#A Nairobi court found a petroleum company and its two directors guilty of ignoring a court order halting construction, though sentencing awaits mitigation.
What this practically means
#Executive summary
#Key legal issues
#Whether the respondents and named contemnors were in contempt of the status quo order of 24th April 2023
The court found the 2nd Respondent and the two named directors in contempt, all four elements of civil contempt having been proved
The order was clear, unambiguous and binding; counsel for the contemnors was present when it was made and service was effected on the site; time-stamped photographs with a certificate showed workers continuing construction; the activity, though minimal, was a deliberate breach. The directors did not deny the workers acted under their directions.
The legal framework and standard for civil contempt
Civil contempt requires proof to a standard higher than civil cases of four elements: clear order, knowledge/notice, breach, and deliberateness
The court applied Section 5 of the Judicature Act incorporating English contempt law, specifically Part 81 of the Civil Procedure (Amendment No 3) Rules 2020, and adopted the four-element test from Cecil Miller and North Tetu Farmers, citing 'Contempt in Modern New Zealand'.
Legal principles established
#- Knowledge of a court order by a contemnor's advocate suffices for contempt proceedings where the order was made in the advocate's presence
- A company acts through its directors, who may be cited for contempt of orders breached by the company
- Courts punish contempt to safeguard the rule of law, not the integrity of the judiciary
Court orders
#- 1.A declaration that Maar Petroleum Limited, Yusuf Abdi Hussein and Omar Ibrahim Abdi are in contempt of the Order of 24th April 2023 by proceeding with construction works on LR No. 1870/111/71 Westlands Sub-County, Nairobi County
- 2.The two named contemnors, Yusuf Abdi Hussein and Omar Ibrahim Abdi, to mitigate before sentence is meted out
- 3.The two named contemnors, Yusuf Abdi Hussein and Omar Ibrahim Abdi, to pay the costs of the application
- Jurisdiction invoked
- Inherent contempt jurisdiction; Section 29 of the Environment and Land Court Act and Section 5 of the Judicature Act
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Mathu & 2 others (All Jointly Suing as and on Behalf of Kyuna Neighbours Association) & another v National Environment Management Authority & 4 others; Director General, Nairobi Metropolitan Services (Interested Party)", Case Analysis (2023). Environment and Land Appeal E075 of 2022. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/21318/eng@2023-11-02
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.