Kariuki v Tofina Rom Builders Ltd & 2 others (Environment & Land Case 334 of 2015) [2024] KEELC 3450 (KLR)
The bottom line
#A Nairobi court refunded a homebuyer KShs 8.7M but refused to force transfer of the apartment, because he declined to pay agreed extra construction costs.
What this practically means
#Executive summary
#Key legal issues
#Whether the increase in project costs was in breach of the agreement
No breach: clause 3(b) obliged the developer only to notify the client of increased development costs, and the client to increase his contribution; notice was given by email in June 2014
The court found a plain reading of clause 3(b) imposed no obligation to consult the Plaintiff, only to notify. Schedule A stated the costs were estimates likely to vary. The Plaintiff admitted being notified in writing of the top-up but refused to pay. The court could not rewrite the contract, and no coercion or misrepresentation was proved. The burden lay on the Plaintiff to prove the increase was caused by the added units, which he failed to discharge.
Whether the contract was lawfully terminated and the unit lawfully sold
Yes; termination was lawful under clause 8 for the Plaintiff's failure to pay additional costs, so specific performance and the injunctions could not issue
The Plaintiff had paid Kshs 8.7 Million but refused to top up the additional costs as the agreement required. Clause 8 permitted termination for delayed payment. The unit was sold to the 3rd Defendant and was no longer available, making specific performance inequitable. The court applied the principle that a claimant seeking specific performance must have performed all essential terms.
What remedy survives where specific performance fails
The alternative prayer for refund of the Kshs 8.7 Million purchase price with court-rate interest from the termination notice date was granted, but lost-rent and damages prayers collapsed
Because the 1st and 2nd Defendants received the sum of Kshs 8.7M, the court granted the alternative prayer for refund with interest from the notice to terminate. The Plaintiff voluntarily executed the impugned contract, so claims for lost rent and damages for breach failed. Half-costs were awarded reflecting the Defendants' earlier settlement offers which the Plaintiff rejected.
Legal principles established
#- A court of law cannot rewrite a contract between the parties; parties are bound by the terms of their contract unless coercion, fraud or undue influence are pleaded and proved
- A plaintiff seeking specific performance must show that he has performed all the essential terms of the contract he undertook to perform
- The terms of a contract reduced to writing can only be proved by the document itself or admissible secondary evidence under section 97(1) of the Evidence Act
Court orders
#- 1.Prayers (a) to (g) of the further amended plaint dated 20th July 2022 dismissed
- 2.1st and 2nd Defendants jointly to refund the Plaintiff Kshs 8,700,000 with interest at court rates calculable from the date of the notice to terminate (seven days from 17th April 2015) until payment in full
- 3.Prayers (i) and (j) dismissed
- 4.Plaintiff awarded half costs of the suit against the 1st and 2nd Defendants
- Jurisdiction invoked
- Original civil jurisdiction of the Environment and Land Court over dispute relating to land parcel L.R No. 209/3091
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Kariuki v Tofina Rom Builders Ltd & 2 others (Environment & Land Case 334 of 2015) [2024] KEELC 3450 (KLR)", Case Analysis (2024). ELC Case of 2015 (Nairobi). Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2024/3450/eng@2024-04-24
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.