AI-generated case brief
Case Brief · caselaw.co.ke
ELCPartially AllowedEnvironment & Land Case E245 of 2022· [2023] KEELC 19939 (KLR)

Shisanya & another v National Olympic Committee of Kenya & 3 others; Tysons Limited (Interested Party)

Environment and Land Court of Kenya
21 September 2023
11,287 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~45 min to read original · ~4 min brief

The bottom line

#

Kenya's Environment and Land Court ordered the Sports Fund to refund KES 4.6 million for a failed office purchase, with interest from 2015.

What this practically means

#

Executive summary

#
The Plaintiffs contracted in 2012 to purchase office space in Nock Plaza (L.R No 209/12386) from the National Olympic Committee of Kenya (1st Defendant) and paid a deposit of Kes.4,612,000/- in two installments. The sale collapsed and the deposit was never refunded. The property was later taken over by the Fund Administrator, Sports, Art and Social Development Fund (3rd Defendant) under a sale agreement dated 1st September 2020 (a duplicate dated 9th September 2020), under which the 3rd Defendant undertook to settle all claims and liabilities attaching to the property. The Plaintiffs sued for refund, interest, and general damages for breach of contract. The court framed four issues. On the first, it found payment proved, acknowledged by receipts and correspondence, admitted by NOCK's witness, and never refunded. On the second, it held that under clauses 1.1(d), 3.1 and 3.2 of the takeover agreement, the 3rd Defendant undertook to liquidate all liabilities, including the refund, and could not renege; the privity objection raised by the 3rd and 4th Defendants was distinguished on the basis that a contract conferring legitimate interests on a third party is enforceable by that party. On damages, the court held general damages are not awardable for breach of contract, following Dharamshi v Karsan, Securicor and KTDC v Sundowner Lodge. On interest, it awarded court rates (14%) but only from January 2015, when the two-year completion period in the letter of offer lapsed, rejecting the claim from December 2012. Judgment was entered against the 3rd Defendant for Kes.4,612,000/- with interest; claims against the 1st, 2nd and 4th Defendants and for general damages were dismissed, with costs awarded against the 3rd Defendant.

Key legal issues

#
01

Proof of payment and non-refund of the deposit

Holding

The payment of Kes.4,612,000/- was proved, acknowledged by receipts and correspondence, and never refunded; the debt was admitted by DW1 and not disputed

Reasoning

PW1 and PW2 testified to execution of letters of offer and payment of the 20% deposit, evidenced by Exhibits P1, P5, P6, P7 and P8. DW1 admitted in cross-examination that the debt was acknowledged and that the Plaintiffs were owed the money. The sale having aborted, the deposit remained due and outstanding.

p. 12
02

Liability for the refund as between the 1st and 3rd Defendants; effect of the 1st–3rd Defendants' sale agreement

Holding

The 3rd Defendant, having taken over the suit property and undertaken under clauses 1.1(d), 3.1 and 3.2 to settle all claims and liabilities attaching to it, is solely liable for the refund

Reasoning

The sale agreement expressly defined the purchase price to include all liabilities and debts attached to the property, and the 3rd Defendant undertook to settle established liquidated claims. DW2 admitted the asset and liabilities were taken over and that the Plaintiffs' claim was forwarded to and accepted by the 3rd Defendant. The court read the agreement within its four corners and held the 3rd Defendant bound.

p. 15
03

Privity of contract objection by the 3rd and 4th Defendants

Holding

The privity doctrine is distinguished; the sale agreement conferred enforceable interests on third parties with proven claims, including the Plaintiffs

Reasoning

Relying on Savings & Loan (K) Ltd v Kanyenje Karangaita Gakombe, the court noted recognised exceptions to privity, including collateral contracts conferring benefits on third parties. Although the 3rd Defendant was not party to the Plaintiffs' contract, it threw itself into the mix by the 1st September 2020 sale agreement whose terms were intended to affect the rights and liabilities of third parties including the Plaintiffs.

p. 18
04

Entitlement to general damages for breach of contract

Holding

Not entitled; general damages are not awardable for breach of contract

Reasoning

The claim was not canvassed in submissions. Citing Dharamshi v Karsan, Securicor Courier (K) Ltd and Kenya Tourist Development Corporation v Sundowner Lodge Ltd, the court reaffirmed that general damages are not recoverable for breach of contract and that only quantified, specially pleaded and proved damages are awardable.

p. 19
05

Entitlement to interest and period of computation

Holding

Interest at court rates (14%) is payable but only from January 2015, being the lapse of the two-year completion period in clause 12 of the letter of offer, not from December 2012

Reasoning

The deposit was paid in two installments (December 2012 and early 2013), so there was no basis for interest from 12th December 2012. The letter of offer contemplated completion within two years. Following Highway Furniture Mart Ltd v Permanent Secretary Office of the President, interest compensates for deprivation of money, and computation properly begins when the obligation to hand over crystallised.

p. 20
06

Liability of the Attorney General

Holding

The suit against the 4th Defendant was dismissed for disclosing no reasonable cause of action

Reasoning

The 3rd Defendant is a body corporate under the Sports Act, 2013; the Plaintiffs did not demonstrate why the Attorney General was impleaded.

