#A Kenyan court awarded costs to a property buyer even after the developer fixed the problem mid-case, confirming that resolving a dispute late doesn't avoid paying the other side's legal fees.
What this practically means
#Executive summary
#Key legal issues
#Entitlement to costs where the suit is overtaken by events
The Plaintiff is the successful party and is awarded costs with interest
Costs follow the event under Section 27 of the Civil Procedure Act, which is discretionary but presumptively awards costs to the successful party. 'The event' means the result of the entire litigation. Here the Defendant completed the registration which was the Plaintiff's cause of action, vindicating the claim. Unopposed status does not disqualify the Plaintiff, both parties agreed costs was the sole issue, and the arbitration clause was immaterial to the court's costs jurisdiction.
Legal principles established
#- Costs follow the event; a plaintiff is not deprived of successful-party status merely because the suit was unopposed or the dispute was resolved mid-stream
Court orders
#- 1.The Plaintiff is awarded costs of this suit together with interest thereon at court rates from the date of filing of suit until payment in full
- 2.The registry shall mark this file as closed
- Jurisdiction invoked
- Original jurisdiction of the Environment and Land Court over land leases/registration; costs jurisdiction under Section 27 of the Civil Procedure Act
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Bella Hill Management Limited v Vipingo Development Plc (Environment & Land Case 121 of 2018) [2025] KEELC 3235 (KLR)", Case Analysis (2025). . Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2025/3235/eng@2025-04-08
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.