The bottom line

#

A Nairobi court ruled a land buyer who never paid the balance lost the property, keeping only his deposit refund.

What this practically means

#

Executive summary

#
The plaintiff, registered owner of LR No.13114/59 (a subdivision of LR No.13114/3, Langata), sued for possession, injunction, declarations, damages for trespass and demolition of structures, alleging the defendant breached a sale agreement dated December 9, 2005 for Ksh.5,900,000 by failing to pay the balance beyond the 10% deposit. The defendant counterclaimed for specific performance, damages of Ksh.35,000,000 and a permanent injunction, contending the plaintiff breached by failing to complete subdivision and effect transfer within the 180-day completion period. The court framed four issues: rescission, the plaintiff's prayers, the counterclaim, and costs. It held the defendant breached the agreement by failing to pay the balance, stamp duty and outgoings, and by refusing to issue a professional undertaking, demanding transfer before payment contrary to clause 11. The subdivision delay was beyond the plaintiff's control, and the defendant had remedies of requiring completion or termination which he never invoked. Correspondence the defendant sought to shield as without prejudice was relied upon, the court finding it was not genuinely settlement communication. The plaintiff was entitled to rescind; the defendant's counterclaim for specific performance failed, he being entitled only to a refund of the deposit. The defendant was not a trespasser since entry was with permission, so damages for trespass and unjust enrichment were refused, but the unapproved incomplete structures were ordered demolished within 120 days. Judgment entered for the plaintiff with a permanent injunction, declarations of discharge of the agreement and beneficial ownership, demolition order, costs and interest.

Key legal issues

#
01

Who breached the sale agreement

Holding

The defendant breached by failing to pay the balance of the purchase price, stamp duty and outgoings, and by refusing to issue a professional undertaking

Reasoning

The agreement required payment of the balance by the 180-day completion date, or transfer against a professional undertaking. The defendant paid only 10%, admitted non-payment of the balance, stamp duty and outgoings, and demanded transfer before payment, going beyond the contract terms. The subdivision delay was beyond the plaintiff's control and the defendant had remedies of completion or termination which he never invoked.

p. 11
02

Whether the plaintiff was entitled to rescind the agreement

Holding

Yes; the plaintiff validly repudiated/rescinded the agreement after the defendant's persistent breach

Reasoning

The plaintiff, though delayed by subdivision, granted the defendant possession and sought payment or an undertaking. The defendant refused payment, rejected a joint account proposal and refused refund of the deposit with vacant possession. Following Kihuba Holdings, a purchaser who fails to pay the balance cannot complain; the plaintiff was entitled to rescind and reclaim possession.

03

Whether the defendant's counterclaim for specific performance succeeds

Holding

No; dismissed save for refund of the 10% deposit

Reasoning

Specific performance is discretionary and unavailable where the claimant is himself in breach and an adequate alternative remedy exists. The defendant never paid the balance nor issued an undertaking, and the agreement had been validly rescinded. He is entitled only to a refund of the deposit.

04

Whether the defendant was a trespasser and liable for damages

Holding

No; entry and construction were with the plaintiff's permission, so no damages for trespass or unjust enrichment

Reasoning

The plaintiff voluntarily granted possession before payment of the balance, so the defendant was not a trespasser. The court found no intention to unjustly enrich himself; stamp duty, rent and rates remain payable by the plaintiff since title never passed. However, the unapproved incomplete structures must be demolished.

p. 13

Legal principles established

#
  • A court cannot rewrite a contract between parties; parties are bound by its terms unless coercion, fraud or undue influence are pleaded and proved
  • Specific performance is a discretionary equitable remedy not granted where the contract is defective or an adequate alternative remedy exists
  • Correspondence exchanged in a genuine attempt to settle a dispute is without prejudice, but a party cannot shield contractual performance communications behind that label

Court orders

#
  1. 1.A permanent injunction restraining the defendant by himself and/or his servants and agents from interfering with the plaintiff's possession of the suit property
  2. 2.A declaration that the sale agreement stands discharged and parties are released from performance of the same
  3. 3.A declaration that the plaintiff is the true and beneficial owner of the suit property
  4. 4.An order directing the defendant to demolish all incomplete structures on the suit property within 120 days, in default the plaintiff to demolish at the defendant's expense
  5. 5.Costs of the suit and interest to the plaintiff

Authorities

#

Legislation

  • Evidence ActSection 107
  • Civil Procedure ActSection 27(1)
  • Physical Planning ActSections 30 and 33

Cases cited (12)

  • Fidelity Commercial Bank Limited v Kenya Vehicle Industries Limited
    (2017) eKLR

    Courts cannot rewrite contracts; parties bound by express terms

  • National Bank of Kenya Ltd v Pipeplastic Samkolit (K) Ltd
    (2002) 2 EA 503

    A court of law cannot rewrite a contract between parties absent coercion, fraud or undue influence

  • Lalji Rabadia & Others v Commercial Bank of Africa
    (2015) eKLR

    Court has no power to rewrite a contract for the parties

  • Trollope Colls Ltd v North West Metropolitan Regional Hospital Board
    (1973) 1 WLR 601

    Parties bound by their bargain; courts cannot rewrite contracts

  • Parminder Singh Sagoo & Another v Nevillee Anthony Dourado & another
    (1983) eKLR

    A party cannot seek to rewrite the agreement

  • Kenya Airways Limited v Satwant Singh Flora
    (2013) eKLR

    A party cannot benefit from his illegal acts

  • Santowels Limited v Stanbic Bank (K) Limited
    Civil Appeal 160 of 2018 (2022) KECA 545 (KLR)

    Burden of proof on a party alleging facts

  • Dhanjal Investments Ltd v Shabaha Investments Ltd
    (2022) KECA 366 (KLR)

    Legal significance of time being of the essence; consequences of fundamental breach

  • Kukal Properties Development Ltd v Tafazzal H. Maloo & 3 Others
    (1993) eKLR

    Course of action on breach of condition that time is of the essence

  • Johnson v Agnew
    (1979) 1 All ER 883

    Law on termination and specific performance after breach

  • Kihuba Holdings Limited v Charo Karisa Ngulu
    [2021] eKLR

    Purchaser who fails to pay balance cannot complain; refund of deposit is the remedy

  • Reliable Electrical Engineers Ltd v Mantrac Kenya Ltd
    (2006) eKLR

    Specific performance is discretionary and refused where adequate alternative remedy exists

Jurisdiction invoked
Original civil jurisdiction of the Environment and Land Court over disputes relating to land (Article 162(2)(b) Constitution / ELC Act)

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Lakhani v Waweru", Case Analysis (2023). Environment & Land Case 686 of 2011. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/19299/eng@2023-07-26

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.