Lamba & another v Pearls Kids Academy Limited & another; Nairobi County Government & another (Interested Parties)
The bottom line
#A Nairobi court stopped a school from operating because its owners lacked proper change-of-user and environmental impact assessment approvals.
What this practically means
#Executive summary
#Key legal issues
#Whether the plaintiffs established a prima facie case for a temporary injunction
Yes - the absence of a change of user application for a school and of an EIA licence demonstrated a prima facie case
The defendants' 2015 change of user approval was for commercial offices and shops, not a school, and no application for change of user to put up a school existed. The intended land use was out of character with the residential surroundings, requiring an EIA under the second schedule of EMCA, but no EIA licence was annexed. These omissions evidenced non-compliance with planning regulations and grounded a prima facie case.
Whether the school being already operational defeats the injunction
No - the applicants acted promptly and had already obtained temporary orders on 13 March 2023 restraining admissions
The defendants argued the application was overtaken by events since the school was up and running. The court rejected this, noting the applicants came to court as soon as they saw the enrolment advertisements and obtained temporary orders on 13 March 2023 requiring the defendants to stop admissions, so delay was not a bar.
Legal principles established
#- A change of user approval for a purpose other than that actually intended (commercial offices and shops rather than a school) does not constitute compliance with planning regulations
- An activity out of character with its surroundings or involving a change in land use requires an environmental impact assessment under EMCA
- Possession of county and Ministry of Education approvals does not excuse non-compliance with land use and physical planning regulations
Court orders
#- 1.Pending compliance with the EIA and Change of User Regulations and or hearing and determination of the suit (whichever is earlier), a temporary injunction restraining the 1st and 2nd defendants, their agents, servants, employees or any person acting under their authority from operationalizing, running and/or in any other way carrying on the business of a school known as Pearls Kids Academy on LR.No.1870/X/84 situated in Westlands, Sports Road
- 2.Costs of the application to the Applicants
- Jurisdiction invoked
- Environment and Land Court jurisdiction under the Environment and Land Court Act; motion brought under Order 40 and 51 of the Civil Procedure Rules, sections 3A and 63(e) Civil Procedure Act and sections 45, 46, 56-57 and 72 of the Physical Land Use and Planning Act
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Lamba & another v Pearls Kids Academy Limited & another; Nairobi County Government & another (Interested Parties)", Case Analysis (2023). Environment & Land Case E078 of 2023. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/20964/eng@2023-10-26
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.