ELCPartially AllowedPetition (Environment and Land Court, Nairobi) - notice of motion dated 11th June 2024; tender No. NCC/ENV/287/A./3882/2022-2023· [2025] KEELC 634 (KLR)

Mbae v Nairobi City County Government; China National Electric Engineering Co (Interested Party) (Environment and Planning Petition 4 of 2023) [2025] KEELC 634 (KLR)

Environment and Land Court
10 February 2025
3,133 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~13 min to read original · ~4 min brief

The bottom line

#

Kenya's Environment and Land Court gave a Dandora waste plant challenger extra time to appeal and blocked construction for four months, but the signed contract stands.

What this practically means

#

Executive summary

#
The Petitioner, who had lost a petition in which this court struck out his challenge to the award of tender NCC/ENV/287/A./3882/2022-2023 for a Waste to Energy Processing Plant at Dandora Dumpsite to China National Electric Engineering Company, moved the court by notice of motion dated 11th June 2024. He sought a temporary injunction staying the award pending his intended appeal, alternatively reinstatement or extension of earlier injunctive orders, and leave to lodge a notice of appeal out of time. He explained that judgment was delivered on 24th April 2024, a day earlier than the originally scheduled 25th April 2024, without direct notice to the parties, and that he only learnt of it in late May 2024, partly via social media. The Respondent and Interested Party opposed, contending the applicant had not shown substantial loss, had delayed 47 unexplained days, and that the application was overtaken by events because they executed a contract on 28th August 2024 in the absence of any stay. Applying the Salat principles on extension of time, the court found 47 days was not inordinate delay and granted the benefit of doubt to the applicant where no prejudice was shown. On the injunction, applying Patricia Njeri v National Museum of Kenya and Giella v Cassman Brown, the court held the application was not moot since the order sought reached implementation of the signed contract. It granted the injunction on revised terms, excluding the award and the design and financing phases, restraining only building, operating, maintaining and transferring the project for four months. The application was allowed on those terms by A. Omollo, Judge, on 10th February 2025.

Key legal issues

#
01

Extension of time to lodge a notice of appeal out of time

Holding

A 47-day delay was held not to be inordinate; the applicant was given the benefit of doubt regarding lack of notice of the early delivery of judgment, and no prejudice was demonstrated.

Reasoning

Applying the Salat principles, the court weighed the explanation that the judgment was delivered on a date earlier than scheduled without direct notice to the parties. Although doubts existed about what the petitioner did on the due date and who at the registry was contacted, the court granted the benefit of doubt, holding 47 days not inordinate and noting no prejudice was deponed to by the Respondent or Interested Party if leave were granted.

p. 5
02

Temporary injunction pending appeal

Holding

Injunction granted but on revised terms: limited to building, operating, maintaining and transferring the project, for four months only, since award and design/finance components were overtaken or harmless.

Reasoning

The court applied the Patricia Njeri principles and Giella v Cassman Brown. It held the application was not overtaken by events because the order sought would restrain implementation of the signed contract. Weighing hardship, it found building, operating and transferring the dumpsite would prejudice the appeal, while award, design and financing would not, and granted a time-limited injunction to allow the appeal to be prosecuted.

p. 6
03

Whether the application was overtaken by events given the contract signed on 28th August 2024

Holding

Rejected; the order sought went beyond award and sought to restrain implementation of the signed contract.

Reasoning

The court read the proposed order as targeting not only the award but the whole project lifecycle - design, finance, build, operate, maintain and transfer - so the existence of the signed contract did not render the motion futile. It therefore proceeded to consider the injunction on its merits and granted modified, time-bound orders.

p. 6

Legal principles established

#
  • The Environment and Land Court in its appellate jurisdiction has power to grant a temporary injunction pending appeal where the ends of justice demand and the procedure for instituting an appeal has been complied with.
  • Extension of time is an equitable remedy available only to a deserving party at the discretion of the court, requiring a satisfactory explanation of the delay.

Court orders

#
  1. 1.Time is extended for the Petitioner to file and serve a notice of appeal within 7 days of the date of this ruling
  2. 2.Temporary injunction restraining the Respondent and the Interested Party from Building, Operating, maintaining and Transferring a Waste To Energy Processing Plant At Dandora Dumpsite To M/s China National Electric Engineering Company (NCC/ENV/287/A./3882/2022-2023) for a period of Four (4) months from the date of delivery of the ruling

Authorities

#

Legislation

  • Civil Procedure ActSections 1A & 3A
  • Civil Procedure RulesOrder 40
  • Civil Procedure RulesOrder 42
  • Civil Procedure RulesOrder 21
  • Civil Procedure RulesOrder 51 Rule 10
  • Constitution of KenyaArticle 159

Cases cited (8)

  • David Bundi v Timothy Mwenda Muthee
    [2022] eKLR
  • Raphael Mulinge Muthusi & 2 others v Mary Ndila Nyolo
  • Patricia Njeri & 3 Others vs. National Museum of Kenya
    [2004] eKLR
  • Giella vs. Cassman Brown
    [1973] EA 358
  • Stanley Kangethe Kinyanjui vs Tony Ketter & Others
    [2013] eKLR
  • Nicholas Kiptoo Arap Korir Salat v Independent Electoral and Boundaries Commission & 7 others
    [2014] eKLR
  • Ecobank Kenya Limited v Meya Agri Traders Limited
    [2021] eKLR
  • County Executive of Kisumu v County Government of Kisumu & 8 others
    SC. Civil Appl. No. 3 of 2016; [2017] eKLR
Jurisdiction invoked
Section 1A & 3A of the Civil Procedure Act; Orders 40, 42 and 21 of the Civil Procedure Rules; Article 159 of the Constitution

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Mbae v Nairobi City County Government; China National Electric Engineering Co (Interested Party) (Environment and Planning Petition 4 of 2023) [2025] KEELC 634 (KLR)", Case Analysis (2025). Petition (Environment and Land Court, Nairobi) - notice of motion dated 11th June 2024; tender No. NCC/ENV/287/A./3882/2022-2023. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2025/634/eng@2025-02-10

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.