ELCPartially AllowedNot stated in the judgment· [2024] KEELC 381 (KLR)

Kibira & 3 others v Njorogre & 3 others; Garden Ridgeways Residents Association & another (Interested Parties) (Environment & Land Case E137 of 2023) [2024] KEELC 381 (KLR)

Environment and Land Court
25 January 2024
2,509 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~10 min to read original · ~4 min brief

The bottom line

#

Nairobi's Environment and Land Court stopped new unapproved constructions on two land parcels and ordered a noise report, but left demolition questions for full trial.

What this practically means

#

Executive summary

#
The Applicants, neighbours of the 1st and 2nd Respondents, moved the court by Notice of Motion dated 6th April 2023 seeking temporary injunctions to restrain the Respondents from erecting unapproved semi-permanent structures on LR No. 15003/88 and LR No. 15003/90 in Nairobi, from carrying on unlicensed businesses, and an order compelling the 4th Defendant to stop the resulting noise pollution. The applicants alleged the structures were built without approvals and had converted a residential area to commercial use. The 1st and 2nd Respondents denied commercialisation and asserted proprietary rights; the 3rd Respondent filed a preliminary objection contending the court lacked jurisdiction because the Applicants had not exhausted statutory mechanisms under EMCA and the Physical and Land Use Planning Act. The court canvassed the objection and application together on two issues: jurisdiction and merit of the injunction. On jurisdiction, it applied the Supreme Court's decision in Kibos Distillers on exercising jurisdiction strictly according to law, but held that because the 3rd Respondent had already determined the structures should be demolished (evidenced by marking them) and failed to act, the suit sought enforcement of that determination, a remedy beyond the County Liaison Committee; the objection therefore failed. On the injunction, applying Giella v Cassman Brown and the principle that continuous injury cannot be quantified in damages, the court found a genuine and arguable case and irreparable harm, but limited relief: it restrained new constructions pending the hearing and directed the 4th Defendant to prepare a noise-level report within 30 days, with costs of the application to abide the hearing of the suit. The demolition issue was deferred to the full trial.

Key legal issues

#
01

Whether the ELC has jurisdiction despite statutory alternative dispute resolution mechanisms under EMCA and the Physical and Land Use Planning Act

Holding

The preliminary objection fails because the plaintiffs seek enforcement of a determination the 3rd Respondent has already made, a remedy the County Liaison Committee cannot grant.

Reasoning

The court accepted that the Liaison Committee under sections 77 and 78 of the Physical and Land Use Planning Act has defined functions over applications, appeals and enforcement notices. Had those been the issues, it would have downed its tools. But the uncontroverted evidence was that the 3rd Respondent had already determined the structures should be demolished and even marked them, yet failed to act. Compelling the authority to implement its own decision is a judicial function beyond the Committee.

p. 5
02

Whether a temporary injunction ought to issue

Holding

Yes, in part: the applicants established a prima facie arguable case and irreparable harm warranting an injunction against new constructions only.

Reasoning

Applying Giella v Cassman Brown, the court found a genuine and arguable case and irreparable loss not compensable in damages, relying on the principle that continuous injury cannot be quantified in damages. Photographic evidence that the 3rd Respondent had marked the structures for demolition lent credence to the applicants' case. However, demolition and existing business operations were left for the full hearing.

p. 5

Legal principles established

#
  • Where a planning authority has already made a determination (that structures be demolished) and the suit seeks its implementation or enforcement, the ELC rather than the County Liaison Committee is the proper forum, so the doctrine of exhaustion does not oust the court's jurisdiction.
  • Continuous injury cannot be adequately compensated by an award of damages, supporting interim injunctive relief.

Court orders

#
  1. 1.An injunction restraining the 1st and 2nd Defendants, their agents, servants, employees, tenants or any person acting on their behalf from carrying out any new construction of unapproved and semi-permanent structures on land parcel LR 15003/88 and LR 15003/90 pending the hearing and determination of the suit.
  2. 2.The 4th Defendant to prepare, within 30 days, a report on the noise level posed by any activities carried out by the 1st and 2nd Defendants or their agents, employees or tenants, and present it to court within 30 days.
  3. 3.Costs of the application to abide the hearing of the suit.

Authorities

#

Legislation

  • Constitution of Kenya, 2010Articles 162(2)(b), 169, 42, 69, 70
  • Environment and Land Court Actsections 13(1), 13(2), 13(3)
  • Environment Management and Coordination Act (cap 387)sections 31, 32, 33, 129
  • Physical and Land Use Planning Act No. 13 of 2019sections 73, 77, 78, 80, 84
  • Civil Procedure RulesOrder 40 rule 1

Cases cited (6)

  • Giella v Cassman Brown
    [1973] EA
  • Nguruman Limited v Jan Bonde Nielsen & 2 Others
    [2014] eKLR
  • Joshua Sembei Mutua v Attorney General & 2 Others
  • West Kenya Sugar Company Limited v Busia Sugar Industries Ltd & 2 others
    [2017] eKLR
  • Benard Ambuti Andega & 2 Others v Kibos Distillers Ltd and 5 others
    (2020) eKLR
  • Justus Irungu Githae & 12 others v Attorney General & 4 others
    [2016] eKLR
Jurisdiction invoked
Article 162(2)(b) of the Constitution and section 13 of the Environment and Land Court Act

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Kibira & 3 others v Njorogre & 3 others; Garden Ridgeways Residents Association & another (Interested Parties) (Environment & Land Case E137 of 2023) [2024] KEELC 381 (KLR)", Case Analysis (2024). Not stated in the judgment. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2024/381/eng@2024-01-25

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.