Kazimzuri v North Coast Development Company Limited (Environment and Land Appeal 25 of 2021) [2024] KEELC 6755 (KLR)
The bottom line
#What this practically means
#Executive summary
#Key legal issues
#Whether the appeal should be dismissed for want of prosecution under Order 42 Rule 35
The application failed because the Respondent did not prove that directions under Order 42 Rule 13 had been given, which is a mandatory precondition to dismissal; in any event the Record of Appeal had been filed, overtaking the application
Order 42 Rules 35(1) and (2) are couched in mandatory terms requiring (a) directions taken by the court and (b) lapse of three months after the directions. The court adopted Pinpoint Solutions Ltd v Lucy Waithegeni Wanderi, holding an appeal cannot be dismissed before directions are taken. The record showed the appeal delay was largely attributable to the trial court's failure to type proceedings, and the Record of Appeal had since been filed.
Whether the Appellant's delay was excusable
Yes, largely, since the delay was caused by the lower court registry's failure to type and certify proceedings, and the court took judicial notice of staffing shortfalls at Mombasa
The court noted the Appellant consistently attributed non-filing of the Record of Appeal to untyped proceedings and that the court itself had summoned the Court Administrator to have proceedings typed. The judge, posted at the station for three years, accepted that understaffing of office administrators delays typing of proceedings, so the Appellant should not be punished for registry delay.
Who bears the costs of the application
Although the application was overtaken by events, costs were awarded to the Respondent because the Appellant bore responsibility for the prolonged delay in filing the Record of Appeal
Applying Section 27(1) of the Civil Procedure Act, costs are discretionary and follow the event. The court found the Appellant had a duty to demonstrate steps taken to finalise the appeal and had failed to do so, so despite the application being overtaken by events, it was reasonable that the Respondent be awarded costs of the application.
Legal principles established
#- An appeal cannot be dismissed for want of prosecution under Order 42 Rule 35(1) unless directions under Rule 13 have first been given and three months have lapsed thereafter
- Costs are in the discretion of the court and follow the event unless the court for good reason otherwise directs
- A party alleging mischief or abuse of process must substantiate the allegation with evidence
Court orders
#- 1.That the Notice of Motion application dated 12th April, 2023 partly succeeds on costs, being largely found to be overtaken by events as the Appellant has already filed the Record of Appeal
- 2.That the matter be fixed for mention on 28th October, 2024 for taking final direction on the disposal of the appeal pursuant to Section 79B of the Civil Procedure Act and Orders 42 Rules 11, 13 and 16 of the Civil Procedure Rules, 2010
- 3.That the appeal be prosecuted within thirty (30) days from the date the directions shall have been given
- 4.That the Court reserves a judgment date on 27th January, 2025
- 5.That costs of the application be awarded to the Respondent to be borne by the Appellant
- On appeal from
- Chief Magistrate's Court, Mombasa (CMCC (ELC) Mombasa No. 1 of 2021)
- CMCC (ELC) Mombasa No. 1 of 2021
- Jurisdiction invoked
- Appellate jurisdiction under Sections 79B to 79G of the Civil Procedure Act, Cap. 21 and Order 42 of the Civil Procedure Rules, 2010; Environment & Land Court Act No. 19 of 2011, Sections 3 & 13
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Kazimzuri v North Coast Development Company Limited (Environment and Land Appeal 25 of 2021) [2024] KEELC 6755 (KLR)", Case Analysis (2024). Not stated in the judgment text. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2024/6755/eng@2024-10-09
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.