Cannon Aluminium Fabricators Ltd v Wendano Matuu Co Ltd
The bottom line
#A Kenyan court ruled that transferring disputed land mid-case doesn't shield you from paying the other side's legal costs.
What this practically means
#Executive summary
#Key legal issues
#Whether the plaintiff is entitled to the costs of the suit notwithstanding the defendant's transfer of the suit property during the pendency of the suit
The plaintiff was awarded costs because it had already undertaken substantial steps in the litigation, including filing pleadings and making several court appearances, which the court could not disregard.
The court applied section 27 of the Civil Procedure Act and the principle that costs follow the event, tempered by judicial discretion. Although the defendant transferred the suit property while the suit was pending and claimed to have acted in good faith, the plaintiff had filed a plaint, an interlocutory application, a reply to defence and defence to counter-claim, and attended several court appearances. In the interest of justice, that effort justified an award of costs.
Legal principles established
#- Costs of and incidental to all suits are in the discretion of the court, which must be exercised judicially and in accordance with reason and justice.
- Costs follow the event but there is no one-size-fits-all rule; the discretion depends on the circumstances of each case.
Court orders
#- 1.The plaintiff is awarded the costs of the suit, subject to taxation by the Taxing Officer
- Jurisdiction invoked
- Section 27 of the Civil Procedure Act (discretion as to costs)
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Cannon Aluminium Fabricators Ltd v Wendano Matuu Co Ltd", Case Analysis (2023). Environment & Land Case 455 of 2017. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/19180/eng@2023-07-25