ELCStruck OutPetition (Nairobi), dated 1st September 2023· [2024] KEELC 3472 (KLR)

Mbae v Nairobi City County Government (Environment & Land Petition 4 of 2023) [2024] KEELC 3472 (KLR)

Environment and Land Court
24 April 2024
3,371 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~13 min to read original · ~4 min brief

The bottom line

#

Kenya's Environment and Land Court struck out a challenge to the Dandora Waste-to-Energy tender, ruling it was filed too early and before the wrong forum.

What this practically means

#

Executive summary

#
The Petitioner, Advin Muthoni Mbae, petitioned the Environment and Land Court challenging the award by Nairobi City County of tender No. Ncc/Env/287/A./3882/2022-2023 to China National Electric Engineering Company for a Waste to Energy Processing Plant at Dandora Dumpsite. He sought a declaration that his rights under Articles 10, 42, 47 and 50 were violated and certiorari to quash the award, arguing the tendering was opaque, lacked public participation, contravened EMCA and was inconsistent with orders in ELC Constitutional Petition No. 43 of 2019 requiring decommissioning of the Dandora dumpsite. The Respondent and Interested Party opposed, contending the petition was premature (no contract signed, no EIA conducted), that PPP Act remedies had not been exhausted, that the court lacked jurisdiction, and that allegations of breaching the ELC decree were res judicata. The court framed four questions. It held the petition premature since no activity had commenced on site and no contract had been signed, making rights violations anticipatory. Although, following Abidha Nicholas, the exhaustion objection does not defeat a constitutional rights petition, the court held it lacked power under Article 162(2)(b) to quash a tender award, as tendering disputes do not concern use and occupation of land. Alleged breach of the ELC Petition No. 43 of 2019 decree was res judicata, having been determined in a ruling of 9th November 2023. The petition was struck out with no order as to costs, each party bearing its own costs in view of the public-interest motivation.

Key legal issues

#
01

Prematurity/ripeness

Holding

The petition was filed prematurely because only the tender had been awarded, no contract had been signed, no activity had commenced on the dumpsite and no EIA had been undertaken

Reasoning

The court found there was no dispute that no activity had commenced on the Dandora dumpsite beyond the award of the tender. With no contract signed, the scope of works could not be inferred and no environmental impact could be established. The EIA and public participation would follow contract signature, so allegations of rights violations were anticipatory.

p. 7
02

Jurisdiction over the tender award

Holding

The Environment and Land Court lacks power to quash the tender award because tendering disputes do not concern use and occupation of land

Reasoning

The court accepted that the exhaustion objection fails where constitutional violations are alleged, but nonetheless examined jurisdiction over prayer 2. Article 162(2)(b) confers jurisdiction over land use and occupation disputes; advertising, evaluating and awarding a tender falls outside that, and the PPP Act provides the appellate channel via the Committee and the High Court.

p. 7
03

Res judicata on breach of ELC Petition No. 43 of 2019 orders

Holding

Alleged breach of the orders in ELC Petition No. 43 of 2019 cannot found a fresh suit; the issue was already raised and determined in a ruling of 9th November 2023

Reasoning

The Petitioner tied the tender to the earlier decree requiring decommissioning of the Dandora dumpsite. The court held such allegations belong in the former suit, and since breach of the decree was already litigated in the ruling of 9th November 2023, re-raising it is res judicata.

p. 7
04

Violation of right to clean and healthy environment

Holding

No violation or threatened violation was proved as the project had not commenced

Reasoning

The court accepted the Respondent's and Interested Party's position that an EIA would be conducted after contract signature, with public participation at that stage. Since no activity was ongoing on the site, the alleged contravention of Section 58 of EMCA was premature and no declaratory orders could issue.

p. 7

Legal principles established

#
  • The doctrine of exhaustion does not defeat a petition alleging violation of constitutional rights
  • This Court's jurisdiction under Article 162(2)(b) does not extend to reviewing tender awards
  • A constitutional petition is premature where no activity under the impugned decision has commenced and no right is yet threatened

Court orders

#
  1. 1.The petition is struck out
  2. 2.Each party to bear their own costs

Authorities

#

Legislation

  • Constitution of Kenya, 2010Articles 10(2), 22, 23, 42, 43, 47, 48, 50, 69, 70(1), 162(2)(b), 165(3)(b), 258, 259
  • Environment Management and Co-ordination Act (EMCA)Sections 3 and 58
  • Public Private Partnership Act, 2021Sections 32, 64, 65, 75 (including 75(4) and 75(8))
  • Fair Administration Action ActSection 9(2)

Cases cited (5)

  • Consumer Federation of Kenya & Another vs Cabinet Secretary, Ministry of Transport Infrastructure, Housing, Urban Development and Public Works
    Pet. No. 213 of 2022 as consolidated with Pet No. 218 of 2022
  • Okiya Omtata Okoiti & Another vs. Kenya Power & Lighting Company Ltd. & 4 Others
    (2023) eKLR
  • Anthony Mumio & others vs. Attorney General and Others
    (2021) eKLR
  • Abidha Nicholas vs Attorney General & 5 Others
    (2022) eKLR
  • Nairobi ELC Constitutional Petition No. 43 of 2019
Jurisdiction invoked
Articles 165(3)(b), 22 and 23 of the Constitution as pleaded by the Petitioner; the court found jurisdiction ousted on the tender issue and proceeded under Article 162(2)(b)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Mbae v Nairobi City County Government (Environment & Land Petition 4 of 2023) [2024] KEELC 3472 (KLR)", Case Analysis (2024). Petition (Nairobi), dated 1st September 2023. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2024/3472/eng@2024-04-24