#Kenya's Environment and Land Court refused a site visit in a property damage dispute, saying courts only inspect land after evidence is heard, not before.
What this practically means
#Executive summary
#Key legal issues
#Whether a site visit should be ordered at the interlocutory stage
No – the application is premature as the hearing has not commenced and the matters to be observed should crystallise during evidence.
Order 18 Rule 11 empowers the court to inspect property at any stage, but superior court authority holds that a locus visit is exceptional and serves to clarify evidence already given, not to fill gaps or collect evidence. The matters plaintiffs wanted observed (proximity, excavation depth, cracks) are best captured in expert reports filed, served and subjected to cross-examination; a visit before evidence would risk the court becoming a witness.
Costs of the application
Costs in the cause despite the plaintiffs' failure.
Section 27 of the Civil Procedure Act provides that costs follow the event unless otherwise ordered for good cause. The court found it fair and just that costs of the application be in the cause, notwithstanding that the plaintiffs failed in their quest.
Legal principles established
#- A site visit (locus in quo) is the exception rather than the rule and requires special circumstances; its purpose is to help the court understand evidence adduced, not to collect missing evidence.
- The court should not visit the locus before a reasonable basis has been made through factual evidence presented before it.
Court orders
#- 1.The plaintiffs' notice of motion dated 18th July 2024 is without merit.
- 2.The said application is dismissed.
- 3.Costs be in the cause.
- Jurisdiction invoked
- Order 18 Rule 11 of the Civil Procedure Rules 2010; sections 1A, 1B, 3 and 63 of the Civil Procedure Act
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "D’Souza & 2 others v Khansa Developers Limited & another (Civil Suit E005 of 2024) [2025] KEELC 1010 (KLR)", Case Analysis (2025). ELC Case (Mombasa) – Notice of Motion dated 18th July 2024 in the main suit. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2025/1010/eng@2025-03-05
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.