of the current status quo regarding developments on LR No. 9X5/I/MN (LR 46XX50/I) pending the hearing and conclusion of arbitral proceedings.
- 3.An interim injunction is granted restraining the defendants from altering, changing or reviewing the development plan, architectural plan, building plan, sectional plan, or undertaking any structural changes or developments on LR 9X5/I/MN (CR 466XX0/I) pending the hearing and conclusion of the arbitral proceedings.
- 4.The plaintiffs are granted leave to regularize the anomalies in their authority to act and verifying affidavits within 30 days from the date thereof.
- 5.Costs of the application shall be in the cause.
- 6.Mention on 29.9.2025 to ascertain the status of the arbitral proceedings.
- Jurisdiction invoked
- Sections 6 and 7 of the Arbitration Act and Order 40 Rules 1 and 2 of the Civil Procedure Rules
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Samatar & 13 others v Delta Holdings Limited & 2 others (Environment & Land Case E085 of 2024) [2025] KEELC 3749 (KLR)", Case Analysis (2025). Chamber Summons dated 27.09.2024. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2025/3749/eng@2025-05-08
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.