ELCStruck OutPetition (Notice of Motion dated 22nd November, 2022)· [2024] KEELC 4024 (KLR)

Irungu v Hayer Marquis Limited & 2 others (Environment & Land Petition E034 of 2021) [2024] KEELC 4024 (KLR)

Environment and Land Court
2 May 2024
1,809 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~7 min to read original · ~4 min brief

The bottom line

#

A Nairobi court struck out an application seeking the same injunction a party had already agreed to abandon by consent, warning that relitigating settled matters abuses court process.

What this practically means

#

Executive summary

#
The Petitioner, Professor Lucy Irungu, moved the Court by Notice of Motion dated 22nd November 2022 seeking an injunction restraining the 1st Respondent, National Housing Corporation, from continuing construction on LR No 209/9674 pending determination of her Petition, contending the construction was contaminating her residence on LR 209/16014. She asserted that earlier conservatory orders granted on 28th September 2021 were withdrawn by consent without her instructions. The 1st Respondent, through its Finance Manager Omar Ali, replied that construction was substantially complete (95.2%), that the EIA Licence challenge belonged before the National Environment Tribunal, and that on 12th October 2021 Petitioner's then-Advocate consented to compromise both the Petitioner's Motion of 15th September 2021 and the Respondent's Motion of 2nd October 2021, with the interim orders set aside. The Court examined the record and confirmed the consent order adopted on 12th October 2021. Applying Kenya Commercial Bank Ltd v Specialized Engineering Co. Ltd and S M N v Z M S, it held that a consent order is contractual and binding unless fraud, collusion, agreement contrary to public policy, or misapprehension is proved. Since no attempt had been made to set aside the consent order, and the new Motion sought the same relief as the compromised Motion, the Court found the application to be an attempt to by-pass the consent and re-litigate the issues, amounting to an abuse of court process. The Motion dated 22nd November 2022 was struck out with costs to the 1st Respondent.

Key legal issues

#
01

Effect of the consent order of 12th October, 2021

Holding

The consent order setting aside the interim conservatory orders and marking the earlier Motion withdrawn remains valid and unvaried; it binds the Petitioner

Reasoning

The Court traced the proceedings and found that on 12th October 2021, Petitioner's Counsel consented to compromise both Motions and set aside the interim orders. No attempt had been made to set aside that consent order under the KCB v Specialized Engineering principles. The Petitioner's claim of lack of instructions could not displace the binding consent absent proof of fraud, collusion or misapprehension.

p. 4
02

Whether the present Motion is an abuse of process

Holding

Yes; the Motion seeks the identical relief (restraint of construction pending Petition) as the compromised Motion of 15th September, 2021, amounting to re-litigation by-passing the consent order

Reasoning

The Court compared the two Motions and found both sought the same relief - restraining construction until determination of the Petition. Seeking afresh what was compromised by a valid consent constitutes abuse of court process, rendering the Motion fatally defective and unmerited, justifying striking it out.

p. 4

Legal principles established

#
  • A consent order entered into by counsel is contractual in nature and binding unless it is proved it was obtained by fraud, collusion, agreement contrary to the policy of the court, or without sufficient material facts or in misapprehension of such facts
  • Filing a fresh application seeking the same relief already compromised by a valid consent order constitutes an abuse of court process

Court orders

#
  1. 1.The Notice of Motion dated 22nd November, 2022 is struck out
  2. 2.Costs of the application to the 1st Respondent

Authorities

#

Legislation

  • Civil Procedure ActSections 1A, 1B and 3A
  • Civil Procedure Rules, 2010Order 40 Rule 1; Order 51 Rule 1

Cases cited (2)

  • Kenya Commercial Bank Ltd v Specialized Engineering Co. Ltd
    [1982] KLR 485
  • S M N v Z M S & 3 others
    [2017] eKLR
Jurisdiction invoked
Sections 1A, 1B and 3A of the Civil Procedure Act; Orders 40 Rule 1 and 51 Rule 1 of the Civil Procedure Rules, 2010

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Irungu v Hayer Marquis Limited & 2 others (Environment & Land Petition E034 of 2021) [2024] KEELC 4024 (KLR)", Case Analysis (2024). Petition (Notice of Motion dated 22nd November, 2022). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2024/4024/eng@2024-05-02

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.