p. 21

Legal principles established

#
  • General damages are not recoverable for breach of contract; only specially pleaded and specifically proved special/liquidated damages are awardable
  • A vendor who by a subsequent agreement undertakes to settle all claims and liabilities attaching to the property assumes liability for refunds owed to third-party depositors, whose interests the contract confers
  • Courts cannot rewrite contracts freely entered into; parties are bound by the terms of their contract
  • Extrinsic evidence is inadmissible to contradict or vary the terms of a written agreement (four corners rule)
  • Interest on a refunded principal compensates for deprivation of money, but may be computed from the date the entitlement crystallised rather than the date of payment

Court orders

#
  1. 1.The Plaintiffs shall be refunded the sum of Kes.4,612,000/- by the 3rd Defendant
  2. 2.The refund shall attract interest at court rates (14%) w.e.f January 2015 to date of payment in full
  3. 3.The Plaintiffs' claim against the 1st and 2nd Defendants is dismissed
  4. 4.The Plaintiffs' claim against the 4th Defendant is dismissed
  5. 5.The Plaintiffs awarded costs of the suit to be borne by the 3rd Defendant, to be agreed and in default taxed
  6. 6.The claim for General damages for breach of contract is dismissed
  7. 7.Any other relief not expressly granted is declined

Authorities

#

Legislation

  • Law of Contract Act, Chapter 23 Laws of KenyaSection 3(3)
  • Evidence Act, Chapter 80, Laws of KenyaSections 97 and 98
  • Sports Act, 2013corporation of the 3rd Defendant
  • Contracts (Rights of Third Parties) Act, 1999 (UK)
  • Contract (Rights of Third Parties) Act, 2001 (Singapore)

Cases cited (27)

  • Muriungi Kanoru Jeremiah versus Stephen Ungu Mwarambua
    (2015) eKLR
  • Swalleh C Kariuki & Another versus Violet Owisi Okuyu
    (2021) eKLR
  • Nyamunyu versus Nyagah
    (1983) KLR
  • Ayub Ndungu versus Marion Waithera Gicheru
    (2006) eKLR
  • Kimakia Cooperative Society versus Green Hotel
    (1988) KLR

    Whether general damages are awardable for breach of contract

  • Consolata Anyango Ouma versus South Nyanza Sugar Co Ltd
    (2015) eKLR
  • Gami Properties Ltd versus National Social Security Fund Board of Trustees & 2 Others
    (2018) eKLR
  • Housing Company of East Africa Ltd versus Board of Trustees National Social Security Fund
    (2018) eKLR
  • Millicent Perpetua Atieno Wandiga & Another versus John Chege
    (2013) eKLR
  • Dharamshi versus Karsan
    (1974) EA 41

    General damages not allowable in addition to quantified damages; would amount to duplication

  • Postal Corporation of Kenya versus Geral Kamondo Njuke T/a Geka General Supplies
    (2021) eKLR
  • Kenya Industrial Estate Ltd versus Lee Enterprises Ltd
    (2009) eKLR
  • Kenya Breweries Ltd versus Natex Distributors Ltd
    (2004) eKLR
  • Standard Chartered Ltd versus Intercom Services Ltd & Others
    (2004) eKLR
  • National Bank of Kenya Ltd versus Pipeplastic Samkolit (K) Ltd & Another
    (2001) eKLR

    A court cannot rewrite a contract; parties are bound by their terms

  • Agricultural Finance Corporation versus Lengetia Ltd & Another
    (1985) eKLR

    Relevance and significance of the doctrine of privity of contract

  • Pius Kimaiyo Langat versus Cooperative Bank Ltd
    (2017) eKLR

    Parties are bound by contract terms; courts do not rewrite contracts

  • Speaker of the County Assembly - Kisii County & 2 others versus James Omariba Nyaoga
    [2015] eKLR

    Extrinsic evidence inadmissible to vary written documents; Sections 97 and 98 Evidence Act

  • John Onyancha Zurwe v Oreti Atinda alias Olethi Atinda
    Kisumu Civil Appeal No. 217 of 2003 (UR)

    Adoption of Halsbury's on exclusion of extrinsic evidence

  • Savings & Loan (K) Limited versus Kanyenje Karangaita Gakombe & another
    [2015] eKLR

    Exceptions to privity of contract; contracts conferring benefits on third parties

  • Shanklin Pier V Detel Products LTD
    [1951] 2 KB 854

    Collateral contract exception to privity

  • Darlington Bourough Council V Witshire Northern LTD
    [1995] 1 WLR 68

    Lord Steyn on enforcing contracts for the benefit of third parties

  • Securicor Courier (K) Ltd. vs. Benson David Onyango & another
    [2008] eKLR

    General damages are not awardable for breach of contract

  • Kenya Tourist Development Corporation versus Sundowner Lodge Limited
    [2018] eKLR

    Settled position that general damages are not recoverable for breach of contract

  • Highway Furniture Mart Limited versus Permanent Secretary Office of The President & another
    [2006] eKLR

    Justification for award of interest - compensation for deprivation of money

  • Later v Mbiyu
    [1965] EA 592

    Party deprived of money by defendant's wrongful act should be compensated by interest

  • Lwanga v Centenary Rural Development Bank
    [1999] 1 EA 175

    Supporting authority on award of interest

Jurisdiction invoked
Original civil jurisdiction of the Environment and Land Court over a dispute relating to L.R No 209/12386 (Nock Plaza), Nairobi

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Shisanya & another v National Olympic Committee of Kenya & 3 others; Tysons Limited (Interested Party)", Case Analysis (2023). Environment & Land Case E245 of 2022. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/19939/eng@2023-09-21

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.