Samora Sikalie (Chairman) Suing on behalf of Karen Lang’ata District Association v Nairobi City County Government; Director General Nairobi Metropolitan Services & 3 others (Interested Parties)
The bottom line
#The Environment and Land Court dismissed Karen residents' challenge to a development approval because they skipped the statutory appeal routes before going to court.
What this practically means
#Executive summary
#Key legal issues
#Exhaustion of alternative dispute resolution mechanisms
The doctrine of exhaustion applies; planning and development disputes must come to the ELC as appeals from the Planning Liaison Committee, and NEMA licensing grievances go to the NET
The court adopted its own ruling of 11.5.2023 which had set out the applicable legal framework, holding that the petitioner bypassed statutory mechanisms under PLUPA and EMCA. Citing Speaker of National Assembly v Karume, where alternative dispute resolution mechanisms exist, the constitutional petition route was not available.
Whether there was adequate public participation
Public participation was adequate under Section 58 of PLUPA; the petitioner failed to demonstrate insufficiency
The court noted an advertisement for change of user in the Daily Nation in May 2021, a site signage inviting objections, and public consultation questionnaires in the 4th Interested Party's replying affidavit. The petitioner did not show the participation was insufficient or below PLUPA standards.
Status of the 2017 Recognition Agreement vis-à-vis PLUPA 2019
The court declined to interrogate the decision in Nairobi ELC Petition No. 40 of 2018, being a decision of a court of equal jurisdiction, but observed the agreement predates PLUPA 2019
The court observed that the recognition agreement was made in 2017, before commencement of PLUPA 2019 and the Physical and Land Use Planning (Liaison Committees) Regulations 2021 which set out the statutory framework for approval of developments, implying the agreement's framework was superseded.
Legal principles established
#- Matters relating to planning and development approvals must first be brought as appeals from the relevant Planning Liaison Committee - the doctrine of exhaustion of remedies applies
- A party aggrieved by a NEMA licensing decision must appeal to the National Environmental Tribunal under section 129 of EMCA
- A court should not delve into an analysis of a decision of a court of equal and coordinate jurisdiction
Court orders
#- 1.The petition is dismissed
- 2.Each party shall bear their own costs of the suit
- Jurisdiction invoked
- Article 165(2) of the Constitution - Environment and Land Court jurisdiction (petition filed under the Constitution); exhaustion doctrine applied
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Samora Sikalie (Chairman) Suing on behalf of Karen Lang’ata District Association v Nairobi City County Government; Director General Nairobi Metropolitan Services & 3 others (Interested Parties)", Case Analysis (2023). Environment & Land Petition E027 of 2022. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/21882/eng@2023-11-21
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.