Tonini Holdings Limited v Kenya Urban Roads Authority & another
The bottom line
#A landowner whose property was taken for the Northern Bypass won over KES 110 million in delayed compensation and development costs from the State.
What this practically means
#Executive summary
#Key legal issues
#Entitlement to interest for delayed payment of the compensation award
The plaintiff is entitled to interest as claimed since possession was taken before payment and the 251-day delay was not controverted
Section 16(1) of the repealed Land Acquisition Act provides that where possession is taken before payment of the award, interest at not less than 6% per annum accrues from taking of possession until payment in full. The 1st defendant did not deny taking possession before payment, and the 251-day delay was uncontroverted. The plaintiff's advocate had raised the claim by letter dated 12.06.2013 which was not honoured.
Whether the costs of the proposed USIU hostels development were compensable
The expenses incurred in preparation for the hostels development ought to have been considered in the award
The Schedule to the repealed Land Acquisition Act lists matters to be considered in assessing compensation, including market value and injurious affection of other property and earnings. The plaintiff's evidence of the consultancy agreement and approvals was unrebutted, and the approvals predated the notices of intended acquisition. Compensation follows the principle of equivalence, so losses fairly attributed to the taking must be paid.
Legal principles established
#- Where an acquiring entity takes possession before full payment of compensation, interest at not less than 6% per annum accrues from the time possession was taken until payment in full
- Where a statute prescribes a manner of doing a thing, it must be done in that manner and no other
- Compensation for compulsory acquisition is quantified on the principle of equivalence - losses fairly attributed to the taking, no more
- Expenses incurred in preparation for a development on land compulsorily acquired ought to have been considered in the award
Court orders
#- 1.Judgment for the plaintiff against the defendants jointly and severally for Kshs 4,610,064
- 2.Judgment for the plaintiff against the defendants jointly and severally for Kshs 105,463,367
- 3.Interest on Kshs 4,610,064 at court rates from 27.3.2012 until payment in full
- 4.Interest on Kshs 105,463,367 at court rates from the date of judgment until payment in full
- 5.Each party to bear their own costs of the suit
- Jurisdiction invoked
- Original civil jurisdiction of the Environment and Land Court over compulsory acquisition of land and compensation
Key timeline
#Practical implications
#Frequently asked questions
#Later judgments citing this (1)
#Judgments in the corpus that rely on this one. Where the Court said how it treated the authority, that is shown.
- Kipsiro & another v County Government of Uasin Gishu (Environment & Land Case 42 of 2022) [2025] KEELC 151 (KLR)[2025] KEELC 151 (KLR)22 Jan 2025
Cite this brief
#Cite this brief
Caselaw, "Tonini Holdings Limited v Kenya Urban Roads Authority & another", Case Analysis (2023). Environment & Land Case 005 of 2022. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2023/18975/eng@2023-07-25
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.