ELCPartially AllowedNot stated in the judgment text provided (Petitioner's application dated 8th November, 2023, amended 10th November, 2023)· [2024] KEELC 6742 (KLR)

Mahmud v Al Madaar Trading Company Ltd & another; Nairobi City County Government & another (Interested Parties) (Environment & Land Petition E022 of 2023) [2024] KEELC 6742 (KLR)

Environment and Land Court of Kenya
7 October 2024
3,187 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~13 min to read original · ~4 min brief

The bottom line

#

A Nairobi court ordered KURA, the county government and the water company to repair broken sewer lines within 14 days after a Kibera resident's home was flooded with sewage.

What this practically means

#

Executive summary

#
This interlocutory ruling by the Environment and Land Court at Nairobi (M.D. Mwangi, J) determined the Petitioner's application dated 8th November 2023, amended 10th November 2023, seeking a mandatory injunction compelling the 1st and 2nd Respondents to repair drainage lines damaged during construction of a box culvert at Toughgone, Makina Ward, Kibera, and a temporary injunction restraining further construction. The Petitioner alleged that the 1st Respondent, a contractor engaged by the 2nd Respondent, negligently destroyed sewer lines, causing sewage to flood his residence, damaging household items and exposing his family to disease. The 1st Respondent denied negligence, asserting it followed approved standards and that sewer maintenance fell to the 2nd Interested Party (the water and sewerage provider). The 2nd Interested Party contested its joinder, denied causing the damage, claimed it had repaired the leaking line, and asserted the Petitioner's premises were not connected to the sewer system. Framing three issues - mandatory injunction, temporary injunction, and costs - the court applied the heightened threshold for mandatory injunctions and the Giella principles for temporary injunctions. Relying on Articles 42, 69 and 70 of the Constitution, the precautionary principle, and a court-ordered site visit report confirming ongoing sewage overflow, the court found non-compliance with its earlier ex parte repair order and held the case proper for a mandatory injunction. It granted a mandatory injunction against the 1st and 2nd Respondents and the 2nd Interested Party, jointly and severally, to repair the drainage lines within fourteen days, but refused the temporary injunction since the repair order removed any risk of further harm and the construction benefited the public. Costs were awarded to the Applicant under section 27 of the Civil Procedure Act.

Key legal issues

#
01

Whether a mandatory injunction should issue at the interlocutory stage

Holding

Yes - the court found a damaged sewer line, ongoing leakages and overflow, non-compliance with its earlier ex parte order, and held this a proper case for a mandatory injunction.

Reasoning

The court applied the higher threshold for mandatory injunctions from Kenya Breweries v Washington Okeyo citing Halsbury's Laws, Vol. 24, para 948. It found the case clear and the act simple and remediable. A site visit report by the Assistant Deputy Registrar confirmed sewage overflow and the Petitioner's unconnected sewer pipe, negating the 2nd Interested Party's claim of repair. The court invoked Articles 42, 69 and 70 of the Constitution and the precautionary principle to justify preventive intervention against continuing environmental harm.

p. 5
02

Whether a temporary injunction restraining further construction should issue

Holding

No - with the mandatory injunction in place, no further harm would befall the Applicant and the construction serves the public benefit.

Reasoning

Applying Giella v Cassman Brown as elaborated in Mrao and Nguruman, the court found the Petitioner had a prima facie case given the damaged sewer line and his Article 42 right. However, on the irreparable harm limb, it reasoned that the mandatory injunction already secured repair of the drainage lines, so no further harm would follow. It declined to halt construction that would benefit Nairobi residents generally, finding no merit in the temporary injunction.

p. 7
03

Costs of the application

Holding

Costs follow the event under section 27 of the Civil Procedure Act; the successful Applicant was granted costs.

Reasoning

The court invoked section 27 of the Civil Procedure Act, which provides that costs shall follow the event, with the successful party ordinarily having costs. Having succeeded on the mandatory injunction limb of the application, the Petitioner was awarded the costs of the application against the Respondents and Interested Party against whom the order issued.

p. 7

Legal principles established

#
  • A mandatory injunction may be granted at the interlocutory stage where the case is clear, the act is simple and summary and easily remedied, or where the defendant attempts to steal a match.
  • The three Giella conditions are sequential hurdles; if no prima facie case is established the court need not consider the remaining conditions.
  • Article 42 guarantees the right to a clean and healthy environment and the right to seek redress without demonstrating loss or injury.

Court orders

#
  1. 1.A mandatory injunction is hereby issued against the 1st and 2nd Respondents and the 2nd Interested Party compelling them jointly and severally to forthwith repair the drainage lines in their construction site at Toughgone in Makina Ward, in Kibera in any event within the next fourteen (14) days from the date of this ruling.
  2. 2.The costs of the application are granted to the Applicant.

Authorities

#

Legislation

  • Constitution of KenyaArticle 42
  • Constitution of KenyaArticle 69
  • Constitution of KenyaArticle 70
  • Physical Planning ActSections 29, 30, 38
  • Civil Procedure ActSection 27

Cases cited (9)

  • Malier Unissa Karim –vs- Edward Oluoch Odumbe
    (2015) eKLR
  • Kenya Breweries Ltd -Vs- Washington Okeyo
    (2002) EA 109
  • Jay Super Power Cash and Carry Ltd –Versus- Nairobi City Council and 20 others
    CA 111/2002
  • Shepard Homes Case
  • Giella -vs- Cassman Brown
    [1973] EA 358
  • Mrao Ltd. –vs- First American Bank of Kenya Ltd & 2 Others
    [2003] eKLR
  • Nguruman Ltd –vs- Jan Bonde Nielsen & 2 Others
    (2014) eKLR
  • Nicholas Njeru Muturi –vs- Thome Dynamics Limited & Another
    [2022] eKLR
  • Pius Kipchirchir Kogo –vs- Frank Kimeli Tenai
    (2018) eKLR
Jurisdiction invoked
Articles 42, 69 and 70 of the Constitution of Kenya (environmental rights and redress)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Mahmud v Al Madaar Trading Company Ltd & another; Nairobi City County Government & another (Interested Parties) (Environment & Land Petition E022 of 2023) [2024] KEELC 6742 (KLR)", Case Analysis (2024). Not stated in the judgment text provided (Petitioner's application dated 8th November, 2023, amended 10th November, 2023). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2024/6742/eng@2024-10-07