Skip to content
AI-generated case briefs sourced from Kenya Law · Not legal advice
AI-generated case brief
Case Brief · caselaw.co.ke
ELCPartially AllowedELC Case of 2015 (Nairobi)· [2024] KEELC 3450 (KLR)

Kariuki v Tofina Rom Builders Ltd & 2 others (Environment & Land Case 334 of 2015) [2024] KEELC 3450 (KLR)

Environment and Land Court
24 April 2024
5,515 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~22 min to read original · ~4 min brief

The bottom line

#

A Nairobi court refunded a homebuyer KShs 8.7M but refused to force transfer of the apartment, because he declined to pay agreed extra construction costs.

What this practically means

#

Executive summary

#
The Plaintiff sued the 1st and 2nd Defendants (developer and registered landowner) and the 3rd Defendant (subsequent purchaser) arising from a Project Development Agreement dated 13th October 2010 under which he contributed Kshs 8.7 Million for a 3-bedroomed apartment (Unit C5) in a 30-unit project on L.R No. 209/3091. He alleged that the developer unilaterally increased the units from 30 to 40, raised his unit's cost by Kshs 2.6 Million with punitive interest, terminated the agreement without proper notice, and sold the unit to the 3rd Defendant. He sought declarations, injunctions, specific performance, an alternative apartment, or alternatively a refund with interest, lost rent and damages. The Defendants admitted the agreement but maintained the Plaintiff was bound to top up additional development costs under clause 3(b) and that clause 8 permitted termination for non-payment. The court found the facts largely undisputed: the agreement, the full payment of Kshs 8.7 Million, and the notice of increased costs. It held that clause 3(b) required only notification, not consultation; the Plaintiff was notified but refused to pay; and he bore the burden of proving the increment was caused by the added units, which he failed to discharge. The contract was lawfully terminated, so specific performance and prayers (a) to (g) failed; the unit having been sold to a third party. Prayers (i) and (j) also collapsed because the Plaintiff voluntarily executed the contract. The court granted the alternative prayer: refund of Kshs 8.7 Million with court-rate interest from the termination notice date, with half-costs awarded given the rejected settlement offers. Judgment delivered at Nairobi on 24th April 2024.

Key legal issues

#
01

Whether the increase in project costs was in breach of the agreement

Holding

No breach: clause 3(b) obliged the developer only to notify the client of increased development costs, and the client to increase his contribution; notice was given by email in June 2014

Reasoning

The court found a plain reading of clause 3(b) imposed no obligation to consult the Plaintiff, only to notify. Schedule A stated the costs were estimates likely to vary. The Plaintiff admitted being notified in writing of the top-up but refused to pay. The court could not rewrite the contract, and no coercion or misrepresentation was proved. The burden lay on the Plaintiff to prove the increase was caused by the added units, which he failed to discharge.

p. 8
02

Whether the contract was lawfully terminated and the unit lawfully sold

Holding

Yes; termination was lawful under clause 8 for the Plaintiff's failure to pay additional costs, so specific performance and the injunctions could not issue

Reasoning

The Plaintiff had paid Kshs 8.7 Million but refused to top up the additional costs as the agreement required. Clause 8 permitted termination for delayed payment. The unit was sold to the 3rd Defendant and was no longer available, making specific performance inequitable. The court applied the principle that a claimant seeking specific performance must have performed all essential terms.

p. 9
03

What remedy survives where specific performance fails

Holding

The alternative prayer for refund of the Kshs 8.7 Million purchase price with court-rate interest from the termination notice date was granted, but lost-rent and damages prayers collapsed

Reasoning

Because the 1st and 2nd Defendants received the sum of Kshs 8.7M, the court granted the alternative prayer for refund with interest from the notice to terminate. The Plaintiff voluntarily executed the impugned contract, so claims for lost rent and damages for breach failed. Half-costs were awarded reflecting the Defendants' earlier settlement offers which the Plaintiff rejected.

p. 9

Legal principles established

#
  • A court of law cannot rewrite a contract between the parties; parties are bound by the terms of their contract unless coercion, fraud or undue influence are pleaded and proved
  • A plaintiff seeking specific performance must show that he has performed all the essential terms of the contract he undertook to perform
  • The terms of a contract reduced to writing can only be proved by the document itself or admissible secondary evidence under section 97(1) of the Evidence Act

Court orders

#
  1. 1.Prayers (a) to (g) of the further amended plaint dated 20th July 2022 dismissed
  2. 2.1st and 2nd Defendants jointly to refund the Plaintiff Kshs 8,700,000 with interest at court rates calculable from the date of the notice to terminate (seven days from 17th April 2015) until payment in full
  3. 3.Prayers (i) and (j) dismissed
  4. 4.Plaintiff awarded half costs of the suit against the 1st and 2nd Defendants

Authorities

#

Legislation

  • Evidence ActSection 97(1)

Cases cited (5)

  • National Bank of Kenya Ltd vs. Pipe Plastic Samkolit (K) Ltd
    (2002) 2 E.A. 503, (2011) eKLR
  • Moi University versus Zaippeline & another (Petition 43 of 2018)
    [2022] KESC 29 (KLR) (Civ)
  • Garvey v Richards
    [2011] JMCA Civ 16
  • Industrial & Com Devt Ltd v Mawa Family Company Ltd & another
    [2015] eKLR
  • Gurdev Singh Birdi & Narinder Singh Ghatora as Trustees of Ramgharia Institute of Mombasa V Abubakar Madhbuti
    [1997] eKLR
Jurisdiction invoked
Original civil jurisdiction of the Environment and Land Court over dispute relating to land parcel L.R No. 209/3091

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Kariuki v Tofina Rom Builders Ltd & 2 others (Environment & Land Case 334 of 2015) [2024] KEELC 3450 (KLR)", Case Analysis (2024). ELC Case of 2015 (Nairobi). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2024/3450/eng@2024-04-24

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.