ELCPartially AllowedPetition dated 7th December 2022 (E005 of 2022, not expressly stated)· [2024] KEELC 4877 (KLR)

Dahir v Lapsset Corridor Development Authority & 3 others (Environment & Land Petition E006 of 2022) [2024] KEELC 4877 (KLR)

Environment and Land Court
20 June 2024
3,557 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~14 min to read original · ~4 min brief

The bottom line

#

Kenya's Environment and Land Court ordered the government to compensate a Garissa landowner whose land was taken for the LAPSSET project without notice or payment.

What this practically means

#

Executive summary

#
The Petitioner, Mohamed Bashir Dahir, petitioned alleging that the Respondents breached Articles 40, 42, 43, 47 and 63 of the Constitution by constructing the LAPSSET Corridor through his 6.0 Ha parcel at Diiso, Garissa County (PDP No. 326/2017/34), allocated to him by the defunct Municipal Council of Garissa in April 2009, without compulsory acquisition notice or compensation. He sought a declaration of breach, a permanent injunction, alternatively compensation, and general damages. The Respondents contended the land was community land, that the PDP was irregularly issued after gazettement of the acquisition notices, that due process and public participation were followed, and that the parcel did not fall within the gazetted corridor. The court framed three issues: ownership, due process in compulsory acquisition, and the reliefs. It found the Petitioner was the lawful and beneficial owner, relying on the allocation letter, rate receipts, gazettement of the development plan, and the County Government's letter recommending title processing; the land, having been allocated before the Community Land Act, 2016, was not community land. It further found the Petitioner was never served with the mandatory preliminary notice under Section 107(5) of the Land Act and was not involved in the acquisition, violating Articles 40 and 47. The petition was allowed in part: a declaration of violation issued, the National Land Commission was ordered to pay just compensation within 120 days, and the Petitioner got costs. The permanent injunction was refused as the project was complete, and general damages were declined as compensation for the land was adequate.

Key legal issues

#
01

Lawful ownership of land parcel PDP No. 326/2017/34

Holding

The Petitioner was the lawful and beneficial owner as allottee of the defunct Municipal Council of Garissa; the land was not community land

Reasoning

The court relied on the 2009 allocation letter from the Town Clerk, payment receipts, the gazetted development plan, and the 4th Respondent's 2019 letter recommending title processing. The 4th Respondent, which authored most documents, never challenged their authenticity. The land had been allocated and adjudicated before the Community Land Act, 2016 and had become private property requiring only formalization of title.

p. 5
02

Whether due process was followed in compulsorily acquiring the suit land

Holding

No due process was followed; the Petitioner was neither served with the statutory preliminary notice nor involved, violating Articles 40 and 47

Reasoning

Article 40(3) and Sections 107 and 110 of the Land Act set out the compulsory acquisition process. The suit land was not among parcels gazetted for acquisition, yet construction traversed it. The court found the Petitioner was never served with the NLC preliminary notice under Section 107(5), a mandatory requirement, and thus was deprived of property without due process, entitling him to prompt and adequate compensation.

p. 7
03

Whether the orders sought should issue

Holding

Declaration and compensation granted; permanent injunction and general damages refused

Reasoning

The permanent injunction could not issue because construction of the corridor through the land was already complete. The Petitioner was entitled to compensation for the appropriated portion rather than an injunction. General damages were also declined since compensation for the land value would be adequate. The court therefore allowed the petition in part and directed the NLC to pay just compensation within 120 days.

p. 7

Legal principles established

#
  • Service of the preliminary notice under Section 107(5) of the Land Act is a mandatory requirement in the compulsory acquisition process; acquisition of an owner's land without notice and involvement violates Article 40
  • An injunction will not issue to restrain an act that has already been completed
  • An allotee who has fulfilled all pre-requisite conditions, whose PDP has been gazetted without objection, is the lawful/beneficial owner even before registration of title, and such land is not community land

Court orders

#
  1. 1.An order and declaration that the Respondents acted in violation and breach of Articles 40 and 47 of the Constitution
  2. 2.The National Land Commission to process and make payment in full of just compensation to the Petitioner in respect of the portion of land parcel PDP No. 326/2017/34 situated in Garissa utilized for the construction of the LAPSSET Corridor Project
  3. 3.Compensation to be made within 120 days from the date of the Judgment
  4. 4.The Petitioner awarded the costs of the Petition

Authorities

#

Legislation

  • Constitution of Kenya, 2010Article 40(3)
  • Constitution of Kenya, 2010Articles 42, 43, 63, 47
  • Land Act, No. 6 of 2012Sections 107, 110(1), Part VIII
  • Community Land Act, 2016null
  • Physical Planning Actnull

Cases cited (2)

  • Giella v Cassman Brown
    (1973) EA 358
  • Anarita Karimi Njeru v Republic
    (1979) 1 KLR 54
Jurisdiction invoked
Articles 40, 47 and 63 of the Constitution of Kenya, 2010 (original constitutional petition jurisdiction of the Environment and Land Court)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Dahir v Lapsset Corridor Development Authority & 3 others (Environment & Land Petition E006 of 2022) [2024] KEELC 4877 (KLR)", Case Analysis (2024). Petition dated 7th December 2022 (E005 of 2022, not expressly stated). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2024/4877/eng@2024-06-20

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.