Kibira & 3 others v Njorogre & 3 others; Garden Ridgeways Residents Association & another (Interested Parties) (Environment & Land Case E137 of 2023) [2024] KEELC 381 (KLR)
The bottom line
#Nairobi's Environment and Land Court stopped new unapproved constructions on two land parcels and ordered a noise report, but left demolition questions for full trial.
What this practically means
#Executive summary
#Key legal issues
#Whether the ELC has jurisdiction despite statutory alternative dispute resolution mechanisms under EMCA and the Physical and Land Use Planning Act
The preliminary objection fails because the plaintiffs seek enforcement of a determination the 3rd Respondent has already made, a remedy the County Liaison Committee cannot grant.
The court accepted that the Liaison Committee under sections 77 and 78 of the Physical and Land Use Planning Act has defined functions over applications, appeals and enforcement notices. Had those been the issues, it would have downed its tools. But the uncontroverted evidence was that the 3rd Respondent had already determined the structures should be demolished and even marked them, yet failed to act. Compelling the authority to implement its own decision is a judicial function beyond the Committee.
Whether a temporary injunction ought to issue
Yes, in part: the applicants established a prima facie arguable case and irreparable harm warranting an injunction against new constructions only.
Applying Giella v Cassman Brown, the court found a genuine and arguable case and irreparable loss not compensable in damages, relying on the principle that continuous injury cannot be quantified in damages. Photographic evidence that the 3rd Respondent had marked the structures for demolition lent credence to the applicants' case. However, demolition and existing business operations were left for the full hearing.
Legal principles established
#- Where a planning authority has already made a determination (that structures be demolished) and the suit seeks its implementation or enforcement, the ELC rather than the County Liaison Committee is the proper forum, so the doctrine of exhaustion does not oust the court's jurisdiction.
- Continuous injury cannot be adequately compensated by an award of damages, supporting interim injunctive relief.
Court orders
#- 1.An injunction restraining the 1st and 2nd Defendants, their agents, servants, employees, tenants or any person acting on their behalf from carrying out any new construction of unapproved and semi-permanent structures on land parcel LR 15003/88 and LR 15003/90 pending the hearing and determination of the suit.
- 2.The 4th Defendant to prepare, within 30 days, a report on the noise level posed by any activities carried out by the 1st and 2nd Defendants or their agents, employees or tenants, and present it to court within 30 days.
- 3.Costs of the application to abide the hearing of the suit.
- Jurisdiction invoked
- Article 162(2)(b) of the Constitution and section 13 of the Environment and Land Court Act
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Kibira & 3 others v Njorogre & 3 others; Garden Ridgeways Residents Association & another (Interested Parties) (Environment & Land Case E137 of 2023) [2024] KEELC 381 (KLR)", Case Analysis (2024). Not stated in the judgment. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2024/381/eng@2024-01-25
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.